Finance & Administration CommitteeItem III-AJanuary 13, 2010Overview of Program Management Servicesand Proposed CIP FY2012-17

Washington Metropolitan Area Transit AuthorityBoard Action/Information SummaryActionInformation MEAD Number:Resolution:YesNoTITLE:Overview of Program Management Services & the CIPPURPOSE:To provide a status report on the delivery of the Metro Capital Improvement Plan.Additionally, the presentation shows the evolution of the currently proposedCapital Improvement Program.DESCRIPTION:Metro staff have developed a proposed Capital Improvement Program (CIP) forFY2012-17. Included in this proposed CIP is the FY2012 Annual Work Plan(AWP).The FY2012 AWP will result in capital expenditures of approximately 851 millionin FY2012 and lay the foundation for planned capital expenditures of 5.1 billionfrom FY2012 through FY2017.Key deliverables for the CIP include: Replacement of 100 Metro buses and the rehabilitation of 100 more (CIP005 and CIP 006) Replacement of 230 MetroAccess vehicles (CIP 015) Retrofitting of 2,700 feet of track floating slabs (CIP 019) Rehabilitation of 5,000 feet of track pads/shock absorbers (CIP 021) Rehabilitation of 5 miles of third rail (CIP 023) and rehabilitation of 10miles of running rail (CIP 024)Parsons-Brinkerhoff (PB) is assisting in the development of an IntegratedProgram Management Information System to help speed delivery of the CIP, aswell as implement the reporting and billing requirements in the Capital FundingAgreement. This includes the development of expenditure forecasts, a costtracking system, and project delivery risk tracking.

The presentation provides the Finance and Administration Committee and thepublic with an overview of the process to develop the AWP.FUNDING IMPACT:The total Capital Improvement Program budget is maintained at 5.9 billion.RECOMMENDATION:None. This is for information only.

Washington Metropolitan Area Transit AuthorityOverview of Program Management Servicesand Proposed Capital Improvement PlanFY2012-17Finance and Administration CommitteeJanuary 13, 2011

Program Management Information System& Mitigation ActivitiesActivityEstablish Integrated ProgramManagement InformationSystem (PMIS) Master scheduleCost trackingRisk trackingAll levels of reportingDeliverables Quarterly reports11-15-10 and each QTR Annual work plan12-15-10 Master schedule protocol12-31-10 Cost tracking system12-31-10 Project delivery risk trackingsystem1 31 111-31-11 PMIS system integration4-01-11BBenefitsfit off PMISPMIS: Enhances programmatic transparency via regular progress reporting Identifies & mitigates delivery risks (scope/schedule) before they occur

Building Confidence in Program DeliveryThrough Progressive Tools & 011MayJunJulAugSepResourcesProgress AssessmentSupportProgram Management Information SystemMonthly Status ReportMaster ScheduleCost TrackingRisk ManagementPMIS System IntegrationQuarterly Report/Bill, Draft Annual WorkPlan, Draft Budget Book, Draft CIPIncreasing ConnfidenceConfidence in Achievingg ProgramgDelivery Objectives & Forecasts onScheduleQ1Q2Q3Building Confidence in DeliveryEstablishing TransparencyAssessing RiskMILESTONES:‐ Initial Report Structure Drafted with Limited Data‐ Start of PB Support‐ Report Structure Complete with Core Data‐ Live Version of PMIS Tool Available‐ Report in Final Form & Data Fully AvailableQ4CIPMonitoringg &MaintainingProgress

FY2011 Quarter 1 Progress Report New qquarterlyy reportingpg requirementqperp June 2010Capital Funding Agreement (CFA)CIP Spending PerformanceQ Forecast:Q1 158.4M Reviewed CIP project schedules, progress and budgetwith Metro Project Managers and analyzed Q1variances over 2M100%75% Refined quarterly cash flow forecasts through FY2012to support jurisdictional Q3 bill– FY2011 CIP expenditure forecast 730.3 millionQ1 Spent: 77.2M 49%50% QQuarterlyt l reportt willill beb expandedd d tot includei l d ARRA,ARRAreimbursable, and safety & security grant projects25%

Evolution of FY12-17 CIP Budgetfrom June to October 2010 NTSB recommendations and additional rehabilitation requirements incorporated Project cash flow adjustments/deferrals used to offset additional needs in order to maintain 5 billion FY11-16 cumulative budget. With rescheduled new budget in FY17, total FY11-16 FY17 CIP budget is 5.9 billion.Program Budget (Millions) 0 1,000 2,000 3,000 4,000FY11‐16 Approved CIP (June 2010)11000 Series Replacement Rail Cars: Rescheduled for FY17 (CIP 057)4000 Series Rail Car Replacement: Re‐sequencedRe sequenced into FY17 (CIP 060) 275% 8‐Car Train 7000 Series Rail Cars (CIP 069)Bus Garage Capacity Enhancements: Defer to FY17 (CIP 038)Rail Mileage‐Based Asset Management Phase II (CIP 140)Track Maintenance Equipment: Defer to FY17 (CIP 025)Bus Replacement: Defer to FY17 (CIP 006)Other Projects with Changes Less Than 10MNTSB Recommendations (CIP 139)Rail Rehab Dupont to Grosvenor (CIP 108)Systemwide Infrastructure Rehab (CIP 138)FY11‐16 of FY12‐FY17 Draft CIP (October 2010)Rescheduled FY11‐FY16 Budget in FY17 (from above)Balanceloff New FY17 BudgetdFY11‐17 of FY12‐17 Draft CIP (October 2010)1 Buy Americacompliance requirements resulted in rescheduling production delivery into fiscal year 2017.Dulles Phase 2 to meet Dulles expansion requirements.2 Re‐sequencing with 5,000 6,000 5,105.7( 222.9)( 75.4)( 23.9)( 22.8)( 18.8)( 14.7)( 10.2)( 48 5)( 48.5) 254.2 86.6 20.2 5,029.5 346.0 536.4 5,912.0Initial(Deferral)AdditionFinal

