Chapter 2 - Proposed Action And Alternatives

2y ago
9 Views
2 Downloads
234.17 KB
6 Pages
Last View : 1m ago
Last Download : 3m ago
Upload by : Axel Lin
Transcription

Chapter 2 - Proposed Action andAlternatives2.1 IntroductionThe Proposed Action is authorization to increase Steinaker Reservoir’s normalwater surface elevation from 5,517.8 feet to 5,520.5 feet. This would be anincrease of 2.7 feet and would allow the reservoir to be filled to the currentspillway crest elevation. This EA will be used to analyze the potential effects tothe human environment and will serve to guide Reclamation’s decision, alongwith other pertinent information, whether to implement the Proposed Action.If authorized to proceed, UWCD would be allowed to fill the reservoir to theproposed normal water surface elevation for a period of time not to exceed 60days each water year (during the summer irrigation season). This 60-daylimitation is imposed by Reclamation’s Risk Analysis (U.S. Department of theInterior, 2005).In conjunction with this authorization, UWCD (and Reclamation) would workwith Steinaker State Park management to modify or relocate certain recreationalfacilities. The Proposed Action Alternative is analyzed in this EA, along with aNo Action Alternative to facilitate comparison of potential effects between thetwo.2.2 No Action AlternativeUnder the No Action Alternative, Reclamation would not authorize UWCD to fillthe reservoir to the proposed new normal water surface elevation, and State Parkfacilities and infrastructure would not need to be relocated and/or reconstructed.The No Action Alternative does not require any changes to project features.2.3 Proposed Action AlternativeThe Proposed Action Alternative is to increase Steinaker Reservoir’s normalwater surface elevation from 5,517.8 feet to 5,520.5 feet for a period of time notto exceed 60 days per water year. This would be an increase of 2.7 feet andwould allow the reservoir to be filled to the current spillway crest elevation. Thereservoir would be allowed to fill to this new, higher normal water surfaceelevation during the spring runoff season, for the 60 day period stated above.Total area of new inundation would be approximately 30 acres. Most of this areais vegetated by sagebrush.4

If Reclamation decides to implement the Proposed Action and authorizes UWCDto operate the reservoir at the higher normal water surface elevation, portions ofSteinaker State Park facilities and infrastructure would need to be relocated and/orreconstructed. The following actions would be undertaken by UWCD inconjunction with the Proposed Action (see Map 2 and 3 for locations of thefollowing facilities and infrastructure):1.Soils within the area are mostly sand and could be highly susceptible toerosion from wave action on the new higher shoreline. Erosion can affectboth water quality and recreation. This erosion could affect approximately30 acres. Most of this affected area is located adjacent to the WestCampground and Boat Dock. If deemed necessary by Reclamation and/orthe State Park, erosion would be repaired as necessary, including whererecreational facilities or water quality are affected.2.The current location of the Lower Pavilion Area would be partiallyinundated by the higher water level in the reservoir. The structure shouldbe able to withstand the increased lake level; however, some erosion mayoccur to the sand material around the post bases. The supports areanchored by concrete at each post location and there is no slab under thepavilion. This pavilion may need to be disassembled and moved to higherground. This can be accomplished by disassembling the cover and placingnew footings at a location. This new location would be within 200 feet ofthe structures current location and be higher on the bank.3.The proposed maximum water level would rise onto the asphalt roadwayabove the concrete section of the West Shore Boat Ramp. The granularbase and subgrade materials under the roadway could be saturated withpossible detrimental effects to the roadway. This ramp would need to beextended at the current location to withstand the proposed maximum waterelevation. The concrete boat ramp would need to be extendedapproximately 35 feet and widened to match the lower concrete sectionwidth. Riprap would need to be extended along the new concrete section.The parking area associated with the boat dock would be reconstructed atits present location. The restroom leach field adjacent to the boat rampwas monitored during tests of the proposed maximum water elevationduring the spring seasons of 2005 and 2006. These tests showed that theproposed elevation increase would not impact the leach field. All leachfields in the state park will maintain a 100-foot horizontal set back and a2-foot vertical limit from any high water level. The boat dock dead-mananchor would not need to be relocated.4.The light pole and power feed adjacent to the West Shore Boat Rampwould need to be relocated approximately 75 feet to the west and higheron the bank, or it must be disconnected or otherwise protected to prevent apossible electrical safety hazard for the public.5

