Biological Commissioning Testing Of Ballast Water Treatment System .

1y ago
2 Views
2 Downloads
1.87 MB
8 Pages
Last View : 1m ago
Last Download : 3m ago
Upload by : Ellie Forte
Transcription

WHITE PAPERBiological commissioningtesting of ballast watertreatment system installationsUnderstanding the purpose and responsibilitiesApril 2022

WHITE PAPERIntroductionEffective as of 1st June 2022, biological performancemust be assessed during the commissioning of anyballast water treatment system. Biological commissioningtesting (frequently shortened to commissioning testing)is not a validation of the ballast water treatment systemitself, as this is already provided by the system’s typeapproval. Rather, it validates the performance of thespecific installation on board, including the pipes, valvesand other equipment surrounding the ballast watertreatment system.The demand for biological commissioning testing waslaid out at MEPC 74 in an amendment to the InternationalConvention for the Control and Management of Ships’Ballast Water and Sediments (BWM Convention). AtMEPC 75, the procedures were clarified and finalized.Following a brief period when flag states could apply theregulation proactively, biological commissioning testing isnow being mandated globally.Although the requirements have been clarified since theyfirst appeared, there has been a degree of confusionsurrounding them. This paper explains what biologicalcommissioning testing is, as well as why, when and howit should be done.

WHITE PAPERThe commissioningtesting regulationA demand for biological performance testing during thecommissioning of ballast water treatment systems firstarose with Resolution A.1120(40) under the HarmonizedSystem of Survey and Certification (HSSC). The demandwas not part of the BWM Convention, however, which iswhy it was addressed at the MEPC 74 meeting in May2019. There it was approved as a draft amendmentto Regulation E-1 of the BWM Convention, which wasadopted at the MEPC 75 meeting in November 2020.The amendment requires a biological commissioningtest as part of the operational testing of a ballast watertreatment system once the installation is complete andfinalized. As clarified at MEPC 77, this applies to bothnewbuilds and retrofits. The sampling for the test shouldbe performed according to BWM.2/Circ.70/Rev.1,Guidance for the commissioning testing of ballast watermanagement systems. Amendment to BWM ConventionRegulation E-1 adopted at MEPC 75 Implementation voluntary prior to entryinto force Biological commissioning testingmandatory worldwide as of 1st June 2022Between the amendment’s adoption and its entry intoforce on 1st June 2022, biological commissioning testingcould be implemented proactively by flag administrations.Testing procedures, either mandatory or voluntary, havetherefore existed in a number of flag states for some time.As of 1st June 2022, biological commissioning testing ismandatory for all newbuild or retrofit installations of ballast water treatment systems, all over the world.

WHITE PAPERWhat commissioningtesting is – and is notBiological commisioning testing is a response todemands from the market. Shipowners have requestedproof that their installed ballast water treatment systemswill perform according to type approval and meet theIMO D-2 discharge standard. It is important, however,to understand what a biological commissioning testactually validates.Biological commissioning testing does not validate theballast water treatment solution as such. That validationis provided by the type approval, which is an approval ofthe standard ballast water treatment system design.The design itself has already been shown to meet theIMO D-2 discharge standard – so this is not in question. Indicates performance according to IMOD-2 but is not part of type approval Shows that a specific installed systemreplicates the performance defined by itstype approvalRather, biological commissioning testing shows thatthe specific installed system replicates the performancedefined in the type approval. It is a tool for spottingdeviation from the type-approved performance, perhapscaused by a manu facturing defect or an installation error– which may be in a connected pipe or valve rather thanthe ballast water treatment system itself. The biologicalcommissioning test is part of the wider commissioningsurvey that ensures all mechanical, physical, chemicaland biological processes are working properly withinthe system.The whole commissioning survey, including the biologicalcommissioning test, is normally overseen by the flag stateor by a classification society authorized by the flag state,to whom any discrepancies must be reported.