Evolution of FY12-17 CIP Budgetfrom October to December 2010 Reflects adjusted forecast growth assumptions for Federal FundingRefined NTSB scope, added state-of-good-repair/safety projects, eliminatedenhancement projectsTotal CIP budget for FY11 FY12-17 CIP is maintained at 5.9 billionProgram Budget (Millions) 0 1,000 2,000 3,000 4,000 5,000 6,000FY11‐17 of FY12‐17 Draft CIP (October 2010) 5,912.0NTSB Recommendations ((CIP 139))( 61.8))( Bus Capacity Enhancements (CIP 003)( 34.9)Open Bankcard/Auto. Fare Collection (CIP 097)( 10.3)Other Projects with Changes Less than 8M( 18.5)Rail Rehabilitation Program (CIP 063) 43.5d Hardeningd& Bus Security ((CIP 145))Raill Yard 18.6Track Maintenance Equipment (CIP 025) 14.7Bus Replacement (CIP 006) 10.2Rail Yard Facilities Repairs Tier 1 (CIP 116) 8.5Track Rehabilitation (CIP 024) 8.5Proposed FY11‐17 Forecast (December 2010) 5,890.6Initial(Deferral)AdditionFinal

Evolution of FY12-17 CIP Fundingfrom June to December 2010 Reduction in Federal funding growth rate assumptions & jurisdictional matchOffset by additional debt, system performance funds & Metro Matters residualfundsProgram Funding (Millions) 0 1,000 2,000 3,000 4,000FY11‐16 Approved CIP (June 2010) 5,000 6,000 5,105.7( 76.2)Reduction in Debt (Shifted into FY17)FY11‐16 of FY12‐17 Draft CIP (October 2010) 5,029.5Rescheduled FY11‐16 Debt in FY17 76.2Balance of FY17 Revenue Forecast (October 2010) 806.3FY11‐17 of FY12‐17 Draft CIP (October 2010) 5,912.0Reduction in Federal Formula Grants( 173.8)Reduction in Jurisd. Match for Formula Grants( 43.4)Additional Debt in FY17 86.6Increase in Jurisd. System Performance Funds 43.4Addition of Metro Matters Residual Funding 43.0Net Additional Miscellaneous Funds (DHS) 15.4Additional CMAQ funds 7.4FY11‐17 Current Forecast (December 2010) 5,890.6Initial(Deferral)AdditionFinal

CIP: FY2012 Annual Work ProgramState of Good Repair FY12 Key Planned DeliverablesReplacement of 100 Metro buses and the rehabilitation of 100 more (CIP 005 and CIP 006) Replacementof 100 Metro buses & the rehabilitation of 100 more Replacement of 230 MetroAccess vehicles (CIP 015)(CIP005 andCIPservice006) Replacementof 200vehicles (CIP 009) g of 2,700,feet of track floatingg slabs (CIP(019)) Retrofitting Replacement of 500 signs and 3,000 chain markers (CIP 020) Rehabilitation of 5,000 feet of track pads/shock absorbers (CIP 021) Rehabilitation of 5 miles of third rail (CIP 023)Rehabilitation of 10 miles of running rail (CIP 024) Installation of 30 turnouts (incl. NTSB), 15,000 direct fixation fasteners, & 8,000 cross ties (CIP 024)Installationof 30 turnouts (incl. NTSB), 15,000 direct fixation Mitigation of approximately 1,700 leaks throughout the various Metro stations (CIP 026)fasteners,& of8,000crossties Rehabilitation20 switchmachines(CIP(CIP027) 024) Purchase of 188 units of rail shop repair equipment (CIP 188) Full rehabilitation of 12 Metro stations and mini-rehabilitation of another 12 Metro stations (CIP 087) Installation of 50,000 track fasteners and anchor bolts (CIP 089) Purchase of 150 police handheld radios (CIP 103) R lReplaceTPSS equipment,it ATC equipmentit andd ETS boxes/cabling,b/ bliescalatorsl t(CIP 107) Rehab of all of Northern & half of Western Bus Garages, Four Mile Run boiler plant (CIP 119) Track circuit replacements (CIP 139)

