August 2016 Monthly Progress Report - Caltrain

2y ago
16 Views
2 Downloads
1.08 MB
60 Pages
Last View : 6d ago
Last Download : 3m ago
Upload by : Dahlia Ryals
Transcription

Modernization ProgramPeninsula Corridor Electrification Project (PCEP)August 2016Monthly Progress ReportAugust 31, 2016Revision 0

Funding PartnersFTA Core CapacityFTA Section 5307/5337 (Environmental / Pre Development only)FTA Section 5307/5337 (EMU only)Prop 1B (Public Transportation Modernization & Improvement Account)Caltrain Low Carbon Transit Operations Cap and TradeProp 1AHigh Speed Rail Cap and TradeCarl Moyer FundRM2RM1Bridge TollsSFCTASan Mateo (SMCTA) ContributionSMCTA Measure AVTA Measure ASanta Clara (VTA) ContributionSan Francisco Contribution

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress ReportTable of ContentsPage1.0BACKGROUND . 1-12.0EXECUTIVE SUMMARY . 2-13.02.1Electrification Infrastructure . 2-12.2Electric Multiple Units . 2-12.3Schedule . 2-12.4Budget and Expenditures . 2-22.5Board Actions . 2-22.6Community Relations and Outreach . 2-2ELECTRIFICATION – INFRASTRUCTURE . 3-13.1Electrification . 3-13.2Supervisory Control and Data Acquisition (SCADA) . 3-13.3Tunnel Modification . 3-23.4Centralized Equipment Maintenance and Operations Facility (CEMOF)Modifications . 3-24.0ELECTRIC MULTIPLE UNITS . 4-15.0SAFETY . 5-16.0QUALITY ASSURANCE . 6-17.0SCHEDULE. 7-18.0BUDGET AND EXPENDITURES . 8-19.0FUNDING . 9-110.0RISK MANAGEMENT . 10-111.0ENVIRONMENTAL . 11-111.1Permits . 11-111.2Mitigation Monitoring and Reporting Program . 11-112.0UTILITY RELOCATION . 12-113.0REAL ESTATE . 13-114.0THIRD PARTY AGREEMENTS . 14-115.0COMMUNITY RELATIONS AND OUTREACH . 15-116.0DBE PARTICIPATION AND LABOR STATISTICS . 16-1Table of ContentsiAugust 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress Report17.0PROCUREMENT . 17-118.0TIMELINE OF MAJOR PROJECT ACCOMPLISHMENTS . 18-1List of TablesPageTable 2-1 Schedule Milestones . 2-2Table 2-2 Budget and Expenditure Status . 2-2Table 6-1 Quality Assurance Audit Summary . 6-1Table 7-1 Schedule Status . 7-1Table 7-2 Critical Path Summary . 7-2Table 7-3 Near-Term, Near-Critical with Less Than Three Months of Float . 7-3Table 8-1 Program Baseline Cost Estimate Summary. 8-2Table 8-2 Electrification Budget & Expenditure Status . 8-1Table 8-3 EMU Budget & Expenditure Status. 8-2Table 10-1 Monthly Status of Risks . 10-2Table 10-2 Risk Classification . 10-2Table 13-1 Real Estate Acquisition Overview . 13-2Table 14-1 Third-Party Agreement Status . 14-1Table 17-1 WD / PO Awards & Amendments . 17-2Table 17-2 Upcoming WD / PO Awards & Amendments . 17-3List of FiguresPageFigure 7-1 Critical Path Bar Chart . 7-3Figure 8-1 Program Cash Flow Projections . 8-3Figure 9-1 Funding Plan. 9-1List of AppendicesPageAppendix A – Acronyms . A-1Appendix B – Schedule . B-1Table of ContentsiiAugust 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress Report1.0BACKGROUNDOver the last decade, Caltrain has experienced a substantial increase in ridership andanticipates further increases in ridership demand as the San Francisco Bay Area’s populationgrows. The Caltrain Modernization (CalMod) Program, scheduled to be implemented by 2020,will electrify and upgrade the performance, operating efficiency, capacity, safety, and reliabilityof Caltrain’s commuter rail service.The Peninsula Corridor Electrification Project(PCEP) is a key component of the CalMod Programand consists of converting Caltrain from dieselhauled to Electric Multiple Unit (EMU) trains forservice between San Francisco Station (at theintersection of Fourth and King Streets in SanFrancisco) and Tamien Station in San Jose. Caltrainwill continue Gilroy service and support existingtenants.An electrified Caltrain will better address Peninsulacommuters’ vision of an environmentally friendly,and fast and reliable service. Electrification willmodernize Caltrain and make it possible to increaseservice while offering several advantages incomparison with existing diesel power use,including:Improved Train Performance, Increased Ridership Capacity and Increased Service:Electrified trains can accelerate and decelerate more quickly than diesel-powered trains,allowing Caltrain to run more efficiently. In addition, because of their performance advantages,electrified trains will enable more frequent and/or faster train service to more riders.Increased Revenue and Reduced Fuel Cost: An electrified Caltrain will increase ridership andfare revenues while decreasing fuel costs.Reduced Engine Noise Emanating from Trains: Noise from electrified train engines ismeasurably less than noise from diesel train engines. Train horns will continue to be required atgrade crossings, adhering to current safety regulations.Improved Regional Air Quality and Reduced Greenhouse Gas Emissions: Electrified trainswill produce substantially less corridor air pollution compared with diesel trains even when theindirect emissions from electrical power generation are included. Increased ridership will reduceautomobile usage, resulting in additional air quality benefits. In addition, the reduction ofgreenhouse gas emissions will improve our regional air quality, and will also help meet theState’s emission reduction goals.An electrified Caltrain system would set the stage for an enhanced, modern commuter railservice and for future blended California High-Speed Rail (CHSR) service. While this project willnot include or study all infrastructure necessary to implement high-speed rail service on thecorridor (such as CHSR maintenance facilities, station improvements, or passing tracks), theelectrical infrastructure (such as overhead wire systems) will be compatible with later blendedservice.Background1-1August 31, 2016Rev 0

