BOND IN PRESTRESSED CONCRETE END SUPPORT EFFECTS

2y ago
35 Views
2 Downloads
2.08 MB
79 Pages
Last View : 28d ago
Last Download : 3m ago
Upload by : Farrah Jaffe
Transcription

BOND IN PRESTRESSED CONCRETEPROGRESS REPORT NO. 3END SUPPORT EFFECTS ON ULTIMATE FLEXURAL BONDIN PRE-TENSIONED BEAMSStephen H. CowenDavid A. VanHornPart of an Investigation Sponsored by:PENNSYLVANIA DEPARTMENT OF HIGHWAYSU. S. DEPARTMENT OF COMMERCEBUREAU OF PUBLIC ROADSREINFORCED CONCRETE RESEARCH COUNCILFritz Engineering LaboratoryDepartment of Civil EngineeringLehigh UniversityBethlehem, PennsylvaniaJanuary 1967; Fritz Engineering Laboratory Report No. 309.3

TABLE OF CONTENTSABSTRACT1I.INTRODUCTION2II.OBJECTIVE AND SCOPE9III. 2.1Objective92.2Scope9TEST SPECIMENS133.1Description of Test Specimens133.2Materials17Prestressing Steel17Shear mentation21 IV.(3.4.1Strains223.4.2Strand Slip243.4.3Deflection Measurement2425TESTS4.1Test Procedure254.2Test Results and Discussion26

,, PageModes of Failure26Cracking of the Concrete26Behavior of Test Specimens284.2.2Load-Deflection Curves324.2.3Force in the Strand at VariousStages334.2.4Average Bond Stress344.2.5Post Bond Slip Load Capacity374.2.1 V.SUMMARY AND CONCLUSIONS38VI.GENERAL DESIGN 49IX.TABLES53X.FIGURES59XI.REFERENCES75!Ic

'.,ABSTRACTThis investigation is a pilot study of the bond characteristics of prestressed members pre-tensioned with multiplelayers of strand.The primary objective was to develop informa-tion in regard to the additional flexural bond attained in strandsfound near the lower extremity of pre-tensioned members as a result of the pinching effect of the end reactions.The results of tests conducted on three beams pretensioned with two layers of 1/2-in., 270K strand are presentedtand compared with similar flexural bond tests by Badaliance andVanHorn on beams with a single-layer strand pattern.The testresults clearly indicate that additional flexural bond is developed as a result of the pinching effect of the end reactionon the prestressing steel near the soffit of the member.Thestudy also demonstrated that bond slip occurred at loads whichwere considerably below both the actual and the computed ultimateflexural capacities of the members.It is recommended that a more extensive study be madein the future, encompassing several variables such as verticalstrand spacing and strand pattern.

I INTRODUCTIONIn a reinforced concrete member, forces are normallytransmitted directly between the concrete and the reinforcingsteel.The medium by which such a transmittal is accomplishedis referred to as bond.In conventional concrete members rein-forced with deformed steel bars, this bonding action is the result of a combination of adhesion and mechanical resistancebetween the steel and concrete.When considering pre-tensionedprestressed concrete members, the bonding action between theprestressing element and the concrete is a result of friction aswell as adhesion and mechanical resistance . In the fabrication of a pre-tensioned prestressedconcrete member the prestressing strand is first tensioned to thedesired stress level.Concrete is then cast about the strand andallowed to cure until it gains sufficient strength for release.The strands are then freed from the tensioning mechanism, causinga gradual build-up of force within the member.The stress in theprestressing tendon varies from zero at the end of the member tofull prestress at some distance inside the concrete.This distanceis known as the transfer length, and the bonding action responsiblefor this stress gradient is called transfer or anchorage bond.The transfer length varies with the type, size,·· andsurface condition of the strand, the concrete strength at release,-2-

