Standard Decommissioning Programme(s) Template

2y ago
13 Views
2 Downloads
1.03 MB
34 Pages
Last View : 30d ago
Last Download : 3m ago
Upload by : Albert Barnett
Transcription

November 2018Version 3Replace with operator logo and picture of on-Derogation)Insert dateConsultaion/pre-draft1

Document ControlInsert Tables of Document Revisions.ApprovalsNameSignatureDatePrepared byReviewed byApproved byRevision ControlRevision NoReferenceChanges/CommentsIssue DateDistribution ListNameCompany2No of Copies

ContentsNote: Annotate the Contents table to indicate which sections refer to installation or pipelineprogrammes or both. INST Installations PL PipelinesDelete options and brackets where appropriate. Remove red help text throughout documentINSTPL11.11.21.31.41.51.61.7Executive SummaryDecommissioning Programme/Combined Decommissioning ProgrammesRequirement for Decommissioning Programme(s)IntroductionOverview of Installation(s)/Pipeline(s) Being DecommissionedSummary of Proposed Decommissioning Programme(s)Field Location Including Field Layout and Adjacent FacilitiesIndustrial Implications555567811 22.12.22.32.42.52.6Description of Items to be DecommissionedInstallation(s): Surface FacilitiesInstallation(s): Subsea including Stabilisation FeaturesPipelines including Stabilisation FeaturesWellsDrill CuttingsInventory moval and Disposal MethodsTopsideJacket(s)Subsea Installations and Stabilisation FeaturesPipeline(s)Pipeline Stabilisation FeaturesWellsDrill CuttingsWaste Streams18182021222324252644.14.2Environmental Appraisal OverviewEnvironmental Sensitivities (Summary)Potential Environmental Impacts and their Management5 272728 Interested Party Consultations29 66.16.26.36.46.56.6Programme ManagementProject Management and VerificationPost-Decommissioning Debris Clearance and VerificationScheduleCostsClose OutPost-Decommissioning Monitoring and Evaluation30303031313232 7Supporting Documents33 8Partner Letter(s) of Support34 3

Terms and AbbreviationsInclude a table of the terms and abbreviations used in the document (examples in blue below).AbbreviationExplanationOPREDOffshore Petroleum Regulator for Environment and DecommissioningEAEnvironmental AppraisalCAComparative AssessmentFigures and TablesInclude a table of Figures and Tables used in the document.AppendicesInclude a table of the Appendices which are to be included as part of this document (example in blue below).AppendixDescription1Copy of Public NoticePageNote: The Environmental Appraisal (EA) and any Comparative Assessment (CA) for pipelines are separate,referenced documents in support of the decommissioning programme(s). They should not be included as anAppendix but listed in Section 7 (Supporting Documents).A copy of the Public Notice should be attached as an appendix to the final version of the programme.4

1EXECUTIVE SUMMARY1.1 Decommissioning Programme/Combined Decommissioning ProgrammesThis document contains decommissioning programme(s) for installation(s) andpipeline(s).Combined Decommissioning Programmes: Please provide a clear statement confirming that there is a separateprogramme for each set of associated notices served under Section 29 of the Petroleum Act 1998.1.2 Requirement for Decommissioning Programme(s)Delete appropriate paragraph below if only one decommissioning programme.Installation(s):In accordance with the Petroleum Act 1998, the Section 29 notice holders of theinstallation(s)/field (see Table 1.2) are applying to the Offshore Petroleum Regulator for Environment andDecommissioning (OPRED) to obtain approval for decommissioning the installations detailed in Section 2.1 and2.2 of this programme. (See also Section 8 - Partner Letter(s) of Support).Pipeline(s):In accordance with the Petroleum Act 1998, the Section 29 notice holders of the pipelines(see Table 1.4) are applying to the Offshore Petroleum Regulator for Environment and Decommissioning(OPRED) to obtain approval for decommissioning the pipelines detailed in Section 2.3 of this programme. (Seealso Section 8 – Partner Letter(s) of Support).In conjunction with public, stakeholder and regulatory consultation, the decommissioning programme(s) is/aresubmitted in compliance with national and international regulations and OPRED guidelines. The scheduleoutlined in this document is for a year decommissioning project plan due to begin in .1.3 IntroductionInsert introductory paragraphs outlining the background of the decommissioning proposal with information ontopsides, jacket and pipelines (where applicable). Freeform text as per example paragraphs below. (Suggestedmaximum of 250 words)The Welland Field is located in the Southern Basin of the UKCS in license block 53/4a. Welland was discovered in1983 and consists of three gas reservoirs with condensate traces. It received Annex B approval in 1989 for asingle platform remotely operated from Thames platform. The platform was installed, and production started in1990. Production ceased in 2003 due to excessive water rates and equipment failures. Cessation of Productionnotification was submitted in 2004.Welland Platform is a 1000 Te topside minimum facilities structure in 37m water depth. It was designed andoperated as a normally unattended satellite installation. Gas was exported to the nearby Thames complex.Subsea tie-backs to 3 remote wells comingle with production from the 2 platform wells.Following public, stakeholder and regulatory consultation, the decommissioning programme(s) is/are submittedwithout derogation and in full compliance with OPRED guidelines. The decommissioning programme(s) explainsthe principles of the removal activities and is supported by an environmental appraisal (EA).5

