Bar Charts (Gantt Charts),Resource Histograms, andS-CurvesDr. Mohammad S. El-MashalehDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh1Bar charts (Gantt charts) Like we said before, bar charts are theoldest scheduling technique Found by Henry GanttDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh21

Consists of horizontal bars and a timescale Each bar represents an activity, with thebar length represents its durationDept. of Civil Eng.Hashemite University Construction Project ManagementDr. Mohammad El-Mashaleh3In addition to the activity bars and the time scale,most bar charts contain data in columnsInformation may include: durations, resources, costs,other (customized)Note that activities in this bar chart example areordered in their ESDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh42

Advantages of bar charts Easily constructed for small or simple projects Reviewers of the bar chart do not need anyspecial knowledge to understand: The status of the project What is expected to be accomplished in thenext few time periods When the project is expected to endDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh5 Disadvantages: Do not typically show logic (logic is notobvious) For example, determine the dependency ofF&EDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh63

Example 1Dept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh7Histograms and s-curves Histograms are period representation ofresource needs or use S-curves (cumulative curves) show the sameinformation on an accumulated basis Resources that are usually shown inhistograms and s-curves include: number oflabor, labor hours, dollarsDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh84

Bar chart and histogramAlthough resourcesneed not beallocated uniformlythroughout theduration of anactivity, thedemonstration hereis based on uniformdistributions ofresourcesDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh9S-CurveDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh105

Histogram use The histogram helps us to identify periods whenresources are being used “ineffectively” For example, based on the above histogram, we canidentify periods of “low-resource” use and periods of“high-resource” useDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh11 The next step for us is to use “resource allocation” or“resource leveling” techniques to improve our resourcehistogram One common technique is called the Minimum MomentAlgorithm ApproachDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh126

S-curve use Used to predict number or size ofresources over the life of the project Also used to compare planned(budgeted) resources with actual onesDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh13 Plotting both s-curves is used to control,make comparisons, and prepare betterforecasts in the futureDept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh147

Examples 2 & 3Dept. of Civil Eng.Hashemite UniversityConstruction Project ManagementDr. Mohammad El-Mashaleh158

Bar Charts (Gantt Charts), Resource Histograms, and S-Curves Dr. Mohammad S. El-Mashaleh Dept. of Civil Eng. Hashemite University Construction Project Management Dr. Mohammad El-Mashaleh 2 Bar charts (Gantt charts) Like we said before, bar charts are

Related Documents:

gantt chart. The gantt chart diagram can contain bar objects that are used for scheduling. Each row of the gantt chart does have a row of the tree grid. To identify the most elements of the gantt chart please see the following list: 4 The gantt chart area, also called (gantt) table. Elements of the gantt chart like

The GANTT procedure produces a Gantt chart that is a graphical scheduling tool for the planning and control of a project. In its most basic form, a Gantt chart is a bar chart that plots the tasks of a project versus time. PROC GANTT displays a Gantt chart correspondi

The GANTT procedure produces a Gantt chart, which is a graphical scheduling tool for the planning and control of a project. In its most basic form, a Gantt chart is a bar chart that plots the tasks of a project versus time. PROC GANTT displays a Gantt chart

The GANTT procedure produces a Gantt chart that is a graphical scheduling tool for the planning and control of a project. In its most basic form, a Gantt chart is a bar chart that plots the tasks of a project versus time. PROC GANTT displays a Gantt chart corresponding to a project schedule such as that produced by the CPM

Best Practice Tips for Gantt Chart Visualization 6 PLEASE SHARE THIS EBOOK! 2. Visualize Resource Bottlenecks in Gantt Chart Row Gantt charts are frequently used to visualize and manage resource utilization and capacity load in production scheduling applications. Ideally, this is achieved by complementing the Gantt diagram with a histogram.

The difference in the level of usage of the term Gantt compared to Gantt Chart reflects Henry Gantt’s importance in the development of management science. The upturn starting in the mid 1980s coincides with the release of Microsoft Project The next charts plots the relative use of the terms Bar Chart and Gantt Chart from the emergence

Implement the Gantt chart in software. Many project managers choose to take all of the information on a Gantt chart and input it into a software environment. For example, the Excel spreadsheet tool can be an effective home for a Gantt chart. Choose appropriate software and digitize the Gantt c

BAB II Landasan Teori Dan Pengembangan Hipotesis A. Teori Agency (Agency Theory) . agent (yangmenerima kontrak dan mengelola dana principal) mempunyai kepentingan yang saling bertentangan.3 Aplikasi agency theory dapat terwujud dalam kontrak kerja yang akan mengatur proporsi hak dan kewajiban masing-masing pihak dengan tetap memperhitungkan kemanfaatan secara keseluruhan.4 Teori agensi .