5.The West Campground pads for picnic tables and fire pits would be onlyslightly above the proposed elevated waterline. This could cause a safetyhazard due to the existence of water, several feet in depth, within severalfeet of the pad sites. These pad sites would need to be protected fromwave action by gently sloping the gradient to the water and placing riprapover this slope. Access to the shore would be provided by the constructionof gravel walkways.6.Within the North Group Use Area, a water supply line would besubmerged by the raised water level. This supply line would to be movedto higher ground (Map 4). Water supply line valve risers must be raisedabove the anticipated lake level, with freeboard for wave action. There isa concrete pipe outlet that drains the parking lot that would be partiallysubmerged during high water. It would need to be checked after highwater periods to make sure debris has not accumulated. The higher waterlevel will be close to the roadway surface for the access road of the grouparea. This roadway would need to be monitored to determine potentialroadway damage. If damage does occur the road would be raised and/orprotected. The bottom of the vault toilet is located above the anticipatedraised water surface; however, the toilet would be within the established50-foot horizontal setback from the reservoir’s shore. Administrativecontrols such as pumping the sewage from the toilet early and often orconstruction of a containment berm around the toilet would beaccomplished to mitigate potential problems.7.Within the Scenic Byway Area, some displays and kiosks would beaffected by the raised water level. The interpretive trail (approximately ½mile in length) would be submerged along the entire length, along withtwo foot bridges. These facilities would be raised by the construction ofan elevated boardwalk or by a berm. The raised water level will be next tothe roadway into the area and sections of the parking area would be underwater. One vault toilet in the area would be above the raised water surfaceand outside the 50-foot setback area. Another toilet was removed becauseit would be within the established 50-foot horizontal setback from theshoreline.8.Fire rings that are below the proposed new high water level must bemoved to keep camp site open. Barriers (wheel stops or jersey barriers)have been installed in parking areas where it was deemed necessary toprevent vehicles from rolling into the reservoir.9.DURING INUNDATION: All roadways and parking areas next to thewater surface must be monitored to assess any potential road damage. TheLower Pavilion area must be monitored to determine if damage isoccurring to the structure and if measures can be taken to reinforce the6

post foundation. Wave erosion must be monitored along the entireelevated waterline of the reservoir. Wave heights in strong winds can be 1to 2 feet and would travel into 2 to 3 camp sites. Camp sites may need tobe closed during periods of high wind. The North Group Area would needto be monitored during high winds, due to the potential for water toovertop the roadway. All restroom leach fields and vault type toiletswould need to be monitored and pumped as necessary to preventcontamination at the higher reservoir level.7

Map 2. Steinaker Reservoir State Park Recreational FacilitiesSt8

Map 3. Steinaker Reservoir State Park Work Locations9

new footings at a location. This new location would be within 200 feet of the structures current location and be higher on the bank. 3. The proposed maximum water level would rise onto the asphalt roadway above the concrete section of the West Shore Boat Ramp. The granular base and sub

Related Documents:

Part One: Heir of Ash Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 Chapter 12 Chapter 13 Chapter 14 Chapter 15 Chapter 16 Chapter 17 Chapter 18 Chapter 19 Chapter 20 Chapter 21 Chapter 22 Chapter 23 Chapter 24 Chapter 25 Chapter 26 Chapter 27 Chapter 28 Chapter 29 Chapter 30 .

TO KILL A MOCKINGBIRD. Contents Dedication Epigraph Part One Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 Part Two Chapter 12 Chapter 13 Chapter 14 Chapter 15 Chapter 16 Chapter 17 Chapter 18. Chapter 19 Chapter 20 Chapter 21 Chapter 22 Chapter 23 Chapter 24 Chapter 25 Chapter 26

DEDICATION PART ONE Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 PART TWO Chapter 12 Chapter 13 Chapter 14 Chapter 15 Chapter 16 Chapter 17 Chapter 18 Chapter 19 Chapter 20 Chapter 21 Chapter 22 Chapter 23 .

About the husband’s secret. Dedication Epigraph Pandora Monday Chapter One Chapter Two Chapter Three Chapter Four Chapter Five Tuesday Chapter Six Chapter Seven. Chapter Eight Chapter Nine Chapter Ten Chapter Eleven Chapter Twelve Chapter Thirteen Chapter Fourteen Chapter Fifteen Chapter Sixteen Chapter Seventeen Chapter Eighteen

18.4 35 18.5 35 I Solutions to Applying the Concepts Questions II Answers to End-of-chapter Conceptual Questions Chapter 1 37 Chapter 2 38 Chapter 3 39 Chapter 4 40 Chapter 5 43 Chapter 6 45 Chapter 7 46 Chapter 8 47 Chapter 9 50 Chapter 10 52 Chapter 11 55 Chapter 12 56 Chapter 13 57 Chapter 14 61 Chapter 15 62 Chapter 16 63 Chapter 17 65 .

HUNTER. Special thanks to Kate Cary. Contents Cover Title Page Prologue Chapter 1 Chapter 2 Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 Chapter 12 Chapter 13 Chapter 14 Chapter 15 Chapter 16 Chapter 17 Chapter

Chapter 3 Chapter 4 Chapter 5 Chapter 6 Chapter 7 Chapter 8 Chapter 9 Chapter 10 Chapter 11 Chapter 12 Chapter 13 Chapter 14 Chapter 15 Chapter 16 Chapter 17 Chapter 18 Chapter 19 Chapter 20 . Within was a room as familiar to her as her home back in Oparium. A large desk was situated i

architectural schematic design t0.01 title sheet a1.1 proposed site plan a2.1 proposed basement plan a2.2 proposed first floor plan a2.3 proposed second floor plan a4.1 proposed roof plan a5.1 proposed section a-a & b-b a5.2 proposed section 3 a6.1 proposed east & north elevations a6.2 proposed west & south elevations civil c-1.1 property .