CLEAN WATER SERVICES TIGARD, OREGON BIDDING REQUIREMENTS AND CONTRACT DOCUMENTS for the construction of the DURHAM ADVANCED WASTEWATER TREATMENT FACILITY WASSTRIP IMPROVEMENTS VOLUME 1 DIVISION 00 THROUGH DIVISION 10 PROJECT NO. 7045 **** **** JACOBS Corvallis, Oregon October 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES TIGARD, OREGON BIDDING REQUIREMENTS AND CONTRACT SPECIFICATIONS for the construction of the DURHAM ADVANCED WASTEWATER TREATMENT FACILITY WASSTRIP IMPROVEMENTS PROFESSIONAL OF RECORD CERTIFICATION(S): Signing as the Professional of Record for the Sections listed below: Sections: 01012, 01110, 01140, 01292, 01320, 01324, 01329, 01330, 01350, 01352, 01410, 01424, 01450, 01500, 01505, 01530, 01532, 01555, 01560, 01600, 01640, 01732, 01738, 01756, 01770, 01782 Craig Massie PW\DEN003\050058\D3244305 OCTOBER 2020 SEALS PAGE 00007 - 1

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Signing as the Professional of Record for the Sections listed below: Sections: 01451, 01612, 05050, 05500, 05516, 05519, 05530, 10400 EXP. 06-30-2022 Luke Aaron Scoggins SEALS PAGE 00007 - 2 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS Signing as the Professional of Record for the Sections listed below: Sections: 11115, 11284, 11285, 11300, 11315 Alan Git Hung Chang PW\DEN003\050058\D3244305 OCTOBER 2020 SEALS PAGE 00007 - 3

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Signing as the Professional of Record for the Sections listed below: Sections: 09900, 15060, 15080, 15200, 15200.01, 15200.03, 15200.08, 15200.10, 15200.13, 15202, 15205, 15810, 15892, 15950, 15955 EXP. 06-20-21 Jason Krumsick SEALS PAGE 00007 - 4 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS Signing as the Professional of Record for the Sections listed below: Sections: 16050, 16052, 16060, 16070, 16075, 16123, 16130, 16134, 16140, 16150, 16222, 16262, 16411, 16422, 16442, 16444, 16510, 16950 Ryan S. Harbert PW\DEN003\050058\D3244305 OCTOBER 2020 SEALS PAGE 00007 - 5

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Signing as the Professional of Record for the Sections listed below: Sections: 17050, 17101, 17201, 17208, 17301, 17302, 17310, 17401, 17402, 17403, 17404, 17405, 17406, 17510, 17710, 17901, 17903 Jeffrey D. Kanyuch END OF SECTION SEALS PAGE 00007 - 6 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS TABLE OF CONTENTS PROJECT NO. 7045 Pages VOLUME 1 PART 1—PROCUREMENT REQUIREMENTS 00030 00100 00300 Advertisement for Bids . 1- 3 Instructions to Bidders . 1- 17 Bid Forms. 1- 15 PART 2—CONTRACTING REQUIREMENTS CONTRACTING FORMS 00500 Agreement . 1- 15 PROJECT FORMS 00610 00630 Performance Bond Form . 1Payment Bond Form . 1- 4 3 CONDITIONS OF THE CONTRACT 00700 00800 00810 General Conditions . 1- 43 Supplementary Conditions . 1- 32 Oregon Prevailing Wage Rates . 1- 1 PART 3—SPECIFICATIONS DIVISION 01—GENERAL REQUIREMENTS 01012 01110 01140 01292 01320 01324 Partnering . 1Summary of Work. 1Work Restrictions . 1Schedule of Values . 1Supplement: Exhibit A – Example Schedule of Values. 1Web-Based Construction Management . 1Construction Schedule . 1- PW\DEN003\050058\D3244305 OCTOBER 2020 2 6 9 2 4 6 10 TABLE OF CONTENTS 00 01 10 - 1

