8.0 ELECTRICAL SYSTEM DESIGN BASIS

2y ago
44 Views
2 Downloads
663.88 KB
11 Pages
Last View : 9d ago
Last Download : 3m ago
Upload by : River Barajas
Transcription

8.08.1ELECTRICAL SYSTEMDESIGN BASISThe main generator (described in Chapter '10) will feed electrical powerat 22 KV through isolated phase bus to two half-sized main power transformers.The auxiliary power distribution system for Indian Point Unit No. 3 isessentially the same as that used in present day conventional plants.large auxiliary transformers supply power at 6.9 KV.TwoOne transformer, designateddesignated the unit auxiliary; is fed directly from the generator output.The other transformer, designated the station auxiliary, is supplied fromthe 138 KV Buchanan Substation.8.2NETWORK INTERCONNECTIONSElectrical energy generated at 22 KV will be stepped up to 345 KV by themain generator transformers and delivered to Buchanan 345 KV switching stationthrough one 345 KV, 25,000 MVA, 2000 amp circuit breaker.Indian Point #2 Unit and a 345 KV tie to Pennsylvania-Jersey-Maryland (P.J.M)system will also be connected to Buchanan 345 KV switching station.Aone line diagram of the proposed system interconnections is shown on Figure3-1.The new Buchanan 345 KV switching station will be connected by two 345 KVoverhead lines, subsequently three, 345 KV overhead lines, to Millwood345 KV switching station.Millwood and Buchanan bus and circuit breakerswill all be rated 345 KV, 25,000 MVA, 2000 amp.Millwood switching station is connected to the north to the Pleasant Valleysubstation (which is the interconnection point between Con Edison and theNiagara Mohawk and Connecticut Light and Power systems) and south to SprainBrook substation (which has connections to New York City and the 1000 MWunit at Ravenswood).(8100237 670426PDR ADOCK 05000286'BPDR8'-1

A 345/138 KV autotransformer will also connect the 345 KV bus to the 138 KVbus and transmission system at Millwood East.The Indian Point Unit:No. 3 138/6.9 KV station startup transformer will besupplied from the 138 KV bus at Buchanan substation.Buchanan has connectionsto Indian Point No. 1 generator, the Lovett station of the Orange and Rocklandsystem and the Consolidated Edison 138 KV transmission system via two overhead lines to Millwood East.8.3STATION DISTRIBUTIONThe function of the Auxiliary Electrical System is to provide reliable powerto those plant auxiliaries required during any normal or emergency modeof plant operation.The design of the system is such that sufficient independence or isolationbetween the various sources of electrical power is provided to guard againstconcurrent loss of all auxiliary power.Independence or isolation of supply to the various duplicate auxiliariesprovided as engineered safeguards is maintained so a single fault willnot result in the total loss of the plant's engineered safeguards systems.The Auxiliary Electrical System is designed to provide a simple arrangementof buses requiring the minimum of switching to restore power to a bus inthe event that the normal supply is lost.The basic components of the station electrical system are shown on the MainElectrical One Line Diagram, Figure 8-2.

8.3.16.9 KV SYSTEMDuring startup, shutdown and hot standby, auxiliary power is supplied fromthe Station Auxiliary.Transformer.When the generator is synchronized tothe 345 KV system, auxiliary power is supplied primarily by the Unit AuxiliaryTransformer.A small portion of the auxiliary load consisting of two circulating water pumps and two 6900/480 auxiliary transformers, remain onthe Station Auxiliary Transformer at all times. The Station Auxiliary Transformer supplies two 6.9 KV bus sections (Nos. 5 and 6) through 2000 ampere,500 MVA air circuit breakers.The Unit Auxiliary Transformer supplies 6.9KV bus sections Nos. 1, 2, 3 and 4 through 1200 ampere, 500 MVA air circuitbreakers.The 6.9 KV bus section No. 1 and 2 can be connected to 6.9 KV bus sectionNo. 5, by a 1200 ampere, 500 MVA air circuit breaker,In a similar manner,6.9 KV bus section No. 3 and 4 can be connected to 6.9 KY bus section No. 6.All major auxiliaries above approximately 300 HP are supplied from the 6.9KV switchgear by 1200 ampere, 500 MVA air circuit breakers.Each of 6.9 KV bus sections 1 through 4 supplies one reactor coolant pumpand other auxiliaries as shown on the main one line diagram, Figure 8-2.The auxiliaries are divided between the four 6.9 KV buses to proyide a highdegree of diversity to minimize the possibility of plant trip due to lossof one 6.9 KV bus.After a reactor or turbine generator trip, the necessaryauxiliaries on 6.9 KV bus sections 1, 23 and 4 are transferred automaticallyto 6.9 KV bus sections 5 and 6 by high speed open transition transfer,transfer time is on the order- of twenty cycles so that the transfer willThisbe completed before the reactor coolant pumps haye begun to slow down.8-3

