STATION CAPACITY PLANNING GUIDANCENetwork RailNovember 2016

CONTENTS1THE OVERVIEW . 52UNDERTAKING CAPACITY ASSESSMENTS . .1Identifying the need for an assessment . 7Remits . 7Proposals . 8Demand forecasts . 8Data requirement and collection . 9SPACE REQUIREMENTS FOR NORMAL OPERATION . 10Passenger demand concepts . 10Revenue protection . 12Platforms . 16Canopies . 20Concourses . 22Access and interchange . 25PLANNING FOR ABNORMAL CONDITIONS . 34Perturbation . 34Construction . 36Special events . 36Emergency evacuation. 36STATION PERFORMANCE CATEGORISATION . 39Station performance categorisation . 39

November 2016ForewordWith significant investment plannedfor stations across the network, it isimportant that the industry adopts aconsistent approach to the planningand design of our stations.Network Rail Station Capacity Planning GuidanceIn the past decade, the number of railpassengers has grown by 50 percent andstations like London Waterloo and LondonVictoria now handle more people per daythan the UK’s busiest airports. However, untilrecent years, there has not been any newmajor infrastructure and many of our stationsare busier than ever.Since Victorian times, our railway hasn’t justmoved passengers and freight; it hasgenerated, and spread, prosperity. That iswhy we are continuously investing in ournetwork with several high profile schemessuch as Thameslink, Crossrail, EdinburghGlasgow Improvement Programme andNorthern Hub. Station upgrades and newfacilities will play a key role in deliveringthese schemes and helping to increasecapacity, safety and passenger comfort. Theimportance of stations in delivering a betterrailway is clearer than ever.With significant investment plans for stationsacross the nation, it is important that theindustry adopts a consistent approach forplanning and design of station environments.This document provides a series of bestpractice guidelines for the design andplanning of railway stations to guarantee thatwe continue to deliver value for money andexcellent passenger experience across thenetwork.Isabelle MilfordStation Capacity ManagerModern stations are the shop windows of ourrailway. In addition to providing access totrain services our stations are used asmeeting places and provide opportunities forretail and leisure. Passengers expect, anddeserve, a positive experience at stations aspart of their overall journey on the railway.Ease of access, readily available travelinformation and ambient station space willimprove passenger satisfaction and theattractiveness of rail as a mode.3

November 2016Executive SummaryThis document provides guidancefor undertaking capacityassessments for stations acrossthe network. It stipulates thethresholds for planning and designof passenger areas with aconsideration for ‘value for money’.Network Rail Station Capacity Planning GuidanceThe guidance shall be used by all partiesinvolved in the station design processincluding, but not exclusive to, Network Railstaff, architects, train operating companies(TOC) and engineering and planningconsultants.This document supersedes the previousversion published in May 2011. The guidancewill be periodically updated to reflect ongoingresearch, consultation and changes inlegislation and shall be read in conjunctionwith;The application of this guidance ensuresstation design supports the Industry andNetwork Rail’s objectives, namely: Station Design Principles for Network RailGuide, March 2015 Develop and maintain consistently highperforming stations that support safemovement of passengers and customersatisfaction Deliver station improvements anddesigns that are fit for purpose, costeffective and sustainable.This guidance provides the informationrequired by architects and designers toproduce an outline station design focussingon public areas. It includes all calculationsrequired to assess whether a station meetsNetwork Rail’s aspirations regardingpassenger comfort and safety in the stationenvironments, during normal operations andemergency/perturbation situations. Spaces and Places for Everyone, NetworkRail Inclusive Design Strategy, 2015 Design Standards for Accessible RailwayStations, Department for Transport andTransport Scotland, March 2015 Other Rail Industry Standards andBuilding codes referred to in Appendix FQueries or comments regarding thisdocument are welcomed and should be sentto: stationcapacity@networkrail.co.uk.It also provides a good practice guide forundertaking capacity assessments. Thisinformation is relevant for those responsiblefor station capacity assessment studies andcontains the Network Rail requirements withregards to analysis and deliverables.4