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Pages 01329 01330 01350 01352 01410 01424 01450 01451 01500 01505 01530 01532 01555 01560 01600 01612 01640 01732 01738 01756 01770 01782 TABLE OF CONTENTS 00 01 10 - 2 Safety Plan . 1Supplements: Oregon OSHA – Confined Spaces and Permit Spaces . 1Facilities Management – Hot Work Yellow Permit . 1Submittal Procedures . 1Special Procedures . 1Alteration Project Procedures . 1Permits and Regulatory Requirements . 1Abbreviations . 1Quality Control . 1Special Inspection, Observation, and Testing . 1Supplements: Contractor’s Statement of Responsibilities. 1Fabricator’s Certificate of Compliance. 1Statement of Special Inspections . 1Temporary Facilities and Controls . 1Mobilization . 1Protection of Existing Facilities . 1Site Conditions Surveys . 1Site Access and Storage . 1Temporary Environmental Controls . 1Product Requirements . 1Anchorage and Bracing . 1Manufacturers’ Services and Training . 1Supplements: Outline of Training Session . 1Training Matrix . 1Cutting and Patching . 1Selective Demolition. 1Testing and Facility Startup . 1Supplements: Equipment Supplier’s Certificate of Proper Installation. 1Field Instrumentation Calibration Sheet . 1Startup Binder (Table of Contents Example) . 1Equipment and Documentation Tracking Log . 1Example Startup Activities Sequence . 1ORT 1 Form . 1ORT 2 Form . 1Closeout Procedures . 1Operation and Maintenance Data . 1Supplement: Equipment Information Sheet . 1- 3 36 4 9 1 4 3 10 2 5 2 1 11 8 1 4 1 3 2 4 6 5 2 1 3 4 11 1 1 3 1 3 1 1 3 4 2 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS Pages DIVISIONS 02 THROUGH 4 (NOT USED) DIVISION 05—METALS 05050 05500 05516 05519 05530 Welding . 1Supplement: Welding and Nondestructive Testing . 1Metal Fabrications . 1Aluminum Railings . 1Post-Installed Anchors . 1Metal Gratings . 1- 6 1 11 8 7 5 DIVISIONS 06 THROUGH 08 (NOT USED) DIVISION 09—FINISHES 09900 Painting and Coating . 1- 19 Supplements: Paint System Data Sheet (PSDS) . 1- 1 Paint Product Data Sheet (PPDS) . 1- 1 DIVISION 10—SPECIALTIES 10400 Signage. 1- 4 VOLUME 2 DIVISION 11—EQUIPMENT 11115 11284 11285 11300 11315 Horizontal End Suction Centrifugal Pumps. 1Rotary Drum Thickeners. 1Polymer Blend Unit . 1Chopper Pumps and Nozzle Mixing Systems . 1Progressing Cavity Pumps . 1Supplement: P-Transfer Pumps Nos. 1 and 2 Data Sheet . 1- 10 22 12 12 5 3 DIVISIONS 12 THROUGH 14 (NOT USED) DIVISION 15—MECHANICAL 15060 15080 Piping Support Systems . 1- 9 Process Piping Insulation . 1- 5 Supplement: Service and Insulation Thickness Table . 1- 1 PW\DEN003\050058\D3244305 OCTOBER 2020 TABLE OF CONTENTS 00 01 10 - 3