and the rate of release.For anyone strand, in a particularconcrete member, the transfer length will be greatest in beamsthat have been subjected to rapid release, and shortest inmembers where the prestress transfer was gradual.When a beam is loaded the steel reinforcement helpsthe concrete resist the externally applied moment.To accomplishthis in a pre-tensioned flexural member, the circumferentialforces are transmitted from the concrete to the prestressingstrand by bond.This type of bond is called flexural bond.In discussing flexural bond in pre-tensioned prestressedmembers, two phases must be considered, before and after crackingof concrete.Before cracking occurs, the increase in the tensilesteel stress and the resulting increase in flexural bond stressis relatively small.This flexural bond stress can be calculatedthrough the use of a free body diagram of an uncracked concretemember, which yielded the expressionne A Vs s ITo CWhen cracking occurs under flexure, the bond stress risesin the vicinity of the crack, and bond failure, resulting in slipbetween the strand and the concrete, occurs in the region adjacentto the crack.As the load is further increased, the high bondstress continues as a wave from the original crack toward the end -3-

of the member.When the peak of this wave of high bond stressreaches the prestress transfer zone, the increase in steel stressresulting from bond slip decreases the diameter of the strandwith the resulting decrease of frictional bond.It is at thispoint that strand movement at the ends of the beam can be detected.This phenomenon is known as bond slip.In members prestressed with strands, the helical sh?peof the individual wires provides mechanical resistance so that thebeam can support additional load even after the strand slipsa the beam ends.Of increasing interest in the characteristics of bondin pre-tensioned prestressed concrete members is the componentresulting from friction.When the prestressing steel is tensionedto the desired tensile stress, the diameter of the strand contracts due to the effect of Poisson's ratio.After release thestress in the strand increases from zero at the end of the memberto some constant level at the end of the transfer length.Thisvariation in the tensile stress of the strand causes an expansionin the diameter of the strand in proportion to the reduction dueto the initial tensile stress.This expansion is resisted by theconcrete surrounding the strand, resulting in a radial force atthe interface.This interface pressure between the strand and theconcrete is for the most part responsible for the development of the,frictional component of bond.However, at the member ends in the-4-

area surrounding the reaction, the concrete is locally compresseddue to the vertical force of the reaction.It is felt that thiscompressive force adds to the frictional component of the bondby increasing the radical pressure at the steel-concrete interface.This phenomenon may be termed the pinching effect of thereaction.In beams containing layers of strand, it is 'possiblethat bond slip may be more critical in the strands at the upperlevels, since the pinching action is less effective at the higherlevel in the beam.The nature of bond was reported in 1954 by Janney.9Four sizes of prestressing wire and one size of prestressingstrand (5/16-in.) were used in a study aimed at the evaluationof both transfer and anchorage bond characteristics.The prin-cipal variables considered were diameter, surface condition, anddegree of initial pre-tensioning of the wire reinforcement.Avariation in transfer length was noted for wires of variousdiameters, and it was found that the surface condition alsoplayed a major role.An elastic analysis of the deformationsoccurring when pre-tensioned steel is released, suggested thatbond is largely a result of friction between concrete and steel.In 1956, Thorsen14showed that the bond forces in theend zones of a pre-tensioned member differs from the bond forcesin the interior regions.It was further demonstrated that bothtypes of bond can be determined by a curve indicating the maximum -5-

tension which can be developed ina tendon, without slip, atvarious distances from the end of a member.In 1957, Nordby and Venuti13tested 27 beams cast fromconventional and expanded shale aggregate concrete.were tested both statically and in fatigue.The beamsThe results indicatedthat the embedment length was the governing factor against failurerather than bond stress as computed from conventional equations.The equationuu 3f As s4TTDLewas used to compute the average bond stress at the time of failure.In 1958, a study by Dinsmore, Deutsch and Montemayor5reported the results of an investigation of both transfer andflexural bond in test specimens pre-tensioned with 7/l6-in. strands.It was concluded that friction played a major role in the development of both types of bond.In 1959, Hanson and Kaar7.announced the results of a de-tailed investigation of flexural bond in beams pre-tensioned withseven-wire str.and of 1/4, 3/8, and 1/2 in. diameter.The primaryobject was to find the effect of strand size and embedment lengthon the bonding action and strength of the member.It was foundthat bond slip occurs in pre-tensioned members when the wave offlexural bond stress reaches the prestress transfer length.-6-A