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress Report2.0EXECUTIVE SUMMARYThe Monthly Progress Report is intended to provide an overview of the PCEP andprovide funding partners, stakeholders, and the public an overall update on the progressof the project. This document provides information on the scope, cost, funding, schedule,and project implementation.Several major milestones were reached during the month of August. The 7-PartySupplemental Funding Agreement was approved by all partners and the PCEP receiveda 20 million grant through the California State Transportation Agency. With the receiptof this grant, execution of the 7-Party Supplemental Funding Agreement, and bi-lateralagreement with California High-Speed Rail Authority (CHSRA), all local, regional, andstate funding sources have been secured for the project. The PCEP program achieved amajor milestone by receiving approval from the FTA to enter into the Engineering Phaseof the project. A signing ceremony was held on August 15th with Stadler and BalfourBeatty Infrastructure, Inc. (BBI). The ceremony was attended by local and federalelected officials, the Peninsula Corridor Joint Powers Board (JBP) and executive staff,key stakeholders, and the project team.2.1Electrification InfrastructureThe Contract Award signing for Electrification took place on August 15, 2016 at theCommunity Outreach Office. The Contract will begin with a Limited Notice to Proceed(LNTP) in September 2016, and is scheduled to proceed to full NTP in March 2017. Thecontract kickoff meeting for the Design-Build (DB) contract is scheduled for earlySeptember 2016.2.2Electric Multiple UnitsThe Contract Award signing with Stadler for the Electric Multiple Units (EMU) took placeon August 15, 2016 at the Community Outreach Office. The Contract will begin with aLNTP in September 2016, and is scheduled to proceed to full NTP in March 2017. TheContract kickoff meeting for the DB is scheduled for early September 2016.2.3ScheduleThe Revenue Service Date (RSD) in the Master Program Schedule (MPS) remainsunchanged. Without adjustment for contingency, the RSD is forecast as July 2021. Withthe addition of five months of contingency to account for potential risk to the project theRSD is anticipated as December 2021. Table 2-1 provides a summary of the currentschedule and milestones.Executive Summary2-1August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportTable 2-1 Schedule MilestonesProgramPlanJuneJulyEMU Contract Limited NTP*08/01/201608/15/201608/15/2016Electrification Contract Limited NTP*08/01/201609/06/201609/06/2016Start of Electrification Major Construction03/20/201707/24/201707/24/2017Start Pre-Revenue Operations09/08/202009/22/202009/22/2020Potential Limited Service12/31/202012/31/202012/31/2020RSD (w/ Risk es*MPS previously contained only Full NTP2.4Budget and ExpendituresA summary of the overall budget and expenditure status for the PCEP is provided inTable 2-2 below.Table 2-2 Budget and Expenditure StatusBaselineBudgetElectrification SubtotalEMU SubtotalPCEP Total2.5Accrued ToDateEstimate ToCompleteEstimate AtCompletion 1,316,125,208 65,432,231 1,250,692,977 1,316,125,208 664,127,325 14,210,636 649,916,689 664,127,325 1,980,252,533 79,642,867 1,900,609,666 1,980,252,533Board ActionsAt the August 4, 2016 meeting, the JPB received the 7th PCEP Quarterly updatepresentation.A copy of the presentation can be viewed here:http://www.caltrain.com/Assets/ Agendas and Minutes/JPB/Board of Directors/Presentations/2016/2016-08-04 JPB PCEP Quarterly Update.pdf2.6Community Relations and OutreachA number of community relations and outreach events took place during the month ofAugust. PCEP staff gave a total of 5 presentations and participated and attendedapproximately 8 third party/stakeholder actions and meetings. A press conference wasalso held with U.S. Transportation Secretary Foxx at the Caltrain Santa Clara Station.Executive Summary2-2August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportExecutive Summary2-3August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress Report3.0ELECTRIFICATION – INFRASTRUCTUREThis section reports on the progress of the Electrification, Supervisory Control and DataAcquisition (SCADA), and Tunnel Modification components. A brief description on eachof the components is provided below.3.1ElectrificationThe Electrification component of the PCEP includes the installation of 138 miles ofsingle-track and overhead contract system (OCS) for the distribution of electrical powerto the EMUs. The OCS will be powered from a 25-kilovolt (kV), 60-Hertz, single phase,alternating current supply system consisting of two traction power substations (TPS),one switching station (SS), and seven paralleling stations (PS). Electrification will beperformed using a DB delivery method.Activity This Month