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Pages 15200 15200.01 15200.03 15200.08 15200.10 15200.13 15202 15205 15810 15892 15950 15955 Process Piping – General . 1Cement-Mortar Ductile Iron Pipe and Fittings Data Sheet. 1Carbon Steel Pipe and Fittings – General Service Data Sheet . 1Stainless Steel Pipe and Fittings – General Service Data Sheet . 1Polyvinyl Chloride (PVC) Pipe and Fittings Data Sheet . 1Copper and Copper Alloy Pipe, Tubing, and Fittings Data Sheet . 1Process Valves and Operators. 1Supplements: Power Operated Modulating Valve Schedule . 1Power Operated Open/Close Valve Schedule . 1Self-Regulated Valve Schedule . 1Process Piping Specialties . 1Metal Ducts and Accessories . 1Foul Air Ductwork and Accessories . 1Testing, Adjusting, and Balancing for HVAC . 1Process Piping Leakage Testing . 1- 20 4 5 3 2 1 17 1 1 1 9 16 14 4 5 DIVISION 16—ELECTRICAL 16050 16052 16060 16070 16075 16123 16130 16134 16140 16150 16222 16262 16411 16422 16442 16444 16510 16950 TABLE OF CONTENTS 00 01 10 - 4 Common Work Results for Electrical . 1Hazardous Classified Area Construction . 1Grounding and Bonding. 1Hangers and Supports . 1Electrical Identification. 1600-Volt or Less Wires and Cables . 1Conduits . 1Boxes. 1Wiring Devices . 1Low Voltage Wire Connections. 1Low Voltage Motors Up to 500 Horsepower . 1Supplement: Motor Data Sheet . 1Variable Frequency Drives 0.5 to 50 Horsepower . 1Disconnect Switches . 1Motor Starters . 1Panelboards . 1Low Voltage Motor Control Centers . 1Lighting: LED Luminaires. 1Field Electrical Acceptance Tests . 1- 25 5 5 6 12 22 21 9 9 5 11 2 18 7 10 4 10 7 13 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS Pages DIVISION 17—PROCESS INSTRUMENTATION AND CONTROLS 17050 17101 17201 17208 17301 17302 17310 17401 17402 17403 17404 17405 17406 17510 17710 17901 17903 Basic Measurement and Control Instrumentation Materials and Methods. 1Control Loop Descriptions. 1Supplements: WAS EQ Control Loop Description . 1WAS Pre-Thickening Feed Control Loop Description. 1WASSTRIP RDT Pre-Thickening Control Loop Description . 1WASSTRIP P-Release Tank Control Loop Description . 1Thickening Centrifuge Feed Pumps Control Loop Description . 1Liquid Polymer for Dewatering Control Loop Description. 1Liquid Polymer for Thickening Control Loop Description . 1Digester Complex 1 Air Flow Monitoring Control Loop Description . 1Level Measurement: Switches . 1Level Measurement: Radar . 1Flow Measurement: Switches . 1Flow Measurement: Magnetic Flowmeters . 1Flow Measurement: Ultrasonic Flowmeters . 1Pressure/Vacuum Measurement: Diaphragm and Annular Seals . 1Pressure/Vacuum Measurement: Instrument Valves . 1Pressure/Vacuum Measurement: Switches . 1Pressure/Vacuum Measurement: Gauges . 1Pressure/Vacuum Measurement: Direct . 1Pressure/Vacuum Measurement: Differential . 1Analyzers: Sludge Density Meter . 1Control Systems: Panels, Enclosures, and Panel Components . 1Supplement: Control Panel Schedule . 1Instrument List . 1Supplement: Instrument List . 1Schedules: I/O List. 1Supplement: PLC I/O List. 1- PW\DEN003\050058\D3244305 OCTOBER 2020 25 1 2 4 5 3 3 4 6 2 5 5 6 6 6 6 6 6 6 6 6 29 1 2 4 1 3 TABLE OF CONTENTS 00 01 10 - 5

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Pages VOLUME 3 PART 4—DRAWINGS END OF SECTION TABLE OF CONTENTS 00 01 10 - 6 PW\DEN003\050058\D3244305 OCTOBER 2020