series of curves were developed to predict the necessary embedment lengths for the various sizes of strand tested . A study conducted at the University of Illinois was3reported by Anderson, Rider, and Sozen in 1964. The investigation included a study of both anchorage and flexural bond in pretensioned prestressed members.Pull-out test specimens werefabricated to simulate both end block conditions and the tensileregion of a beam.In addition several beams with non-prestressedstrands were tested.The three types of strand used were:7/16-in.round seven-wire strand, 7/16-in. rectangular seven-wire strand,and 1/4-in. rectangular three-wire strand.Embedment lengths andtransfer lengths were determined, and it was emphasized that anadditional axial stress may be developed in the strand after bondslip has occurred.In 1965, Badaliance and VanHorn4at Lehigh Universityreported a study of the bond characteristics of 1/2-in. 270Kseven-wire prestressing strand.The results of thirteen tests ontwelve beams were evaluated to determine the embedment lengthnecessary to produce bond slip.The critical observed embedmentlength for the strand tested was found to be 80 inches.lytical concept was developed.An ana-However, because of lack of In-formation on the development of friction, mechanical action andthe coefficient of creep in concrete, a comparison between theexperimental and analytical values was not possible.-7-

To date, no investigation has been directed toward anattempt to isolate the added quantity of frictional bond broughtabout by the pinching effect of the reaction in pre-tensionedprestressed concrete members.-8-

II.2.1OBJECTIVE AND SCOPEObjectiveThe principal objectives of this investigation were(1) the development of information on the effect of the pinchingof the reaction on the flexural bond characteristics of prestressed concrete beams pre-tensioned with 1/2-in. 270K seven-wirestrand, and (2) comparison of this information with the resultsobtained by Badaliance and VanHorn.4A further objective wasto generalize upon the mode of failure that can be expected ina pre-tensioned prestressed concrete flexural member, and alsoto demonstrate the post bond slip strength of such beams.2.2ScopeThe bond characteristics of pre-tensioned prestressedmembers depend upon a number of characteristics such as:(1)size of the strand(2)ultimate strength of the strand(3)surface condition of the strand(4)concrete strength both at the time of releaseand at the time of test(5)rate of release of the strands(6)spacing of the strands(7)steel percentage-9-

In previous studies many of these variables have beeninvestigated.However, since the principal objective in thisinvestigation was the pinching effect of the end reaction inbeams with more than one layer of strand, the vertical spacingof the strands and the embedment length were of maximum concern.Therefore, the test specimens had the following characteristics:(1)One size of 270K strand (1/2-in.) wasused in all three specimens.The ratioof surface perimeter to cross-sectionalarea decreases as the size of the strandincreases.Therefore, bond is most crit-ical in members pre-tensioned with thelar estsize strand.The 1/2-in. sizestrand is the largest size currently usedcommercially.From a previous investiga-tion by Hanson and Kaar 7,it was found thatrust or scale on the strand improves thebond characteristics of the strand.Th re fore, a rust-free strand should representthe most critical case.(2)Five strands and one strand pattern wereused in each of the test specimens.Ofthe five strands, analysis showed that bond would be critical in the four lower strands . -10-

The four lower strands were placed intwo layers, with one strand immediatelyabove the other.The center-to-centervertical spacing was 2 inches, which isthe minimum allowed by the current ACIlBuilding Code.The positioning of thestrands was such that the difference inthe strand stress between the lower twolayers of strands at ultimate load ofthe test specimen was less than 0.5%.(3)The initial strand stress was constantfor all specimens, that is 70% of theminimum ultimate strength which, for270K strand, was 189 ksi.(4)The concrete strength was governed bytwo limits:(1)the release strengthmust be more than 4500 psi, and (2) thestrength at time of test must not bemore than 6000 psi.(5 )From the results of a previous study by4Badaliance and VanHorn it was shown thatthe critical embedment length was 80 inches.Therefore, an embedment length of 48 incheswas chosen to ensure bond slip in the two-11-

lower layers of strand, prior to aflexural or shear failure . The aforementioned characteristics werespe ifiedso asto fulfill the requirements of the current specifications, and toensure a failure by bond slip in at least the lower level of strand.,-12-