WHITE PAPERThe commissioningtesting procedureBiological commissioning testing is a straightforwardprocedure that is defined step-by-step in BWM.2/Circ.70/Rev.1, Guidance for the commissioning testingof ballast water management systems. It should becarried out with local ambient water and should ideallybe completed in the same location as the installationand the wider commissioning survey. The steps canbe summarized as follows. Sampling and analysis of ambient water (optional)To characterize the ambient water, a sample may becollected during ballast water uptake. This can bedone by any means practical, e.g. using an inline sample port or taking a sample directly from the harbour. Sampling of ballast water dischargeWhen the ballast water treatment process iscompleted, a sample of the ballast water dischargeshould be collected in accordance with ResolutionMEPC.173(58), Guidelines on ballast water sampling(G2). The sample should be representative of thewhole discharge of ballast water from any single tankor combination of tanks being discharged. It shouldbe collected as close as possible to the overboarddischarge point and during ballast water discharge. Evaluation of compliance with IMO D-2The respective samples should be analysed by anindependent laboratory to confirm ballast water treatment performance that indicates compliance withthe IMO D-2 discharge standard. Both size classesincluded in the standard need to be evaluated:- Organisms 50 µm- Organisms 10 µm and 50 µmAlthough the regulation stipulates the use of reliableand accurate indicative analysis methods, none ofthe indicative methods defined in Table 3 of BWM.2/Circ.42/Rev.2 have been fully evaluated. Because thespecified indicative methods are not yet validated,test organizations may instead recommend detailedmethods they know to be reliable and accurate.Detailed analysis methods can mitigate the risk offalse positives leading to failure in the biologicalcommissioning test. They are recommended, forexample, by the members of Global TestNet, anassociation of testing organizations involved withthe certification of ballast water treatment systems.In a position statement, the association writes:“The members of Global TestNet recommendthe use of detailed sample analyses wheneverpossible to ensure high reliability and relevanceof compliance data for the ship owner. Theadditional costs associated with detailed sampleanalyses is considered minor compared to thecost of representative sampling. Further, thetime required for detailed sample analyses iscomparable to that of indicative /Discussions/GloBal TestNetPosition Statement BWMS Commissioning Feb 2019.pdf ReportingThe sampling methods and analysis results shouldbe documented for the flag state administrationor the classification society authorized by the flagstate as part of the written report on the widercommissioning survey.The use of ambient waterBiological commissioning testing is to bedone using local ambient water. Accordingto the guidance, the ambient water shouldbe accepted for testing regardless ofthe level of challenge it poses to theballast water treatment system. This hasimplications that are discussed in the nextsection of this white paper, ConsideringSystem Design Limitations.

WHITE PAPERConsidering SystemDesign LimitationsAs part of the commissioning survey, BWM.2/Circ.70/Rev.1 requires an assessment of the ballast water treatment system’s applicable self-monitoring parameters,e.g. flow rate, pressure, total residual oxidants (TRO)and UV intensity. Not only should the correct operationof all sensors and related equipment be confirmed, theso-called System Design Limitations (SDL) of the ballastwater treatment system should also be considered.Depending on the system’s underlying technology, itsSDL may include a minimum water salinity or a minimumvalue for UV transmittance or intensity. Likewise, theremay be a required minimum holding time.The consideration of SDL has an impact on biologicalcommissioning testing as well. On the one hand, theguidance states that the local ambient water should beaccepted for testing regard less of the challenge it posesto the ballast water treatment system. On the other hand,ambient water that is inappropriate with regard to the SDLwill increase the likelihood of failure.Failure is not certain when a ballast water treatmentsystem is run outside its SDL. However, even a positiveoutcome will be open to interpretation. It is up to the flagstate to decide if favourable results achieved with inappropriate water can be approved.Similarly, there may be instances when a vessel’s scheduleprevents it from applying the SDL-mandated holding time.In such cases, a representative discharge sample cannotbe collected in the same location. Once again, it is up tothe flag state or the appointed classification society todecide how this should be handled.In short, whenever there is a conflict between the ambientwater’s char acteristics and the ballast water treatmentsystem’s SDL, it is up to the flag state to decide the courseof action. The guidance states that the testing shouldbe evaluated to the satisfaction of the flag state administration, but it remains to be seen how most flag stateswill deal with this in practice. A likely scenario is that flagstates will require testing in more appropriate conditionsafter the vessel has left the yard. In this event, a short-termInternational BWM Certificate with a Condition of Authoritywould be issued, requiring testing within 2–3 months. Ambient water is to be accepted for testing,even if it falls outside system SDL Flag state determines the course of action if theambient water is inappropriate for the system

WHITE PAPERResponsibilities associatedwith commissioning testingBiological commissioning testing is required after theinstallation of any ballast water treatment system whosecommissioning survey falls after 1st June 2022. Thisapplies to both newbuild and retrofit installations.The collection and analysis of representative water samples must be performed to the flag state’s satisfaction byan independent laboratory, i.e. without the involvementof the ballast water treatment system manufacturer, theengineering company or the shipyard. Depending on therelevant classification society and its rules, it may also benecessary to choose the laboratory from that society’slist of approved service providers.Ultimately, it is the shipowner who is responsible for making testing arrangements with an appropriate independent laboratory. However, the guidance does not preventa system supplier from recommending laboratories oracting as a go-between – so long as the supplier takes nopart in the sample collection and analysis. It is also possible for the supplier to advise when running the systemduring the biological commissioning test.If offered, such support services fall outside the systemsupplier’s standard commissioning scope. Biologicalcommissioning testing is not part of the system’s technical commissioning, and its focus extends beyond theballast water treatment system itself. As described earlier,the testing does not validate the ballast water treatmentsystem as such, but rather the specific installation with allits valves, pipework and other connections.Because the entire installation is involved, there aremany factors that can influence the outcome of biologicalcommissioning testing. Even a seemingly small oversight,such as not cleaning the ballast water tanks and piping priorto installation, can result in failure to indicate compliancewith the IMO D-2 discharge standard. If the installationfails the biological commissioning test, it is the shipowner’sresponsibility to initiate fault-finding and corrective actions– and to arrange for testing again at an additional cost.Likewise, it is the shipowner’s responsibility to apply for ashort-term BWM Certificate in the meantime.A knowledgeable system supplier can mitigate the risk offailure by providing recommendations and checklists priorto biological commissioning testing. If the supplier is alsopresent when running the ballast water treatment systemduring the test, inadvertent errors by an inexperiencedcrew can be avoided. Together, such simple services canhelp ensure that the vessel leaves the shipyard with itsinternational BWM Certificate in hand. Responsibility for arranging sampling and analysis byan independent laboratory rests with the shipowner System suppliers may assist with recommendations,laboratory coordination and running the system– but not the sampling and analysis Support in biological commissioning testingfalls outside a system supplier’s standardcommissioning scopeFor shipowners installing Alfa Laval PureBallast 3Alfa Laval stays up to date with marine legislation, including therequirements for biological commissioning testing. When installingAlfa Laval PureBallast 3 ballast water treatment systems, shipownersshould discuss preparations and support options with their Alfa Lavalrepresentative before contacting an independent laboratory.