PART 1 PROCUREMENT REQUIREMENTS

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS ADVERTISEMENT FOR BIDS Sealed Bids for construction of the Durham WASSTRIP Improvements Project No. 7045 (Project) will be accepted by Michelle Mann electronically via Bid Locker at https://bidlocker.us/details/1290 Itb Durham Wasstrip Improvements Project (Bid Locker) until 2:00 p.m., local time, Thursday, November 12, 2020. Before Bidders can submit their Bids, they will need to register with Bid Locker at https://bidlocker.us/Home/bidlockerus. There is no cost to register. Any Bids received after the specified time will not be considered. First-Tier Subcontractor Disclosure Forms must be electronically submitted to Bid Locker at or before 4:00 p.m. local time on the same day through Bid Locker (Deadline). If Bidder fails to submit a disclosure form with the information required by the stated Deadline, the Bid will be deemed nonresponsive and will not be considered. Owner will not accept Bids by facsimile or email. Bids will then be publicly opened and read aloud by telephone conference at 2:00 p.m. local time on November 12, 2020 at Owner’s Office. Bidders can attend the opening by calling the telephone conference number (503) 681-4498. Contractor shall complete the work as specified or indicated in Owner’s Contract Documents for the Project. The Project contemplated consists of, but is not limited to furnishing all labor, materials and equipment necessary to: Convert an existing concrete tank to a Waste Activated Sludge (WAS) Equalization Tank with associated piping and valves. Install new WAS Pre-Thickening Feed Pumps and associated piping and valves in the existing Aeration Tunnel. Install new WAS piping and valves from the WAS Pre-Thickening Feed Pumps in the Aeration Tunnel, through the tunnel system, Solids Building Basement to the Rotary Drum Thickeners in Digester Complex 1 (DC1). Install two Rotary Drum Thickeners and their appurtenances including wash water booster pumps, controls, sludge hoppers, access platforms and polymer mixers in DC1. Install new P-Release Transfer Pumps in the ground level of DC1. Install a pumped jet mixing system including piping, nozzles, and a mix pump associated with the P-release Tank (a former anaerobic digester) in lower level of DC1. Install an odor control system for the P-release Tank consisting of ducting and an at grade carbon cannister odor control system. PW\DEN003\050058\D3244305 OCTOBER 2020 ADVERTISEMENT FOR BIDS 00030 - 1

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES Piping and HVAC system modifications within DC1. Install new Thickening Centrifuge Feed Pumps in the lower level of DC1. Install new piping and valves from the Thickening Centrifuge Feed Pumps through the tunnel system to piping located in the Solids Building. Modify piping associated with the chemical sludge system to change the point of discharge to the filter drain. Install new polymer blending units and associated piping, valves, and controls in the existing Solids Building. Install exposed and buried piping, valves, and instruments associated with the equipment and systems outlined above. Install new motor controls, variable frequency drives, electrical panelboards, transformers, instrumentation and control panels, associated conduits, conductors, and other appurtenances necessary to complete the Work and to provide a complete and functional system constructed in accordance with the Contract Documents. The Work Site is located at Durham Advanced Water Resource Recovery (AWRRF) Facility, 16580 SW 85th Ave, Tigard, OR 97224 (Site). The Work is a public works project subject to ORS 279C.800 to 279C.870. The estimated construction cost of the Work is 3,910,000. The Bidding Documents are entitled “Durham WASSTRIP Improvements Project No. 7045.” Bidding Documents and Bid Results should be downloaded from the Owner's Website at http://bids.cleanwaterservices.org (Website) under the Project name. Prospective Bidders are responsible for obtaining any Addenda from either Owner's Website under the Project name or by using the links provided in automatic emails that come from the Owner. If problems are experienced downloading the Bidding Documents, please contact Michelle Mann at (503) 547-8035. Each Bid must be submitted on the prescribed Bid Form and accompanied by Bid security as prescribed in the Instructions to Bidders. Bidders must deliver the original of the Bid security to Owner’s office at Rock Creek AWRRF, Engineering Building, 3235 S.E. River Road, Hillsboro, OR 97123 within five business days of the Deadline or Owner may declare the Bid nonresponsive. The Successful Bidder will be required to furnish the additional bond(s) and insurance prescribed in the Bidding Documents. ADVERTISEMENT FOR BIDS 00030 - 2 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS Prior to submission of its Bid, Bidder shall be registered with the Oregon Construction Contractors Board. The Work does not involve asbestos, so the requirements of ORS 468A.700 through 468A.760 shall not apply. Bidders shall be qualified in accordance with the applicable parts of ORS 279C in order to submit a Bid for public work in Oregon. To address technical issues, contact the Engineer: Craig Massie, (541) 768-3478, Craig.Massie@jacobs.com. Prospective Bidders are required to schedule and attend a prebid conference and Site visit on Tuesday, October 20, 2020 between 1:00 p.m. to 4:00 p.m. Site visit appointments can be scheduled by contacting Michelle Mann at mannm@cleanwaterservices.org. Each one-hour session will be scheduled on a first-come, first-served basis, with a limited number of attendees allowed at each session. Attendees will be required wear a mask when on-site. Michelle will provide additional instructions when scheduling the appointments. Representatives of Owner and Engineer will be present to discuss the Project. Owner reserves its right to reject all Bids or any Bid not conforming to the intent and purpose of the Bidding Documents. Dated this 7th day of October, 2020. By Clean Water Services END OF SECTION PW\DEN003\050058\D3244305 OCTOBER 2020 ADVERTISEMENT FOR BIDS 00030 - 3