8.3.2480 VOLT SYSTEMMotors between 100 and 300 HP are supplied by 480 volt switchgear.This480 volt system consists of four bus sections designated as Nos. 2A, 3A,5A and 6A. Each section is normally supplied by a 2000/2666 KVA ventilated,dry type 6900/480 volt transformer.The transformers are numbered to correspondwith the bus section they supply.Two of these transformers (Nos. 5 and 6) are normally supplied by the 138/6.9KV Station Auxiliary Transformer.These bus sections normally supply someof the engineered safeguards equipment and are left on the outside sourceof power to avoid subjecting them to a transfer at the time when the equipmentsupplied by them may be called upon to operate.of engineered safeguards equipment is maintained.Complete duality of supplyAdditional safeguardsequipment which may be used is supplied from 480 volt bus sections Nos.2A and 3Awhich can be connected to bus sections Nos. 5A and 6A if required.The 6900/480 volt transformers Nos. 2 and 3 are fed from bus sections Nos.2 and 3 of the 6900 volt system, and normally supply 480 volt bus sectionsNos. 2A and 3A.The 480 volt buses can be interconnected by electricallyoperated tie breakers in case one of the normal 6900/480 KV transformersis out of service.Each of the four of the 480 volt bus sections can also be supplied by anautomatic starting diesel generator which will act as a back up to the normalsource of supply to the bus section.If the normal supply to all 480 voltbus sections is lost, the diesels will automatically start.For loss of all normal AC power to the 480 volt bus sections, the tie breakersbetween the sections allow any of the four to be supplied by diesel generators.The diesels will be sized so that any two of the three diesels will havesufficient capacity to supply the engineered safeguards load required foran acceptable post-blowdown containment pressure transient.

8.3.3DC SYSTEMThe dc system consists of station batteries, static rectifier type batterychargers and panels to distribute the required dc power to equipment.Thebattery chargers will be of sufficient size to carry normal continuousdc load.8.3.4INSTRUMENT SUPPLY SYSTEMThe 115 volt ac supply system for the Reactor-Turbine Control and Instrumentation Systems will consist of four distribution panels, two having staticinverter system sour ,ces and two-having 480V system sources.An alternatesource will be provided to each panel from the lighting system.Vital instrument loads that make up two out of three or two out of fourlogic matrices for reactor trip circuits are supplied from separate busesso that failure of one bus will not result in a reactor trip,Instrumentchannel isolation is maintained by the use of the four separate panels.Three of the panels provide the sources for the two out of three logic devices.The fourth panel supplies the devices that make up the two out of four logicas well as other nuclear plant instruments that require a regulated source.8.4EMERGENCY POWER SOUR CESThe 480 volt bus sections which supply power to the engineered safeguardsequipment have the following alternate sources of power, to provide assuranceof operation under all conditions.1.All four buses can be supplied from the 138 KV Buchanan Substation.2.All buses can be supplied directly by automatically starting dieselgenerators.3.All buses can be interconnected by tie breakers,4.Automatic transfer is proyided to an active bus if a diesel shouldfail to start.