This is Alfa LavalAlfa Laval is active in the areas of Energy, Marine,and Food & Water, offering its expertise, products,and service to a wide range of industries in some100 countries. The company is committed tooptimizing processes, creating responsible growth,and driving progress – always going the extra mile tosupport customers in achieving their business goalsand sustainability targets.Alfa Laval’s innovative technologies are dedicated topurifying, refining, and reusing materials, promotingmore responsible use of natural resources. Theycontribute to improved energy efficiency and heatrecovery, better water treatment, and reducedemissions. Thereby, Alfa Laval is not only acceleratingsuccess for its customers, but also for people and theplanet. Making the world better, every day. It’s allabout Advancing better .How to contact Alfa LavalContact details for all countries are continually updatedon our web site. Please visit www.alfalaval.comto access the information.How to contact Alfa LavalUp-to-date Alfa Laval contact details for all countries arealways available on our website at www.alfalaval.com100002342-2-EN 2204Alfa Laval reserves the right to change specifications without prior notification.

treatment system once the installation is complete and finalized. As clarified at MEPC 77, this applies to both newbuilds and retrofits. The sampling for the test should be performed according to BWM.2/Circ.70/Rev.1, Guidance for the commissioning testing of ballast water management systems. Between the amendment's adoption and its entry into

Related Documents:

128 GE 480-XLH-TC-P-IP Rapid Start Ballast P 129 GE 487-SLH-TC-P-IP Rapid Start Ballast P 130 GE 487-XLH-TC-P-IP Rapid Start Ballast P 131 GE 960-VLH-TC-P-IP Rapid Start Ballast P 132 GE 532-BR-TC-P-IP Instant Start Ballast P 133 GE 213-TC-P-IP Instant Start Ballast P

4. ReCom KIT INSTALLATION P.5 To separate the fixture from the ballast: To connect the fixture to the ballast: 1 Ensure the light kit is disconnected from any power and controller. 2 Disconnect ballast output plug from reflector input cable. 3 Lift the unlocking latch inside the bracket box. 4 Slide reflector bracket out from ballast “T” slot/s. 1 Change ballast position to desired .

Defining Commissioning for GSA Buildings Commissioning ensures the delivery of efficient, durable, and comfortable facilities. ASHRAE Guideline 0‐2019 The Commissioning Process defines commissioning as follows: “Commissioning Process (Cx): a quality‐focused process for enhancing the delivery of a project. The

Commissioning Your Way To High Performance Buildings THE COMMISSIONING PROCESS Core Phases Of The Commissioning Process PRE-DESIGN STAGE The owner selects the design team, which includes the commissioning authority (CxA). Commissioning authority consists of the initial Cx team and team leader, and they are involved from project initiation

F40T12 - Std. Magnetic Ballast 192 11590 60 E.S. Magnetic Ballast 172 11590 67 F34T12 - Std. Magnetic Ballast 164 9500 58 E.S. Magnetic Ballast 144 9500 66 F32T8/700 - Magnetic 142 10640 75 F32T8/800 - R.S. Electronic 122 10380 85 FO32/XP - QT4x32IS 114 10800 95 Weight: 2.8 lbs each (approx) 49555 QT3x32/120IS-PAL 49557 QT4x32/120IS-PAL

Lamp ballast Matrix and ballast Cross reference August 2017 Lamp Drivers. 2 3 Master T5 Electronic fixed output ballast for Fluorescent Lamps Lamp type Philips Master TL5 HE . Electronic ballast is not compatible with lamp KEY. 6 7 Lamp type Philips Master PL-L 4 Pin Philips PL-L Xtra 4 Pin Osram Dulux L Lumilux 4 Pin

The temperature the ballast reaches depends on the tempera-ture of the area surrounding it — plus the heat-conducting surface touching the ballast. Ballasts should be installed in a manner that avoids future overheating. To maintain normal ballast temperature, you should: 1. Mount the ballast against a flat surface of heavy gauge

Biology 1413 Introductory Zoology – 4Supplement to Lab Manual; Ziser 2015.12 Lab Reports Each student will complete a Lab Report (see Table of Contents)for the material covered in each of 4 Lab Practicals. Lab reports are at the end of each section of material for each practical (see Table of Contents).