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS INSTRUCTIONS TO BIDDERS 1. DEFINED TERMS 1.1. Terms used in these Instructions to Bidders and the Advertisement for Bids which are defined in the General Conditions have the meanings indicated in the General Conditions and Supplementary Conditions. Certain additional terms used in the Bidding Documents have the meanings indicated below which are applicable to both the singular and plural thereof: 1.1.1.1 Owner’s Office—The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered. 1.1.2.1 Bidder—One who submits a Bid directly to Owner, as distinct from a sub bidder, who submits a price or quote to a Bidder. 1.1.3.1 Successful Bidder—Lowest, responsible and responsive Bidder to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award. 2. COPIES OF BIDDING DOCUMENTS 2.1. Complete sets of Bidding Documents shall be used in preparing Bids. Neither Owner nor Engineer assumes responsibility for errors or misinterpretations resulting from use of incomplete sets of Bidding Documents. 2.2. The Bidding Documents can be downloaded from the Owner’s Website at http://bids.cleanwaterservices.org (Website). Prospective Bidders are responsible for obtaining any Addenda from District's Website listed above or using links from emails from Owner. If problems are experienced downloading the Bidding Documents, please contact Michelle Mann at the Owner’s Office at (503) 547-8035 or by email to Mannm@cleanwaterservices.org. Full-size Drawings may be obtained from Owner at cost of reproduction and handling, plus postage for mailing (if mailing is requested) and half-size drawings and specs are 250 per set. Drawings will only be made available to firms on the Bid Holders List having complete sets of Bidding Documents. 2.3. Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license or grant for any other use. 3. QUALIFICATIONS OF BIDDERS 3.1. To demonstrate qualifications to perform the Work, the apparent Successful Bidder and other Bidders as determined by Owner, must be prepared to submit within seven calendar days after Owner’s written request, evidence such as financial data, previous PW\DEN003\050058\D3244305 OCTOBER 2020 INSTRUCTIONS TO BIDDERS 00100 - 1

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES experience, present commitments, and other such data as may be called for in the Bidding Documents. 3.2. Each Bid must contain evidence of Bidder’s qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to Contract award. 3.3. Nothing indicated herein will prejudice Owner’s right to seek additional pertinent information as is provided in Article 24 – Evaluation of Bids and Award of Contract. 3.4. Bidders and every Subcontractor performing Work on the Project must have filed with the Construction Contractors Board a public works bond in the amount of 30,000 with a corporate surety authorized to do business in the State of Oregon before starting Work on the Project unless exempt under ORS 279C.836(4), (7), (8), or (9). 3.5. In order to perform public work, Bidder and its Subcontractors, prior to award of Contract or as otherwise required by the jurisdiction, shall hold or obtain such licenses as required by State Statutes, and federal and local Laws and Regulations. 3.6. Bidder is advised to carefully review those portions of the Bid Form requiring representations and certifications. 3.7. Bidder shall not be listed on the Bureau of Labor and Industries list of persons having violated prevailing wage rate laws as required in ORS 701.227. 3.8. Bidder shall not be in violation of any tax laws as required in ORS 305.385. 3.9. Bidder shall have a drug-testing program as required in ORS 279C.505. 3.10. Bidders for public work in Oregon shall be qualified in conformance with ORS Chapter 279C, in the manner designated in the Advertisement for Bids. 4. REGISTRATION REQUIREMENTS 4.1. A person, partnership, corporation, limited liability company or joint venture shall have a current, valid license issued by the Oregon Construction Contractors Board, as required by ORS Chapter 701 with respect to licensing, prior to submitting a Bid to do work as a Contractor or Subcontractor. 4.2. Asbestos is not anticipated to be encountered during the project. 5. EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND SITE 5.1. It is the responsibility of each Bidder before submitting a Bid to: 5.1.1.1 Examine thoroughly the Bidding Documents and other related data identified in the Bidding Documents. INSTRUCTIONS TO BIDDERS 00100 - 2 PW\DEN003\050058\D3244305 OCTOBER 2020