There will be three (3) 50% capacity emergency generators installed forIndian Point Station, Unit #3. Any two units, as a back-up to the normalstandby AC power supply (Consolidated Edison 138 KV system) will be capableof sequentially starting and supplying the power requirements of one completeset of safeguards equipment.Figure 8-3, as attached, is a one-line diagramof the 480 volt bus arrangement of the emergency diesel-generator unitsand the engineered safeguards equipment.The equipment automatically startedduring the injection phase is:One residual heat removal pumpTwo safety injection pumpsTwo service water pumpsOne containment spray pumpThree of five containment ventilation fansOne auxiliary steam generator feed pumpThe loads will be changed manually from the above during the recirculationphase to provide cooling to the containment and core by either the fan coolersor the recirculation of coolant from the containment sump.The diesel units will be started on loss of voltage on the 480 volt buses.The loss of voltage signal coincident with a safeguards signal, will alsotrip all motor feeder, main supply, and tie breakers on the 480 volt buses.After each unit comes up to speed and voltage, requirement for a safeguardsystem operation will initiate the closure of the emergency generator supplybreakers to their respective 480 buses.Upon energization of the 480 volt buses, the following two sequences willbe started simultaneously:8-6

Sequence 1 (Equipment Connected to Bus 5A and 2A)Start safety injection pump (#1) and energize motor control center (Bus 5)to supply power to valves.If safety injection pump #1 did not start, startsafety injection pump No. 2.Start first containment ventilation fan.Start second containment ventilation fan.Containment spray pump (No. 1) can now be started by a high containment pressuresignal.If containment spray pump No. 1 did not start, start containment spraypump No. 2.Sequence 2 (Equipment Connected to Bus 6A and 3A)Start residual heat removal pump (No. 2) and energize motor control centerto supply power to-valves.If residual heat removal pump No. 2 did not start,start residual heat removal pump No. 1. Start service water pump No. 4. Ifservice water pump No. 4 did not start, start service water pump No. 5.Start fourth containment ventilation fan.If one of the containment ventilation fans in either sequence 1 or sequence2 did not start, then the third containment ventilation fan in sequence 1and/or the second containment fan in sequence 2 will be started.In the event an emergency diesel-generator unit did not start, appropriatetie breakers will be closed in order to energize the four 480 volt busesdepending on which unit did not start; the buses will be energized as follows:1.Diesel-generator 1 did not start-diesel-generator2 supplies Bus 5Aand Bus 2A, diesel-generator 3 supplies Bus 3A and Bus 6A.2.Diesel-generator 2 did not start-diesel-generator 1 supplies Bus5A and Bus 2A, diesel-generator 3 supplies Bus 3A and Bus 6A.3.Diesel-generator 3 did not start-diesel-generator 1 supplies Bus 5Aand Bus 2AP diesel-generator 2 supplies Bus 3A and Bus 6A.8-m-7

The sequence of starting the motors will be the same as previously listedand will not be affected by the buses being supplied either by two or threediesel generators.Two 60 cell, lead acid, station type batteries are provided for power supplyfor control, emergency lighting and the inverters for critical 60 cycleinstrument power.8.5TESTS AND INSPECTIONPeriodic tests and inspections will be made on all breakers.Also, periodicstart tests and routine maintenance procedures will be performed on thediesel-generator sets.The frequency and nature of these tests will beestablished during the system design when the components are selected.8-8

CORNWALL GEN. STATIONCORNWALL EASTNI AGARATO STEM GAS & ELEC.TOLOVETT STA.ORANGE & ROCKLAND SYSTEMBUCHANAN138 KvTON.Y. STATEGAS & ELEC.138 KV345 Kv345 KvSOUTH TO NEW YORK.CITYSIMPLIFIED ONE-LINE DIAGRAM PROPOSED SYSTEM INTERCONNECTIONSFIG. 8-1

