Baseline Risk Assessment And Hazard Identification

2y ago
55 Views
3 Downloads
1.08 MB
7 Pages
Last View : 10d ago
Last Download : 3m ago
Upload by : Kaden Thurman
Transcription

HartRAOPO Box 443Krugersdorp 1740South AfricaTel: 012 301 3100Int. Code: 27 12http://www.hartrao.ac.zaBaseline Risk Assessment and HazardIdentificationProject:Supply, Delivery, Install and Commissioning of a backup generator,automatic mains failure panel, and diesel trailer for the VGOS radiotelescope at the Hartebeesthoek Radio Astronomy ObservatoryDate of issue: 27 February 2017

Table of ContentsTITLE . 3EXECUTIVE SUMMARY . 3DESCRIPTION OF WORK . 3DESCRIPTION OF SITE. 3EXISTING SERVICES. 3HAZARD IDENTIFICATION AND RISK ASSESSMENT (HIRA) . 6RESULTS . 6HIGH RISK (200 – 400 POINTS). 7SUBSTANTIAL RISK (70 – 200 POINTS) . 7LOW RISK (20 - 70 POINTS) . 7CONCLUSION . 7

General InformationTitleThe baseline risk assessment based on Occupational Health and Safety issues relevant to the supplyand installation of a backup electric generator, automatic mains failure panel, and diesel trailer.Executive SummaryA baseline risk assessment is required which identifies possible hazards and the risks involved withthe work to be undertaken. In this document these risks are identified in order for contractors toplan for and mitigate all risks to ensure a safe working environment.Description of WorkA new radio telescope is being built at the Hartebeesthoek Radio Astronomy Observatory situatedon Farm 502JQ, Broederstroom rd, Hartbeesthoek, Gauteng. The civil works have already beencompleted on site and a mini-sub is currently providing power to the installation. The equipment willeventually be used on a 24/7 basis and it is necessary to have a backup/standby generator installedin the case of power failures.The work entails: The supply of a 400 kVA backup diesel, self-enclosed generator delivered, offloaded andinstalled on site.The supply and connection of an Automatic Mains Failure panel which will switch betweenthe generator and Eskom feed lines.The supply of a diesel trailer which will be used to store additional fuel and fill up thegenerator reservoir as needed.Description of SiteThe Hartebeesthoek Radio Astronomy Observatory is located on Farm 502JQ, Broederstroom road,Hartebeesthoek, 1739 just north of Krugersdorp in the Gauteng province.Figure 1 indicates the layout of the site with figure 2 showing a photo of the buildings. The mini-subis located outside the fenced area.Existing services Clean, drinkable water is available on-site.The mini-sub currently has a single-phase socket for equipment and circuit breakers arealready installed (i.e. 3-phase electricity is available if the connections are made to thecircuit breakers).The as-built drawings will be provided to the successful bidder and the services will beshown.

General InformationFigure 1: Location of mini-sub, and proposed generator, is indicated by the "Concrete Slab" white block to the West (left)

General InformationFigure 2: Recent photo of the site (Feb 2017).

Baseline risk assessmentHazard Identification and Risk Assessment (HIRA)During the hazard identification and risk assessment the presence of occupational health stressesand safety factors were considered. The following terms have been used for the risk assessment.ConsequenceThe potential degree of harm, potential severity of injuries and/or health; and/orthe number of people potentially affected.ExposureHow often and for how long people are exposed to a hazard.FrequencyOr Likelihood. Chance per unit time. Frequency Exposure X Probability.HarmInjuries, occupational diseases or losses.HazardConditions, circumstances or objects with the potential to cause harm.ProbabilityChance that a person or persons will be harmed during the exposure.RiskLikelihood that harm from a particular hazard will occur. Risk Consequence XFrequencyTo determine the risk factor the consequence, exposure and probability of occupational disease andinjury were assessed and weights allocated on a scale of 1 – 5, with 1 being the highest risk and 5 thelowest risk. Each of these weights carries a certain point value as 321Probability106310.5The risk profile is obtained by multiplying the associated weights. E.g. a fire hazard can have highconsequence (40) with a low exposure (2) and medium probability (3) will result in 40 x 2 x 3 240risk score which is classified as a high risk. This classification is as follows.More than 400200 - 40070 – 20020 – 70Below 20Very High RiskHigh RiskSubstantial RiskLow RiskPossibility of riskConsider stopping actionImmediate remedial actionRemedial action requiredAttention necessaryRisk is possible, but acceptableResultsThe above HIRA process was followed based on the works to be done on site for this project, i.e. theinstallation of a generator and automatic mains failure panel on site. The following risks wereidentified.