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS 5.1.2.1 Visit the Site and become familiar with and satisfy Bidder as to the general, local and Site conditions that may affect cost, progress, or performance of the Work. 5.1.3.1 Become familiar with and satisfy Bidder as to federal, state, and local Laws and Regulations that may affect cost, progress, or performance of the Work. 5.1.4.1 Study and carefully correlate the Bidder’s observations with the Bidding Documents. 5.1.5.1 Carefully study all: 5.1.5.1.Reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph 5.03 of the Supplementary Conditions as containing reliable “Technical Data”. 5.1.5.2.Reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in Paragraph 5.06 of the Supplementary Conditions as containing reliable “Technical Data”. 5.1.6.1 Consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on: 5.1.6.1.Cost, progress, and performance of the Work. 5.1.6.2.Means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents. 5.1.6.3.Bidder’s safety precautions and programs. 5.1.7.1 Agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) Bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents. PW\DEN003\050058\D3244305 OCTOBER 2020 INSTRUCTIONS TO BIDDERS 00100 - 3

DURHAM AWWTF WASSTRIP IMPROVEMENTS CLEAN WATER SERVICES 5.1.8.1 Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents. 5.1.9.1 To promptly notify the Engineer of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in or between the Bidding Documents and such other related data and

CLEAN WATER SERVICES DURHAM AWWTF WASSTRIP IMPROVEMENTS PW\DEN003\050058\D3244305 ADVERTISEMENT FOR BIDS OCTOBER 2020 00030 - 1 ADVERTISEMENT FOR BIDS Sealed Bids for construction of the Durham WASSTRIP Improvements Project No. 7045 (Project) will be accepted by Michelle Mann electronically via Bid Locker at

Related Documents:

Tigard PD Strategic Dashboard Explanation. The Tigard Police Strategic Dashboard was created as a management tool for the Tigard Police leadership to review crime statistics, patterns, calls for service, staffing, budget, and monitor

Oregon State Bar Professional Liability Fund 16037 S.W. Upper Boones Ferry Road, Suite 300 Tigard, Oregon 97224 P.O. Box 231600 Tigard, Oregon 97281 www.osbplf.org 503-639-6911 1-800-452-1639 2009 Board of Directors and Officers James G. Rice – Chair – Portland Ronald L. Bryant – Vice Chair – Redmond

Jun 02, 2016 · Oregon State Bar Professional Liability Fund 16037 S.W. Upper Boones Ferry Road, Suite 300 Tigard, Oregon 97224 P.O. Box 231600 Tigard, Oregon 97281 www.osbplf.org 503-639-6911 1-800-452-1639 2016 Board of Directors and Officers Robert D. Newell – C

clean water services durham awwtf wasstrip improvements pw\den003\050058\d3244305 seals page october 2020 00007 - 1 clean water services tigard, oregon bidding requirements and contract specifications for the construction of the durham advanced wastewater treatment facility wasstrip improvements professional of record certification(s):

Motor Vehicle Bill of Sale Template. Click the following link to find out more details about . does oregon require a bill of sale, bill of sale form oregon, oregon bill of sale fillable, bill of sale oregon template, state of oregon bill of sale, bill of sale oregon form oregon dmv bill of sale, dmv bill of sale

May 19, 2014 · Tigard Wilsonville Oregon City CLARK COUNT Y Gresham Clean air and clean water do not stop at city limits . Oregon Administrative Rules 162-010-0000 through 162-010-0330 incorporated in the Minimum Standards for . The requirements relating to insurance and fidelity bond coverage.

Jan 07, 2005 · Public Employees Retirement System Headquarters: 11410 S.W. 68th Parkway, Tigard, OR Oregon Mailing Address: P.O. Box 23700 Tigard, OR 97281-3700 (503) 598-7377 TTY (503) 603-7766

In contrast to the prevailing pattern of small apartments surrounding it, Oleson Woods Apartments in Tigard, Oregon—a suburb just south of Portland—is composed primarily of three- and four-bedroom townhouse-style rental units that are suitable for large families. Located between an existing 30-year-old, two-story garden apartment