»III.TEST SPECIMENS 3.1Description of Test SpecimensThe three specimens were designed as under-reinforcedbeams such that a flexural failure would be initiated by yieldingof the strand, followed by crushing of the concrete.In accordancewith the objectives, the tests were designed to indicate (1) thevalue of the component of frictional bond that results from thepinching effect of the reaction, and (2) the amount of additionalload that the beam may sustain after bond slip.The specimens consisted of rectangular prestressed beamswith a cast-in-place slab.The prestressed rectangular beamelement was 7-1/2 inches wide and 12 inches deep, the slab was6 inches deep and 20 inches wide.The beam width of 7-1/2 inchesallowed a strand pattern that ensured the minimum cover requirements as specified by the current ACI Building Code.lThe bottomlayer of strand had a cover of 1-1/2 inches, the minimum allowedby the Code, so as to maximize the component of normal pressureat the interface of the strand and the concrete resulting fromthe pinching effect of the reaction.The depth of the beam sectionand the strand pattern were designed so that the maximum allowableprestress stress of the concrete was not exceeded.270K strands were used for prestressing the beam.were located in three layers.Five 1/2-in.The strandsFour of these strands were placed-13-

near the bottom of the section, two strands in two layers witha vertical center-to-center spacing of 2 inches. The fifthstrand was placed 2 inches from the top of the prestressedelement and served to limit the prestress stress which was imposed upon the concrete.This strand pattern produced nearlyequal stresses in the two lower levels of strand.The strandswere initially tensioned to a stress of 70% of the specifiedultimate stress which is 189,000 psi for 270K strand.Figure 1includes a detailed sketch of the cross-section.The test section was reviewed to determine to expectedultimate load and the associate failure characteristics.Thisseries of calculations was carried out in accordance with themethod presented by Janney, Hognestad, and McHenry.10Theultimate moment was calculated using the factors, k , k , k ,l23and uas presented by Hognestad, Hanson, and McHenry.8Theultimate strength factors were expressed as a function of theconcrete strength as follows:k kl 3k2 3900 0.35 flc3200 flc flc0.50 80,000fl U 0.004 -C6.5 x 10-14-6

JUsing these factors and a value of Fstress at ultimate flexural strength fcessive approximations. 1.0,the steelwas calculated by suc-suFor beams containing more than onelevel of steel, the strain compatibility equations are:aFeu (1 - d) -------;::;--de- e FesUseutcFeuThe condition of equilibrium of forces leads to:The flexural moment is given by the equation:Several trials were necessary to establish compatibility betweenthe calculated fsuand the value of esuand fsuobtained fromthe stress-strain curve of the strand.In the design calculation an estimate of the prestresslosses was required.The components of losses which were includedin the estimate were elastic shortening, shrinkage of the concrete,and creep in both the steel and concrete.-15-The loss in steel stress

due to elastic shortening was determined by:t,fLin12srecommends that concrete shrinkage loss becalculated by:t,fwhereE:ssc E:Es sis equal to the unit shrinkage strain of the oncrete.A value ofE:s 0.0003was used in this study.The loss due toconcrete creep was likewise calculated by the equation:t,fcs (Cc- 1) nfcwhere the value of C , the creep coefficient, was assumed equalcto 4.The loss due to creep in the prestressing steel wassimilarly computed by:t,fss K0 F.l -16-

where K is equal to three percent.oTable 4 is a comparisonbetween the measured and the calculated values of prestress losses.3.2MaterialsPrestressing SteelThe prestressing steel used was 1/2-in., 270K, seven-wire, uncoated, stress relieved type strand.This type of strandis commercially manufactured and tested in accordance with ASTMdesignation A416-64.The physical properties of this strand aregiven in Fig. 3 and the load-elongation curves are shown in Fig. 4.Further information concerning the static and fatigue propertiesof this strand is given in a recent report by Tide and VanHorn.15Although this type of strand is commercially available from severalmanufacturers, the strand used in this investigation was producedby John A. Roebling's Sons Division of the Colorado Fuel and IronCorporation.Shear ReinforcementThe shear reinforcement was fabricated from No. 3formed bars having a nominal yield stress fY de 50,000.ConcreteThe concrete strength was not a variable in this investigation.The concrete used in the beam element was designedto yield an ultimate strengthf -17- 6000psi, at an age of 21 days.