1.4 Overview of Installation(s)/Pipeline(s) Being Decommissioned1.4.1 Installation(s)Table 1.1: Installation(s) Being DecommissionedField(s)Production Type(Oil/Gas/Condensate)Water Depth (m)UKCS blockDistance tomedian (km)Distance from nearest UKcoastline (km)Surface Installation(s)NumberType*Topsides Weight (Te)Subsea Installation(s)NumberJacket Weight (Te)Number of WellsType**PlatformSubseaDrill Cuttings pile(s)Total Estimated volume (m3)Number of Piles* fixed steel jacket/floating facility/FPSO/etc**template/manifold/WHPS etcTable 1.2: Installation(s) Section 29 Notice Holders DetailsSection 29 Notice Holder(s)*Registration NumberEquity Interest (%)If zero show 0%Any companies which are Exited companies on the Section 29 Notice should also be listed here. Do not includewithdrawn companies.*Please use full registered company names as recorded on Companies House.1.4.2 Pipeline(s)Table 1.3: Pipeline(s) Being DecommissionedNumber of Pipeline(s) Details given in Table 2.3Table 1.4: Pipeline(s) Section 29 Notice Holders DetailsSection 29 Notice Holder(s)*Registration Number6Equity Interest (%)If zero show 0%

Any companies which are Exited companies on the Section 29 Notice should also be listed here. Do not includewithdrawn companies.* Please use full registered company names as recorded on Companies House.1.5 Summary of Proposed Decommissioning Programme(s)Complete Table 1.5, as per examples in blue below.Table 1.5: Summary of Decommissioning Programme(s)Selected OptionReason for SelectionProposed Decommissioning SolutionPerenco subsidiary indicated thatWelland installation suitable fordevelopment of new well outsideUKCS waters.Cleaned equipment refurbished forre-use where possible. Removewholly by HLV. Equipment whichcannot be re-used will be recycled orother disposal routes as appropriate.Leaves clean seabed, removes apotential obstruction to fishingoperations and maximisesrecycling of materialsMay need to be cut at the -11m level(26m above sea-bed) to allow re-useat proposed new location. Legs willbe removed with piles and cut onvessel/ barge decks or at an onshorelocation. Lower 26M of the jacketand piles and subsea wellheadprotection frames will betransported ashore for recycling.To remove all seabed structuresand leave a clear seabedWellhead protection frames will beremoved along with the top sectionsof piles. Piles for wellhead protectionstructures will be removed to -3metres.1. TopsidesComplete removal and re-use(or N/A if subsea installation(s)only or pipeline(s) onlyprogramme)2. Substructures (Jackets/FPSO etc)Complete removal and recycling(or N/A if a subsea installation(s)only or pipeline(s) onlyprogramme)3. Subsea Installation(s)Wellhead protection frames willbe removed by HLV or cranevessel with crane (or N/A if nonepresent or pipeline(s) onlyprogramme)4. Pipelines, Flowlines & UmbilicalsFlush and leave buried in situ (orN/A if an installation(s) onlyprogramme)Minimal seabed disturbance,lower energy usage, reduced riskto personnel5. Wells7The 16 inch pipeline, 3inch piggyback line, three 8 inch flowlines andthree 4” umbilicals will be left in situ,with the cut ends re-buried asrecommended by the Fishermen’sFederation. Surveys indicatepipelines and umbilicals will remainburied with flooding. Degradationwill occur over a long period withinseabed sediment, not expected torepresent a hazard to other users ofthe sea.