Coordination continued with PG&E on the Power Quality Study. PCEP staff andPG&E worked to finalize the scope and necessary infrastructure to supportCaltrain loads required for electrification. PCEP staff continued the coordination efforts with PG&E to refine interim poweroptions to support PCEP testing. A final option for interim power will be selectedfor PG&E to proceed with design and implementation. Contract signing occurred on August 15, 2016 The kickoff meeting was scheduled for September 6, 2016.Activity Next Month3.2 PCEP Team will hold a kickoff meeting for the DB contract. PCEP staff prepared Supplemental Agreement No.2 for PG&E oversight of 115 kVinterconnections and Supplemental Agreement No.5 for interim power. Bothagreements will be presented to the JPB in September 2016. Work with PG&E on the Power Quality Study and finalize load profile submissionsrequired for the California Independent System Operator (CAISO).Supervisory Control and Data Acquisition (SCADA)SCADA is a system that monitors and controls field devices for electrification, includingsubstations, paralleling stations and sectionalization. SCADA will be integrated with thebase operating system for Caltrain Operations and Control is Rail Operations CenterSystem (ROCS).Activity This Month Activity was limited to providing technical support on an as needed basis to theCaltrain Contract and Procurement Department for the procurement of the SCADAsystem.Electrification - Infrastructure3-1August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportActivity Next Month 3.3PCEP staff will continue to support Caltrain Contracts and Procurement Departmenton providing technical support during the procurement status.Tunnel ModificationTunnel modifications will be required on the four tunnels located in San Francisco. Thiseffort is needed to accommodate the required clearance for the OCS to supportelectrification of the corridor. Outside of the PCEP scope, Caltrain Engineering andConstruction has requested the PCEP team to manage completion of design andconstruction management for the Tunnel 1 and Tunnel 4 Drainage Rehab Project, TheDrainage Rehab Project is funded separately from PCEP and will be a Design-Bid-Build(DBB) construction package. Construction will occur concurrently with the Electrificationcontractor’s efforts in Segment 1.Activity This Month PCEP team continued coordination efforts with the design team on drawings andspecifications with particular focus on Tunnel 1 and Tunnel 4 Drainage Rehabprojects. The construction schedule and cost estimate was revised and review by PCEP team.Activity Next Month 3.4Coordination will continue on the Tunnel Modification design efforts.PCEP staff will assist with the field survey activities of Tunnel 1 and Tunnel 4Drainage Rehab Project.Centralized Equipment Maintenance and Operations Facility (CEMOF)ModificationsThe Centralized Equipment Maintenance and Operations Facility (CEMOF)Modifications project will provide safe work areas for performing maintenance on thenew EMUs.Activity This Month No work was undertaken during this reporting period.Activity Next Month The design contractor will resume their design activities now that a vehiclemanufacturer has been selected.Electrification - Infrastructure3-2August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress Report4.0ELECTRIC MULTIPLE UNITSThe EMU procurement component of the PCEP consists of the purchase of 96 StadlerEMUs. The EMUs will consist of both cab and non-cab units configured as sixteen sixcar units. Power will be obtained from the OCS via roof-mounted pantographs which willpower the axle-mounted traction motors. The EMUs will replace a portion of the existingdiesel locomotives and passenger cars currently in use by Caltrain.Activity This Month The EMU Pre-Commencement Conference was held on August 11, 2016. The contract signing took place on August 15, 2016, with an LNTP scheduled to beissued to Stadler in September 2016. Stadler secured all required Bonding and Insurance documents and submittedthese documents to Caltrain on August 16, 2016, in compliance with contractrequirements. Weekly Pre-LNTP coordination teleconferences were conducted with Stadler’sProject Team during the month of August. Action items and tasks were establishedand will carry over following LNTP. A list of EMU tests which can be performed on the Santa Clara Drill Track as wellas those that will need to be performed on the Main Line was prepared by Caltrainand will be reviewed with Stadler prior to finalizing.Activity Next Month LNTP is expected to be issued to Stadler in September 2016. Stadler will formally submit the EMU contract Mobilization Plan upon issuance ofthe LNTP. Monthly technical interface coordination conference calls with CHSRA will bescheduled.Electric Multiple Units4-1August 31, 2016Rev 0