The mix chosen consisted of Type III (high-early strength) portland cement, sand, and crushed limestone coarse aggregate (3/4-in.maximum).The proportions of the mix, by weight, (cement-to-sand-to-coarse aggregate), were 1.00:2.64:2.98.The concrete wassupplied by a local ready-mix plant and was delivered in 1-1/2cubic yard batches.Although the concrete used in casting theslabs was of the same design as that used in the webs, tsslumpwas 2-1/2 inches compared to a slump of 3-1/2 inches for the beams.This difference in water content yielded a higher 21-day compressive strength for the slabs than for the beams.The three rectangular prestressed beams were all castfrom one batch of concrete, and all of the slabs from another.Compression tests were conducted on 6 x 12 in. cylinders, whichwere cast along with each batch of concrete, to determine thecompressive strength fT associated with the test beams at the timecof prestress release and at the time of test. Strains weremeasured on selected cylinders with a compressometer to determinethe shape of the stress-strain curve and the modulus of elasticityof the concrete at the time of test.As a measure of the tensilestrength of the concrete splitting tensile tests were conducted onstandard 6 x 12 in. cylinders.1/8-in Strips of plywood approximatelythick, l-in. wide, and 12 inches long were placed on thediametrical upper and lower bearing surfaces in the splitting test.The splitting cylinder tensile stress fT was determined by thespequation:-18-

f'sp -2PTId LcThe age and strength properties of the concrete described in the preceding paragraphs are presented in Table 2.3.3FabricationThe beams were fabricated in .a prestressing bed at theFritz Engineering Laboratory.follows:The sequence of operations was asthe strands were tensioned, strain gages were attachedto the strands, lead wires were soldered into place, the shearreinforcement waspo itionedand wired, forms were erected, thebeam concrete was placed and cured, the beam forms were removed,Whittemore targets were installed, the strands were released,the slab forms were set in place, the slab concrete was placedand cured, the slab forms were removed.The prestressing bed has been described in previousFritz Engineering Laboratory reports.16The bulkheads of theprestressing bed were spaced 40 feet apart and bolted to thelaboratory floor.The three beams were cast simultaneouslyusing the same assemblage of strands and three individual steelforms.The prestressing strands were held in the chosen patternwith two one-inch thick anchorage plates, one at each end of theprestressing bed.The projecting ends of the strands were securedby strand chucks.-19-

The tension was applied to the prestressing strandsby jacking the moving bUlkhead, using two 50-ton hydraulic jacks.The strand tension was measured for each strand individually byplacing a load cell between the anchorage plate and the strandchuck at the stationary end of the prestressing bed.If required,the tension in individual strands was adjusted by means of aspecial hydraulic jacking arrangement.After pre-tensioning thestrand, the strain gages were mounted on the strand.The shear reinforcement was tied to the strand with14 gage wire.In addition, wire ties were used between successiveprojecting elements of the stirrups in the compressive flangetarea, in order to prevent movement of the stirrups during theplacement of the concrete.Steel forms made of No. 7 gage steel plates were usedto cast the test beams.Dimensional checks, made after the forms had been removed, indicated that the cross-sectional dimensions were maintained to within 1/16 in. and consequently, the nominal dimensionsof the cross-section were used in all calculations.The concrete was brought from the ready-mix truck tothe forms in steel buggies, and shoveled into the forms.Theconcrete was placed in two layers, and the tops of the beams wereleft unfinished.each beam.Ten standard concrete cylinders were cast withWaxed cardboard molds were used.-20-

The concrete in the test specimen was internally vibrated, while the cylinders were rodded.All specimens were covered with burlap and plasticsheeting for a period of two days, after which the forms wereremoved.After the surface of the test beams had become air dry,Whittemore targets were positioned on the beams.When cylindertests indicated that the specimen1s concrete compressive strengthhad reached a strength of 4500 psi, the prestress force was slowly,released.An oxy-acetylene torch was used to cut the strands.,Thebeams were then removed from the casting bed, and stored in thelaboratory.Wood forms were used for fabrication of the slabs.Theconcrete was placed in one layer and allowed to cure under thesheets of plastic and burlap for one week.At that time, theforms were removed and the beams were air-cured until the timeof test.3.4InstrumentationIn order to determine the behavior of the beams, datawas recorded in the form of strains, strand movement and deflections.-21-