ATYFPICNL FOR1, - 5a0-YO"-op,-9 ?D0- 1203VG o-SS-toSSr(-ir !G00v-SU%2.o-rA.00tN.r- Gl oov-.,O-G-riiS's RtIT3.o.K F --, -iBi%"4IJAVARD-H -p043Tj03T{5ZC-CT'S --Tirt55ZtT52SWSR CSZIL-1 1 - ---CT'SSSIdaw3.53MM CZM-CIR51 SZ1RI - C TF P, S- .L IN K(VGROmu119iNo,115 IFo%200266-KPVJNTER3-60(CLRCULLFCIGCOOl-ANT UMP1UCI5IPOWFl"DVMAIPUMPMPP0UMPIEDFlMP 3432?2)2 p NoFPUMPNW0S,25C UL OZSNPIC?4pUMPtAO024 P-A-UF14;o5325101TRAN .PUMP No GS SOO-4No. 2000/a2o 4UMP4033NoumpUT5A315226.1,111p115R'431te oo -A4S50too - 4 bo0VB'4 - OGKA-ota0I2S&VUNT417IUY.,Zap- r.0J-D 43 M VAFO RSMIT1Ph;CM - FOR AMLF453-1F'OIU4bOV/ BUS KIT-9177a, Fkl't x4RDV-Busl %atAII).A4501'4-AXABUS).-BAClCI:-2LPte 0IS002lD.ccociio. byI ICS32,5CR, 7S a)3-T)5-CT 5CDT25iTuR-lMAIN ELECTRICAL1

SECTION 9PSARSectionPage9.1.19-1Table 9-1 has been superseded by Table 1 of Item 11of Supplement 1.9.1.29-2A description of the method of calculation of thereactor coolant fission product activities andactivity in the volume control tank is given inItem 16 (E - 4.2) of Supplement 1.9.1.3.99-7Preliminary design parameters of the charging pumpsare given in Item 2 (1 - 18) of Supplement 1.9.59-35A modified flow diagram of the service water systemis presented in Item 1 of Supplement 5.Figure9-4RemarksA modified flow diagram of the auxiliary coolantsystem is presented in Item 1 of Supplement 5.Supplement 8

Start residual heat removal pump (No. 2) and energize motor control center to supply power to-valves. If residual heat removal pump No. 2 did not start, start residual heat removal pump No. 1. Start service water pump No. 4. If service water pump No. 4 did not start, start service water pump No. 5. Start fourth containment ventilation fan.

Related Documents:

Electrical Infrastructure includes an electrical installation, electrical equipment, electrical line or associated equipment for an electrical line. 1.9 Electrical installation As per the Electrical Safety Act 2002 (s15) (a) An electrical installation is a group of items of electrical equipment that—

Grade (9-1) _ 58 (Total for question 1 is 4 marks) 2. Write ̇8̇ as a fraction in its simplest form. . 90. 15 blank Find the fraction, in its

P100 Partial Plumbing Plan ELECTRICAL E001 Electrical Notes E002 Electrical Symbols E003 Energy Compliance ED100 Electrical Demo Plan E100 Electrical Lighting Plan E200 Electrical Power Plan E300 Electrical One-Line E400 Electrical Schedules The Addenda, if any, are as follows: Number Date Pages . .

Electrical Design Group, 86-68430 Technical Approval: cT Eric T. Mendlin, P.E. Electrical Engineer, Electrical Design Group, 86-68430 Peer Review: Manager, Electrical Design Group, 86-68430 Security Review: aan opower Diagnostics and SCADA Group, 86-68450 Submitted: George Girgis, P.E. Chief, Electrical and Mechanical Engineering Division

26 00 00 Electrical General Requirements 26 01 00 Basic Electrical Systems Testing By Electrical Contactor 26 05 00 Basic Electrical Materials and Methods 26 08 00 Commissioning of Electrical Systems 26 10 00 Medium-Voltage Electrical Distribution 26 20 00 Electrical Service & Distribution 26 29 00 Variable Speed Drives 26 30 00 Standby Power .

treated electrical design and the routing of wires, cables, and harnesses, as afterthoughts, separating electrical design from investments in 3D technology and holding back progress toward electrical/mechanical design integration and collaboration. However, continuing to give electrical design short shrift by not integrating it into more efficient

CATIA Electrical Design CATIA V5R30 Electrical Design Electrical Design is the first phase of defining an electrical harness. Before you can begin defining the wire segments and bundles, you need to build the electrical parts. The actual building of the parts is done utilizing part design, generative shape design, and other part related .

positive. The unit of electrical charge is the coulomb (symbol: C). Electrical current An electrical current is the movement of negative electrical charges (electrons) through a conductor (electrical wire, metal foil, etc.). In an electrical circuit, the current flows from the point where the electrical potential is highest to the point where .