November 20161 The OverviewIntroduction to the basicprinciples of spatial planning forpublic areas and Network Rail’splanning criteria.Network Rail Station Capacity Planning GuidanceThis guidance applies to the spatial aspectsof station planning for public areas duringnormal operations and abnormal conditions.Requirements for staff accommodation andareas that are only used by tenants are notcovered in this guidance.It is important to understand that the capacityrequirements included here shall be treatedas a minimum. Depending on the projectaspirations it may be desirable to deliberatelydesign public areas in excess of the spatialrequirements outlined here.The following chapters provide methods forsizing public areas that have sufficient spaceto allow unimpeded circulation ofpassengers, and also for reasonable comfortin waiting areas.The Fruin levels of Service (LoS) specifiedhere relate to Network Rail’s aspirations ofproviding adequate level of comfort withoutmaking stations uneconomically large. Theseguidelines are applicable to existing and newstations. Station layouts shall always beassessed in relation to the peak usage that iseither based on a survey or predicted futuredemand.5

November 2016Network Rail Station Capacity Planning GuidancePassengers have different needs and behavedifferently within any given stationenvironment (see Figure 1-2). They walk atdifferent speeds on flat and steppedsurfaces. For example, most passengerswalk at speeds between 0.6 to 2.0m/s on flatsurfaces in free-flow conditions. An averageadult may walk at a speed of 1.5m/s or aboveon flat surfaces in normal conditions1. Incrowded conditions however, the walkspeeds are significantly lower.Passenger demand shall be classified intothe following categories. Analysts shallconsider site specific factors that may affectpassenger demand and diversity e.g.availability of step-free access, stationsconnecting to airports or stations nearhospitals. Such assumptions shall be agreedwith the Network Rail’s Station CapacityTeam (NR SCT).Commuters are normally travelling to andfrom work or place of study and are familiarwith the station layout and train services. Atmost stations, a large proportion ofpassengers during the peak periods areregular commuters.1The passenger walk speeds quoted here are based onLeisure travellers are infrequent users ofthe railway; may require assistance in termsof wayfinding and train information. Theygenerally tend to arrive at the station earlier,and hence dwell longer in comparison withregular commuters. At some stations, a largeproportion of users can be of this type on aFriday afternoon and at weekends or duringspecial events. They may also carry someform of luggage.Passengers in wheelchairs need step freeaccess and may require assistance inaccessing train services or other facilities at astation.Passengers with reduced mobility mayhave a physical or cognitive condition whichaffects their ability to navigate within a stationenvironment. Such passengers require morespace, time or even staff assistance.Passengers with luggage require morespace depending upon the size and shape ofluggage they are carrying. This includespassengers carrying small rucksacks, largeshopping bags, large musical instruments,regular or fold-up bikes and large suitcases.Passengers with young children andinfants in pushchairs may be slow-movingand prefer to remain in groups.anecdotal evidence gathered from various stations on theNational Rail network. These are consistent with thepassenger walk speeds observed by Transport for London atLondon Underground stations.6

November 20162 Undertaking CapacityAssessmentsGuidance for analysts and otherparties involved in scoping andproducing capacityassessments studies.Network Rail Station Capacity Planning Guidance Evaluate the impact on passengers dueto changes in timetables, introduction ofnew services or rolling stock2.1 Identifying the need for anassessmentStation capacity assessments shall beundertaken for the design and planning of allnew railway stations and for schemes thataffect the usage and flow of passengers instation environments. For any scheme,consideration shall be given to the stationlayout, volume of passengers and complexityof movement, GRIP (Governance for RailwayInvestment Projects) stage and the level ofintervention. Particular consideration shall begiven to station category2, strategicimportance along the Route or within thelocal area.NR SCT shall be consulted at the earliestopportunity in order to identify the need of anassessment and to help define a remit.2.2 RemitsA remit shall clearly set out the following withrespect to the assessment that is required: Context, the strategic fit and the problemstatement Objectives of the study3, scope,interdependenciesThe objectives of an assessment maytypically include: Indicates any gaps in availability ofpassenger and train information Benchmark existing station performance Operational and other assumptions Optimise station layouts Option selection and designdevelopment Evidence for a business case Test crowd management, constructionimpact and evacuation plans Programme milestones and deadlines.Remits shall be developed by the Client,Sponsor or Manager in conjunction with, orreviewed by, the NR SCT. Following on fromthis, a proposal will be provided by the NRSCT or an external consultant.32Better Rail Stations, November 2009.Clearly set out what is expected from the assessment i.e.what are the questions that need answering.7