Building Confidence in Program DeliveryThrough Progressive Tools & 011MayJunJulAugSepResourcesProgress AssessmentSupportProgram Management Information SystemMonthly Status ReportMaster ScheduleCost TrackingRisk ManagementPMIS System IntegrationQuarterly Report/Bill, Draft Annual WorkPlan, Draft Budget Book, Draft CIPIncreasing ConnfidenceConfidence in Achievingg ProgramgDelivery Objectives & Forecasts onScheduleQ1Q2Q3Building Confidence in DeliveryEstablishing TransparencyAssessing RiskMILESTONES:‐ Initial Report Structure Drafted with Limited Data‐ Start of PB Support‐ Report Structure Complete with Core Data‐ Live Version of PMIS Tool Available‐ Report in Final Form & Data Fully AvailableQ4CIPMonitoringg &MaintainingProgress

Master Schedule/Cost Tracking Work Breakdown Structure to include all capital programs CIP, ARRA, Reimbursable Projects, Safety and Security Initial high level reporting by phase Consistent reportingacross projects Interdependenciesamong projects Quarterly updates Web-based access

Program Delivery Proactive Risk ManagementTop Projects w/Expenditure Underruns Staff Needed ((field staff,, contract admin,, track rights,g, escorts))––––CIPCIPCIPCIP107110119138Red Line Rehabilitation Tier 1Orange and Blue Line RehabilitationBus Facility Repair Tier 1Miscellaneous Projects Schedule Refinement/Deferrals– CIP 049 Management Support Software– CIP 057 1000 Series Rail Car Replacement Cost Reporting (Operations to Capital Transfer)– CIP 005 Bus Rehabilitation– CIP 125, 137, 142, 143 Preventive Maintenance CIP 139 (NTSB) – Scope,Scope Schedule,Schedule & Cost Estimate Refinement

Staff Augmentation for CIP Program Delivery Regulatory Compliance– Safety/Security reporting support Expedite Procurement and Closeout– Contract Administrators– Claims support KKey StStaffff ffor CContractttEExecutionti– Office Engineer for Red Line Rehabilitation– Inspection support for Bus 1– Assistant Project Manager for Orange & Blue Line Rehabilitation Grant Acquisition– Financial Analyst

(CIP 005 and CIP 006) g, g ( ) Replacement of 500 signs and 3,000 chain markers (CIP 020) Rehabilitation of 5,000 feet of track pads/shock absorbers (CIP 021) Rehabilitation of 5 miles of third rail (CIP 023) Rehabilitation of 10 miles of running rail (CIP 024)Rehabilitati

Related Documents:

3 TABLE OF CONTENTS 1. EXO Platform Overview 1.1 EXO1 Sonde Overview 1.2 EXO2 Sonde Overview 1.3 EXO2S Sonde Overview 1.4 EXO3 Sonde Overview 1.5 EXO Field Cables Overview 1.6 EXO Handheld Overview 1.7 EXO GO Overview 2. Operation 2.1 Sonde Install / Replace EXO1 Batteries 2.2 Sonde Install / Replace EXO2 and EXO3 Batteries 2.3 Install / Remove Guard or Cal. Cup 2.4

5 Enterprise Campus 3.0 Architecture: Overview and Framework OL-15716-01 Campus Architecture and Design Principles Access and Mobility Services Application Optimization and Protection Services Virtualization Services Security Services Operational and Management Services In the later sections of this document, an overview of each of these services and a description of howFile Size: 1MB

Air Service Incentive Program ("ASIP") Program Overview and Guidance Document Page 8 of 38 J:\Contracts\AIRLINE OPERATING AGREEMENTS\ASIP\ASIP Program Overview Document.docx SECTION II -INCENTIVE PLANS 2.1 Plan A: New Entrant The following incentive plan is available to any Air Carrier, as defined in this PROGRAM,

Resume Writing Services Business Manager Services Insurance Risk Management Services Safety / Loss Control Consultant Services Career Coach Services Interior Designer Services / Interior Decorator Services Social Security Claims Representative Services / Worker Compensation Claims Representative Services

Bureau of Human Resource Management Organizational Development & Training Services. Bureau of Facilities Maintenance & Office Services HHS Facilities & State Office Safety & Wellness Office Services Oversight – Institutional Services. Communications Bureau. Employee Assistance Program. October 2020 * Overview represents .

School Supportive Health Services Program Preschool Supportive Health Services Program Questions and Answers Issued June 11, 2010 Status of School and Preschool Supportive Health Services Program 1. Q. Who is responsible for setting Medicaid policy and reimbursement rates for the Preschool/School Supportive Health Services Program (SSHSP)? A.

Clinica Sierra Vista also operates a variety ofcontract services including mental health services, dental services, WIC program, prenatal case management services, homeless medical and case management services, HIV/AIDS medical and case management services, and other related projects. Your paid position w

Project Issue Management Process Project Issue Management Process Template, version 1.0 (03.15.12) ii 1 Introduction The Project Issue Management Process is followed during the Execution phase of the Project Management Life Cycle throughout the project; however, issues may be identified at any stage of the project life cycle.File Size: 258KBPage Count: 8People also search forissue management processcontemporary issue management:contemporary issue management: quizletdefine opportunity management processacquisitions the issue management proces asana project management templates