3.4.1StrainsLoad-deformation data was measured in two fashions (1) strain gages mounted at various locations on the strands,and (2) strain gages mounted on the concrete surface.Load-deformation data on the strand was measured withSR-4 electrical resistance strain gages, A-12 type, mounted onthe lower four strands of all three beams.The gages were mountedupon completion of, pre-tensioning, in order to increase the effective range of strain measurements.The gages were located onthe instrumented strands at 20-in. intervals starting 20 inchesfrom the ends of the members.One gage was attached to an in-dividual wire at each gage location.Before the strain gage wasmounted the strand was cleaned using emery cloth and acetone.The gage was glued to the strand using Duco-Cement.The water-proofing consisted of a coating of Armstrong adhesive A-16,followed by a layer of liquid rubber.The location of thesestrain gages can be seen in Fig. 5.The primary objective in positioning strain gages onthe prestressing strand, was to determine the change in strandforce as load was applied to the beam.In addition, these straingages were used to measure the elastic shortening of the strandat the time of release of the pre-tensioning force.The straindata received from the gages mounted on the strands was converted to force with a calibration curve.-22-This plot of strain

vs. strand force was determined by averaging strains measuredby three gages mounted on individual wires of a strand sample.Figure 4 compares the calibration curve to the load-deformation'14curve determined by Tide and VanHorn.The load-deformation data of the concrete surface wasmeasured (1) with a S-in. Whittemore gage, and (2) with SR-4 gageslocated around the cross-section at midspan of the test specimens.a.Whittemore strain gage data was used todetermine concrete surface strains at alevel midway between the lower two layers of prestressing strand.The Whittemoretargets were fabricated from brass plugs,7/32-in. in diameter and 1/16-in. inthickness.These targets were center-drilled and cemented at the prescribedlevel on both sides of the beam, afterthe forms were removed but before releaseof the pre-tensioning force.The purposeof the Whittemore data was to determine thetransfer length, and the loss of prestressat various intervals up until the time oftest.These gage readings were lsousedas an indicator of initial cracking of theconcrete .-23-

b.Twelve SR-4 gages, A-9 type, weremounted on the cross-section atmidspan of the beam.Figure 5 showsthe placement of these gages.Thestrain information from these gageswas used to determine the location ofthe neutral axis as cracking becamesevere, and the maximum concrete strainat ultimate load.3.4.2Strand SlipStrand slip was measured by the use of Ames dial gageswith a least count of l/lO,OOO-inch.These dial gages wereattached to a steel mounting bracket that clamped to the rectangular beam portion of the specimens.The gages indicated themovement of four small steel plates that were attached to thefour lower strands by means of collars and set screws.(SeeFig. 16)3.4.3Deflection MeasurementThe midspan deflection was measured by level readingson scales graduated to the nearest 0.01 inch.located at each of the supports and at midspan . -24-These scales were

IV.4.1TESTSTest ProcedureThree specimens were tested in the 300 kip hydraulictesting machine located in the Fritz Engineering Laboratory.The loading beam and associated apparatus were arranged to provide a symmetric two-point loading for all three specimens.The shear span was 42 inches and the overhang was 6 inches, resUlting in a total embedment length of 48 inches.the testing arrangement is shown in Fig. 2. A sketch ofThe test specimensin all cases were initially loaded in increments of 10 kips,which was approximately 8 percent of the computed ultimate load.When cracking of the concrete became visible, the loading increment was reduced to 5 kips until failure occurred.The in-ternal A-12 type, SR-4 gages mounted on the individual wires ofthe strand were used in conjunction with two different types ofrecording equipment.Six gages of Beam Z-l were connected tochannels of a Brush direct-writing recorder to provide a continuous record of the variation of the load in the strands.The remaining internal gages, as well as the A-9 type, SR-4 gagesmounted on the surface of the concrete at the midspan cross-section,were connected to a Budd Datran digital strain indicator.Allelectric resistance strain gages were read following the application of each increment of load.A review of the test results from-25-