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress Report5.0SAFETYThe PCEP Safety staff continued to develop and update the safety and securitymanagement processes as committed to within the scope of the project Safety andSecurity Management Plan (SSMP).Activity This Month Safety staff continued to work with the IndustrySafe hazard management softwareapplication that will also be utilized by the Electrification Contractor throughout theproject life cycle. Safety staff continued to meet weekly with the JPB management to provide projectupdates, review project document deliverables, and initiated changes as directed. Coordination continues with the DB Contractor on a Site Specific Work Plan’s(SSWP) for preliminary work.Activity Next MonthSafety Safety staff is updating the Roadway Worker Protection (RWP) Program to includeBasic RWP training module that will be required of contractor personnel requiringaccess to the Caltrain track area. Safety staff will continue to work closely with Caltrain Rail Operations to update theSSWP review, approval and document control process. A meeting is scheduled to meet with DB contractor to review SSWP process.5-1August 31, 2016Rev 0

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress Report6.0QUALITY ASSURANCEThe Quality Assurance (QA) staff performs technical review for planning, implementing,evaluating, and maintaining an effective program to verify that all equipment, structures,components, systems, and facilities are designed, procured, constructed, installed, andmaintained in accordance with established criteria and applicable codes and standardsthroughout the design, construction, startup and commissioning of the PCEP.Activity This Month The QA staff coordinated and worked with LKG-CMC to close non-conformancereport (NCR) 2 items. The re-audit for LKG-CMC Document Control will occur 6090 days from finalization of LKG-CMC Scope of Work for Document Control. QA reviews were conducted in response to the Readiness Review comments.Table 6-1 below provides details on the status of audits performed through thereporting period.Table 6-1 Quality Assurance Audit SummaryQuality Assurance ActivityThis Reporting PeriodTotal to DateInternal Audits Conducted014Non-Conformances Open02Non-Conformances Issued04Non-Conformances Closed14Activity Next Month QA staff will continue to provide support of FTA document submittals and alsoprovide reviews for Full Funding Grant Agreement (FFGA) items. QA staff will implement the Quality Manager Transition Plan until such time as areplacement Quality Manager joins the project. Meet with new Quality Manager to provide effective project on-boarding for QualityManagement.Quality Assurance6-1August 31, 2016Rev 0