Abandoned in accordance withOil & Gas UK Guidelines for theSuspension and abandonment ofWells.Meets OGA and HSE regulatoryrequirements.A PON5/ Portal EnvironmentalTracking System (PETS)/MarineLicence application under therelevant regulations will besubmitted in support of workscarried out.Cuttings pile is small, thin andwidely dispersed and falls belowboth of OSPAR 2006/5 thresholdsLeft undisturbed on seabed.6. Drill CuttingsLeave in place to degradenaturally.7. InterdependenciesProvide (as appropriate) a comment on any interactions between the different elements of thedecommissioning programme e.g. drill cuttings/drilling templates etc.Whole of jacket can be removed; cuttings pile has little influence on jacket options. Jacket piles can be cutwith minimal disturbance to the thin layer of cuttings around bottoms of legs. Small amounts of sediment andcuttings may have to be displaced to allow pile cutting.1.6 Field Location Including Field Layout and Adjacent FacilitiesFigure 1.1: Field Location in UKCSInclude a figure which shows the field location in UKCS (see example)8

Figure 1.2: Field LayoutInsert a diagram to show the layout of the field, including subsea installation(s) (see example)Note: Adjacent facilities refer to those potentially impacted by this programme.9

Complete Table 1.6 (examples in blue below) listing any adjacent facilities (e.g. platforms, pipelines, pipelinecrossings and telephone cables). Please use full company names and use pipeline numbers as per OGA PWAConsent.Table 1.6: Adjacent onPerenco UK ThamesLimitedPlatform17km North WestGas/liquidsprocessing, MEGand controlsystem links forWelland, onwardexport to BactonPerenco UK PL674Limited16” PipelineFrom Welland toThames (17km NW)Crosses 2 disusedcables and Sean30” gas pipelineto BactonPerenco UK GawainLimitedSubsea Wellumbilical500mFrom Gawain toThames, crossesoverWelland/ThamespipelineStatuse.g. Operational;Out-of-use;SuspendedImpacts of Decommissioning ProposalsIf appropriate describe any impacts the adjacent facilities may have on the decommissioning proposals.(Suggested maximum of 50 words)Include details in this section of decommissioning arrangements for any pipeline crossings that are impactedby the decommissioning activity.10

Figure 1.3: Adjacent FacilitiesInsert a diagram to show the specified adjacent facilities (see example)1.7 Industrial ImplicationsProvide a summary describing how the contract/procurement strategy is to be undertaken. (Suggestedmaximum of 250 words)11

2DESCRIPTION OF ITEMS TO BE DECOMMISSIONED2.1 Installation(s): Surface Facilities (Topsides/Jacket(s)/FPSO etc.)Complete Table 2.1 (example in blue below). Repeat for each installation in the programme. Insert N/A (notapplicable) or N/D (no data) as appropriate.Table 2.1: Surface Facilities pe*NameWellandSouthPlatformJacket (if 51589WGS84DecimalMinute5803.046’N00 21.095’EWeight(Te)No ofmodulesWeight(Te)Numberof legsNumberof pilesWeightof piles(Te)942157033300*fixed steel jacket/floating facility/FPSO etc.** Location to be given in both WGS84 decimal and WGS84 decimal of a minute (3 decimal places) formats.2.2Installation(s): Subsea including Stabilisation FeaturesComplete Table 2.2 Insert n/a if not applicable. See example in blue below.Table 2.2: Subsea Installations and Stabilisation FeaturesWellheadsNumberSize/Weight(Te)21 x 31.96tonnes1 x 4.5tonnesManifoldWellhead115m x 6m x5m S84Decimal Minute58⁰ 3.046’N00 21.095’EWGS84Decimal58.0499720.3495WGS84Decimal Minute58⁰ 2.998’N00 l Minute58⁰ 4.400’N00 26.166’En/a12Comments/Status***Both wells are suspendedand will undergo plug andabandonment. Neitherstructure is piled to seabedStructure is secured to theseabed by four steel piles.

rout bagsn/aFormworkn/aFrond Matsn/aRock Dumpn/aOther ld etc.** Location to be given in both WGS84 decimal and WGS84 decimal of a minute (3 decimal places) formats.***Indicate in comments/status if piled to seabed.13