Beam 2-1 revealed that little was gained from the use of theBrush recorder. Therefore, in the remaining tests the instru-ment was not used .The Whittemore targets mounted on the surface of theconcrete were read at selected load increments until crackingbecame severe.Midspan deflection readings were taken at eachload increment until failure.The strand-slip dial gages wereread continuously to detect initial bond slip.The developmentof the crack pattern was marked on the surface of the specimenafter each increment of load had been applied.After failurethe specimens were photographed . 4.24.2.1Test Results and DiscussionModes of FailureIn this investigation failure in all three test speci-mens has been associated with flexure.The tensile reinforce-ment initially yielded, followed by the eventual crushing of theconcrete.However, prior to yielding of the reinforcement, bondslip was experienced in the four lower strands in all three tests.The failure mechanism associated with bond slip is closely related to the cracking of the concrete.Cracking of the Concrete In this study two basic types of cracking were exhibited,flexural and flexural-shear cracking . -26-

Flexural cracking occurred in the high moment regionof the test specimens when the stresses in the bottom fibersreached values which are normally associated with the tensilestrength of the concrete.Flexural cracking was characterizedby the initial development of vertical cracks to a level whichvaried between the lower and upper* strand levels.The longi-tudinal spacing of these flexural cracks was approximately6 inches.However, cracks which formed closer together thanapproximately 2 inches would usually merge, or the further development of one of the two cr

prestressed concrete members, the bonding action between the prestressing element and the concrete is a result of friction as well as adhesion and mechanical resistance. In the fabrication of a pre-tensioned prestressed concrete member the prestressing strand is first tensioned to the desired stress level. Concrete is then cast about the strand and

Related Documents:

Lecture 24 – Prestressed Concrete Prestressed concrete refers to concrete that has applied stresses induced into the member. Typically, wires or “tendons” are stretched and then blocked at the ends creating compressive stresses throughout the member’s entire cross-section. Most Prestressed concrete is precast in a plant.

As bond order increases, bond length decreases, and bond energy increases H 2 bond order 1 A bond order of 1 corresponds to a single bond Bond order (number of-bonding e ) - (number of antibonding e ) 2 electrons/bond 38 MO Energy Diagram for He 2 Four electrons, so both and *

Introduction to Prestressed Concrete 1 / 7 In prestressed concrete, compressive stresses are applied to the concrete prior to loading. Under service loads, the entire cross section is essentially in compression, which takes advantage of concrete’s considerable compressive

The bond order, determined by the Lewis structure, is the number of pairs of electrons in a bond. Bond length depends on bond order. As the bond order increases, the bond gets shorter and stronger. Bond length Bond energy C C C C C C 154 pm 134 pm 120 pm 835 kJ/mol 602 kJ/mol

Precast/Prestressed Concrete Institute, Design Handbook-Precast and Prestressed Concrete: Code of Standard Practice for Precast/Prestressed Concrete (PCI MNL-120) Structural Material Specifications Concrete Foundations (Pile Caps and Grade Beams): 6,000 p

As prestressed concrete became widely produced and adopted, a second concept was formulated, commonly known as the ultimate strength theory. Under that concept, prestressed concrete is treated as a combination of h\Ph strength con crete and high strength steel, with concrete to carry the compression

stressed concrete columns with the exception that our knowledge of re-inforced concrete columns may be utilized when dealing with pre-stressed ones. Three approaches are possible for the design of prestressed concrete columns: 1. Rational and analytical ap-proach. 2. A new set of code design clauses to be set up specifically for prestressed .

Storage Systems for Automotive Applications Wasim Sarwar1*, Timothy Engstrom1, Monica Marinescu1, Nick Green2, Nigel . As with PHEVs, in a large ESS the use of active thermal management (system consisting of heating and cooling loop) provides good value, therefore a large thermal operating window is not required. Further, a comparatively shorter cycle life is sufficient in order to meet the .