November 2016Network Rail Station Capacity Planning Guidance2.3 Proposals2.4 Demand forecastsThe NR SCT or an external consultant shallrespond to the remit with a project proposal.This proposal shall be sent to the Client,Sponsor or Manager and reviewed by the NRSCT.A vast majority of station users are railpassengers, but some stations also offer avariety of retail, attracting a significantnumber of visitors who are not rail users.Some stations may also provide access toother transport modes, such as trams ormetro services. A station may also generatefootfall by offering a short-cut between twoexternal locations and hence it may benecessary to include such non-railbackground demand; e.g. the new concourseat Birmingham New Street station connecttwo sides of the city centre.It is important that respondents understandthe objectives and various stages of anassessment to develop a comprehensiveproposal.Each proposal shall demonstrate: Good understanding of the remit, thecontext, ability to identify key areas thatneed to be analysed and anyconstraints. Strong capability in the discipline andselection of an appropriate method foranalysis based on site complexity. Detailed cost and resource breakdowndemonstrating value for money. Project plan showing alignment withwider NR delivery programme. Allowance for review and feedback fromNR SCT throughout the project.Capacity assessments shall at least consideran interim and future year scenario. Anyprofiling of passenger demand across thepeak in relation to train loadings shall beagreed with NR SCT.Network Rail Economic Planners can providedemand forecasts based on Route Studiesand other forecasting tools used in theindustry. Forecasts developed by aconsultant or another organisation will needagreement with the Network Rail EconomicPlanners at the start of any assessmentproject.The Client, Sponsor or Manager will approveand initiate an assessment project once theNR SCT has completed a technical andcapability review of the proposals.8

November 2016Network Rail Station Capacity Planning Guidance2.5 Data requirement and collection2.5.1 Passenger and train dataWherever possible, surveys shall becommissioned to establish a goodunderstanding of passenger numbers in andaround stations and any station specificcharacteristics in relation to train services,interchange and operational controls. Datarequirements may vary based on the scopeof the assessment and project objectives.A survey shall cover two morning andafternoon weekday peaks (e.g. 0700 – 1000and 1600 to 1900hrs) and any other timeswhen passenger volumes are known to behigh. Validation counts and observationsshall be made to ensure consistency in thedata that is collected. At some stations it maybe necessary to include other times duringweekdays and weekends depending on theproject objectives and station usage.Network Rail Project Managers shall reviewthe checklist in Appendix A, to identify if therequired data is readily available and startsourcing this information from Network Railstudies, train operating companies, LocalAuthorities, Transport for London, Merseyrailor other third party developers.Any gaps in the data shall be clearly definedin the remit. In all cases, NR SCT shall beconsulted to determine the suitability of usingexisting data. Appendix A includes a briefdescription of the different datasets requiredand suggested methods of data collection.NR SCT can organise surveys if required.Where surveys are being commissioned byconsultants the proposed methodology andscope will require approval from the NR SCTand the Station Manager. It is important thatcareful consideration is given to the planningand safe operations during any survey.For new stations, demand data may comefrom forecasting models and the suitability ofsuch forecasts and underlying assumptionsshall be discussed with the NR SCT.2.5.2 Station layout and operationsAll assessments require an accuratedefinition of the physical layout of the stationbeing assessed; typically this informationshall be in electronic CAD format.The configuration of existing infrastructuresuch as escalators, ticket barriers and stationentry gates shall be observed and included inthe analysis.Passenger behaviour in relation to concoursedwelling, train announcements, location andformat of CIS (customer informationscreens), wayfinding and crowd managementmeasures such as ‘keep left / right’, one-wayroutes shall be considered in assessments.9