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress Report7.0SCHEDULEThe schedule provided in this Monthly Progress Report is the approved schedule fromJuly due to the timeframe necessary to update and approve the schedule. As indicatedin Table 7-1, the Revenue Service Date (RSD), which is the date in which the project isdeemed completed, remains unchanged in the Master Program Scheduled (MPS).Without adjustment for contingency, the RSD is forecast as July 2021. With the additionof five months contingency to account for potential risk to the project, the RSD isanticipated as December 2021. A summary of the overall schedule status for the PCEPis provided in Table 7-1, which provides comparisons between the baseline schedule(Program Plan), the previous update (June) and the current update (July) to capture anypotential changes in the schedule. A complete schedule can be found in Appendix B.Table 7-1 Schedule StatusProgramPlanJuneJulyEMU Contract Limited NTP*08/01/201608/15/201608/15/2016Electrification Contract Limited NTP*08/01/201609/06/201609/06/2016Start of Electrification Major Construction03/20/201707/24/201707/24/2017Start Pre-Revenue Operations09/08/202009/22/202009/22/2020Potential Limited Service12/31/202012/31/202012/31/2020RSD (w/ Risk es*MPS previously contained only Full NTPItems listed in Table 7-2 and depicted in Figure 7-1 show the critical pathactivities/milestones for the PCEP. Table 7-3 lists important schedules and activities inthe horizon.Notable VariancesNotable variances can be characterized as changes in the schedule that could lead toa significant delay. There were no notable variances during the reporting period.Schedule7-1August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportTable 7-2 Critical Path SummaryActivityStartFinishEMU ProcurementOngoing08/15/2016Electrification ProcurementOngoing09/06/2016EMU Design to Delivery of First Carbody08/15/201609/22/2017Electrification Design to Begin Major Construction09/06/201607/21/2017Electrification OCS Construction07/24/201702/26/2020Electrification Acceptance & Integrated TestingPG&E Complete Infrastructure Upgrades to ProvidePermanent Power*Vehicle Manufacturing & Assembly to Provide First 6TrainsetsPre-Revenue 10/09/201709/21/202009/22/202012/22/2020Potential Limited Service*12/31/202012/31/2020RSD (w/out Risk Contingency)*07/26/202107/26/2021RSD (w/ Risk Contingency)*12/30/202112/30/2021*Milestone activityFigure 7-1 Critical Path Bar ChartSchedule7-2August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportTable 7-3 Near-Term, Near-Critical with Less Than Three Months of FloatWBSScheduleActivityResponsibilityFTAPath to Full Funding Grant Agreement (FFGA)Project DeliveryUtilitiesPG&E Scoping & Preliminary DesignProject Delivery7-3August 31, 2016Rev 0

THIS PAGE INTENTIONALLY LEFT BLANK

Peninsula Corridor Electrification ProjectMonthly Progress Report8.0BUDGET AND EXPENDITURESIn July, PCEP received from the FTA’s PMOC, Readiness to Enter Engineering – July2016 report. As part of the Cost Estimate review, the report recommended five changesto the budget allocations that did not change the bottom line number, but further refinedthe budget within the FTA’s standard cost code (SCC) reporting structure. As a result,Baseline Cost Estimates were revised to reflect the changes. Some of the majorchanges involved allocation contingency and development of a simplified tool fortranslating PCEP cost estimates to the FTA SCC format.A summary of the overall budget and expenditure status for the PCEP is shown in thefollowing tables. Table 8-1 reflects the Electrification budget, Table 8-2 reflects the EMUbudget, and Table 8-3 reflects the overall project budget.Table 8-1 Electrification Budget & Expenditure Status ELECTRIFICATIONElectrificationTunnel NotchingReal EstatePrivate UtilitiesManagement OversightExecutive ManagementPlanningCommunity RelationsSafety & SecurityProject Management ServicesEngineering & ConstructionElectrification Engineering &ManagementIT SupportOperations SupportGeneral SupportBudget / Grants / FinanceLegalOther Direct CostsPrior Costs 2002 - 2013TASI SupportRRP InsuranceEnvironmental MitigationsRequired ProjectsMaintenance TrainingFinance ChargesActual ThisPeriodBudgetDescription of Work (A)(B)Accrued ToDate1(C)2Estimate ToCompleteEstimate AtCompletion(D)(E) (C) (D) ,805,793 62,15058,602613,9546,8008,378311,649- 459438,2636,345,1881,733,481 072,312 ,805,793 817,337,3781,021,8083,168,200 92,4451,0395,423188,220- 01,321,06024,333,358261,228.84367,028- 970,3501,021,8083,168,200 817,337,3781,021,8083,168,200 276,970,649- 276,970,649- 276,970,649-ELECTRIFICATION SUBTOTAL 1,316,125,208 ContingencyOwner's Reserve734,706 65,432,231 1,250,692,977 1,316,125,208Notes regarding tables above:1. Column B "Actual This Period" represents the actual cash payment during the reporting period.2. Column C "Accrued To Date" includes actuals incurred to date and accruals to date.3. The current budget vs. expenditure table represents the reconciled information based on the improvedreporting from the district accounting system and implementation of new cost management system.Budget and Expenditures8-1August 31, 2016Rev 0