Baseline risk assessmentHigh Risk (200 – 400 points) Heavy equipment can fall on persons or be placed upon person’s limbs. E.g. offloading of thegenerator and AMF panel.Electrocution during installation. E.g. Electrical cables need to be connected to the generatoras well as AMF panel.Fire. E.g. there are trees and savannah grass nearby the mini-sub and generator which cancatch fire if there is an electrical short.Explosions. E.g. The generator, and diesel trailer, may have fuel which can be ignited andunder certain conditions explode.Contact with plant and equipment during operation. E.g. The generator will be tested andcommissioned on site and will therefore be in operation with people close by.Substantial Risk (70 – 200 points) Noise and fumes from equipment (generator) and tools used during installation can pose ahealth risk.Weather conditions – rain during installation can increase the likelihood of electrocution.Low Risk (20 - 70 points) As the site is located on a farm, there is some wildlife (warthogs, various types of buck,jackals, baboons, and monkeys) roaming around.Snakes, scorpions, bees, wasps, ticks and spiders have also been spotted on the farm.ConclusionFrom the HIRA investigation there are predominantly physical hazards (crushing, electrocution,entanglement) that are high risk factors. For each of these items the risk can be eliminated orcontrolled to a safe level. Correct PPE should be worn for offloading and installation of equipment.The electricity supply should be switch off when connecting the electrical cables and installing theAMF panel.Noise from equipment (generator) and tools used during installation poses a substantial risk but canbe mitigated by using the correct PPE (ear plugs, etc.) The electrocution probability which isincreased in wet conditions can also be mitigated by postponing the installation/physical electricalconnections to a time when it does not rain.Finally, there is a possibility of spotting local wildlife (though no big predators) and also somevenomous animals. These animals are not known to attack of their own accord, only when agitatedor surprised. Care must be taken to be observant when walking around site and a safe distanceshould be kept from any such animal.

The baseline risk assessment based on Occupational Health and Safety issues relevant to the supply and installation of a backup electric generator, automatic mains failure panel, and diesel trailer. Executive Summary A baseline risk assessment is required which identifies possible hazar

Related Documents:

provider specialty, index year (2014-17), baseline anxiety, baseline dyspnea, baseline congestive heart failure, baseline angina pectoris, baseline renal disease, baseline obstructive sleep apnea, baseline pneumonia, age, baseline Elixhauser comorbidity index score, baseline COPD total medical costs, baseline exacerbation episode

2.4 UNCERTAINTIES IN THE SEISMIC HAZARD ASSESSMENT 35 2.5 SEISMIC HAZARD RESULTS 37 2.5.1 Hazard curves for selected cities 37 2.5.2 Uniform hazard spectra for selected cities 39 2.5.3 Seismic hazard maps 40 2.5.4 Set of stochastic scenarios 43 2.5.5 Comparison of the results with the elastic design spectra defined in NSCE-02 and Eurocode-8 43

a GHS hazard class and category. Signal Words: "Danger" or "Warning" are used to emphasize hazards and indicate the relative level of severity of the hazard, assigned to a GHS hazard class and category. Hazard Statements: Standard phrases assigned to a hazard class and category that describe the nature of the hazard.

PLANT HAZARD AND RISK ASSESSMENT WORKSHEET (PHA) Page 5 of 20 Potential Hazards Hazard Describe Hazard Controls Currently In Place on Plant Current Risk Level New or Additional Controls Required on Plant Final Risk Level New or Additional Controls Action By: (Name and Date) Action Verified a

Risk management Risk evaluation Management options Implementation Control Risk assessment Hazard identification Hazard characterization Exposure assessment Risk characterization . National Food Agency Hazard Risk . National Food Agency Synopsis . National Food Agency . yet a decision needs to be made .

Hazard Assessment and Risk Analysis Project Risk Assessment of Open Stairwell Fall Exposure by Masons As safety officer for XYZ Masonry, I have been tasked with the hazard analysis and risk assessment of what will be an upcoming safety concern at a new site. In a recent pre-job safety analysis

Information presented in these previous sections has been used in the baseline risk assessment to assist in assessing public health risk. Reference to appropriate sections of the RI Report should be made for detailed discussions of the background information. 7.1.3 Organization The baseline risk assessment is organized into the following sections:

universiteti mesdhetar orari i gjeneruar:10/14/2019 asc timetables lidership b10 i. hebovija 3deget e qeverisjes 203 s. demaliaj e drejte fiskale 204 a.alsula histori e mnd 1 b10 n. rama administrim publik 207 g. veshaj tdqe 1