November 20163 Space Requirementsfor Normal OperationThe space requirementsspecified in this section arebased on specific planningcriteria for each type of stationelement for normal operatingconditions. The methodsdescribed here ensure thatadequate level of comfort isachieved in public areas ofstations without making themuneconomically large.Network Rail Station Capacity Planning Guidance3.1 Passenger demand conceptsStation capacity assessments shall be basedon passenger demand from the busiest timeperiods. At most stations the busiest timesare normally the morning and afternoonpeaks as passengers travel to and returnfrom work.In some cases a separate assessment forweekends and special events may berequired. Special events requiremanagement controls and may involvequeuing passengers in a safe environment.This can have a direct impact on spacerequirements in and around stations.Non-rail users shall be included whereapplicable i.e. demand associated withstation retail and thoroughfare.The passenger demand used inassessments shall be based on survey dataand relevant forecasts. Network RailEconomic Planners shall be consultedregarding demand forecasts.The following concepts of demand data areused in this document:Total number of exiting passengers shallbe derived using the alighting loads from themaximum possible number of trains thatarrive during the busiest 5-minute period on atypical day. The busiest train shall have itsalighting load increased by 25% to factor indelays to the service.Total number of entering passengers shall

November 2016 Network Rail Station Capacity Planning Guidance 6 with the station layout and train services. At Passengers have different needs and behave differently within any given station environment (see Figure 1-

Related Documents:

Station 3: Five-Finger Retell card Station 3: Green Questions card Station 3: Key Words card Station 3: Problem-Solution card Station 3: Red Questions card Station 3: Shared Retelling Cards Station 3: Story Retelling Rope Station 3: SWBS card Station 3: Track the Character’s Feelings card Station 3: V.I.P. Fiction card Station 3: V.I.P .

7 Station No. Station Name in Chinese Station Name in English A1 臺北車站 Taipei Main Station A2 三重站 Sanchong Station A3 新北產業園區站 New Taipei Industrial Park Station A4 新莊副都心站 Xinzhuang Fuduxin Sation A5 泰山站 Taishan Station A6 泰山貴和站(明志科大) Taishan Guihe Station A7 體育大學站 National Taiwan Sport University Station

Total Station (Geodimeter/Trimble) 4 Total Station (Leica TPS Series) 10 Total Station (Leica Robotic) 15 Total Station (Leica/Wild Older Models) 23 Total Station (Nikon) 24 Total Station (Pentax) 25 Total Station (Sokkia Set) 27 Total Station (Sokkia Robotic) 31 Total Station (Spectra Focus 30) 33 Total St

years - depending on how often the system is powered down. The more the system's power is off, the shorter the battery's life. Connection points for the CO and station DDK connectors. 82400 - 36 Station 1 Trunk 4 Battery Trunk 3 Trunk 2 Trunk 1 Station 2 Station 3 Station 4 Station 5 Station 6 Station 7 Station 8 HDWR1B.QXD 5/18/98 4:51 PM .

3 1st station: jesus is condemned to death 2nd station: jesus takes up his cross 3rd station: jesus falls for the first time 4th station: jesus meets his mother 5th station: simon of cyrene helps jesus to carry the cross 6th station: veronica wipes the face of jesus 7th station: jesus falls for the second time 8th station: jesus consoles the women of jerusalem 9th station: jesus falls for the .

Transport Stock Chaser Personnel Carrier Burden Carrier BSC BUV BBC 4-wheel Cushion Walkie Reach StackerWalkie Reach Stacker 5,500lb capacity 4,500lb capacity 6,500lb capacity 6,500lb capacity 10,000lb towing capacity 4,400 - 5,500lb capacity 600lb capacity 1,000lb capacity . MAY 2014

Advanced Commercial Controller Owner's Manual, Installation, and Programming Instructions for ACC and ACC Decoder Controllers ACC-1200 12 Station Controller, 42 Station Capacity, Metal Cabinet ACC-1200-PP 12 Station Controller, 42 Station Capacity, Plastic Pedestal ACC-99D 2-Wire Decoder Controller with 99 Station Capacity, Metal Cabinet

AutoCAD education, and apply them right away to your fi rst real drawing. Let us take a look at the Layers Properties Manager. This is AutoCAD’s Layers dialog box, where everything important related to layers happens. Open a new fi le and, if you decide to use toolbars, also bring up the Layer toolbar. We take a closer look at that toolbar in Section 3.3 , but for now you need only the .