Peninsula Corridor Electrification ProjectMonthly Progress ReportTable 8-2 EMU Budget & Expenditure StatusDescription of WorkEMU CEMOF Modifications Management Oversight Executive Management Community Relations Safety & Security Project Management Services Engineering & Construction EMU Engineering &Management IT Support Operations Support General Support Budget / Grants / Finance Legal Other Direct Costs TASI Support Required Projects Finance Charges Contingency Owner's Reserve EMU SUBTOTAL BudgetActual ThisPeriodAccrued ToDateA)(B)1(C)2Estimate ToCompleteEstimate AtCompletionD)(E) (C) 4556,06713,275,28089,113 712,82111,8004,584223,700- 14,210,6361,350,331189,963102,7524,379,23623,817 3,3168,896,04465,296 01,941,80038,562,962- 312,5441,901158,292- 10,447- ,192,6922,740,0004,500,0001,941,80038,562,962-

Monthly Progress Report Executive Summary 2-1 August 31, 2016 Rev 0 2.0 EXECUTIVE SUMMARY The Monthly Progress Report is intended to provide an overview of the PCEP and provide funding partners, stakeholders, and the public an overall update on the progress of the project. This document provides information on the scope, cost, funding, schedule,

Related Documents:

August 2, 2021 15 August 2, 2021 16 August 2, 2021 17 August 3, 2021 18 August 4, 2021 19 August 5, 2021 20 August 6, 2021 21 August 9, 2021 22 August 9, 2021 23 August 9, 2021 24 August 10, 2021 25 August 11, 2021 26 August 12, 2021 27 August 13, 2021 28 August 16, 2021 29 August 16, 2021 30 August 16, 2021 31

XSEDE HPC Monthly Workshop Schedule January 21 HPC Monthly Workshop: OpenMP February 19-20 HPC Monthly Workshop: Big Data March 3 HPC Monthly Workshop: OpenACC April 7-8 HPC Monthly Workshop: Big Data May 5-6 HPC Monthly Workshop: MPI June 2-5 Summer Boot Camp August 4-5 HPC Monthly Workshop: Big Data September 1-2 HPC Monthly Workshop: MPI October 6-7 HPC Monthly Workshop: Big Data

average monthly income or net operating loss. Small Business Startup Eligibility Calculation Reduction in Average Monthly Income Net Operating Loss 1.2 X Average Monthly Income (Prior to March 1, 2020) Average Monthly Income (March 1, 2020 to August 31st 2020) Monthly Cash Flow ( ) Monthly Cash Flow (-) Monthly Cash Flow (-) Monthly Cash Flow ( )

January monthly files – March 15th February monthly files – April 15th March monthly files – May 15th April monthly files – June 15th May monthly files – July 15th June monthly files – August 15th July monthly files – September 15

Billings Clinic Cost Total Monthly Cost Billings Clinic Cost Total Monthly Semi-Monthly Monthly Monthly Semi-Monthly Monthly Monthly Cost Employee Only 99.45 198.90 419.52 618.42 128.01 256.02 415.75 671.77 Preventive Care The Billings Clinic medical plans cover in-network preventive care at 100%. This includes routine screenings and .

Monthly progress report No. 5 2017 2 MONTHLY PROGRESS REPORT NO. 5 1.0.0 Project: Design and Construction of a Proposed New Medical Stores Warehouse, Chipata, Zambia 2.0.0 Project Data Participants 2.01 Employer: United National Development Programme (UNDP) 2.02 Benef

Peninsula Corridor Electrification Project Monthly Progress Report Executive Summary 2-1 April 30, 2018 2.0 EXECUTIVE SUMMARY The Monthly Progress Report is intended to provide an overview of the PCEP and provide funding partners, stakeholders, and the public an overall update on the

security rules for protecting EU classified information, certain provisions in this guide are still based on Commission Decision 2001/844. In the absence of new guidelines they should continue to be applied. Under the new security rules, all classification markings must now be written in FR/EN format (e.g. RESTREINT UE/EU RESTRICTED). EU grants: H2020 Guidance — Guidelines for the .