2.3Pipelines Including Stabilisation FeaturesComplete Tables 2.3 and 2.4 with details of pipelines, flowlines and umbilicals. Please use pipeline details as per OGA PWA consent.Note – Structures including SSIV’s, SDU’S and other similar subsea structures which have been captured in the relevant PWA documentation as components of thepipeline system should be listed in the relevant pipelines sections and tables of the decommissioning programme. As these are substantial structures full removal isrequired. For such structures please include a brief sentence or footnote to the Subsea Installation section of the DP i.e. Section 3.3 to note that X subsea structureassociated with the X pipeline system will be fully removed to shore.Table 2.3: Pipeline/Flowline/Umbilical InformationDescriptionPipelineNumber(as per PWA)Diameter(inches)Length(km)Description ofComponentParts1ProductConveyed2From – ToEnd PointsBurial Status3PipelineStatus4CurrentContent5Export linePL67416"17.5Concretecoated steelGasWelland South Platform– SSIV on Thames AWPlatformTrenched with7m sectionexposedOperationalHydrocarbonMEG linePL6753"17.5CompositeFlexibleChemicalsThames AW Platform –Welland South PlatformSurface laidNo free spansOperationalChemicalsWell 2 Subsea flowlinePL6788"4.2Concretecoated steelGasWell-53/04a- 5 –Welland South PlatformTrenched andburiedOperationalHydrocarbonWell 2 Subsea controlumbilical & MEG and South Platform- Well-53/04a- 5Trenched andburiedIPRChemicalsFTPFEPA Exempt0.17CompositeFlexibleDC1 – U61R1e.g. Concrete; Steel; Umbilical; Flexible; Bundlee.g. Oil; Gas; Water; Chemicals3e.g. Laid on seabed; Trenched; Trenched and Buried; Spanning4e.g. Operational; Out-of-use; Interim Pipeline Regime (IPR)5e.g. Cleaned; Flushed; Hydrocarbons and/or Chemicals in line214Out of Use

Table 2.4: Subsea Pipeline Stabilisation FeaturesStabilisation FeatureConcrete mattressesTotal Number5Weight (Te)Location(s)6 tonnes eachAt PL123 and PL456 crossingpoints.Exposed/Buried/ConditionExposedCan only be recovered when crossover lines are decommissionedGrout bags80Formworkn/aFrond Matsn/aRock Dumpn/aOther (describe briefly)n/a25kg eachAround the subsea tee piece20002 Locations on PL67415Exposed

2.4WellsComplete Table 2.5 (examples in blue below)Table 2.5: Well InformationDesignation1Platform WellsStatusCategory of Well16/03a-E18 (East)Gas Condensate ProducerSuspendedPL 4-3-349/9b-W1Gas ProductionShut-inPL 2-1-1211/19a-M56Water InjectionProducingPL 2-1-3211/23-A34Oil ProducerPhase 1 AbandonedPL-0-4-316/03b-08y (Braemar)Gas Condensate ProducerProducingSS 3-3-311/30a-C1Water InjectionAbandonedSS 3-4-3Subsea Wells1e.g. Production; Injection; Oil; GasFor details of well categorisation see OGUK Guidelines for the Suspension or Abandonment of Wells. Issue 5,July 2015.2.5Drill Cuttings(See Section 3.7 for further information)Complete Table 2.6 for each cuttings pile (examples in blue below)Table 2.6: Drill Cuttings Pile(s) InformationLocation of Pile Centre(Latitude/Longitude)Seabed Area(m2)Estimated volume ofcuttings (m3)Schiehallion Central837111352Schiehallion West67317224Schiehallion North44761548Loyal5501412816

2.6Inventory EstimatesProvide a table or graph (see pie chart example shown) giving the inventory estimates for the decommissioningprogramme(s) contained in this document. Refer to tables or data in the supporting Environmental Appraisal.Please list the inventories in both tonnage and percentage.Figure 2.1: Pie Chart of Estimated Inventories (Installations)Estimated Inventory: errous15%NORM/HazOther21%Insert Total Mass in Tonnes [ x Te]Reference the Environmental Statement for detailed data.NORM/Hazardous Waste - reference the supporting evidence in EA.Figure 2.2: Pie Chart of Estimated Inventory (Pipelines)Estimated Inventory: Pipeline(s)2% zOtherInsert Total Mass in Tonnes [ x Te]Reference the Environmental Statement for detailed dataNORM/Hazardous Waste – reference the supporting evidence in EA.17

3REMOVAL AND DISPOSAL METHODSIn line with the waste hierarchy, the re-use of an installation (or parts thereof) is first in the order ofpreferred decommissioning options. OPRED is keen to encourage the re-use of facilities wherever this ispractical and will expect the decommissioning programme(s) to demonstrate that the potential for re-use hasbeen examined fully.The programme(s) should therefore include a statement of how the principles of the waste hierarchy will bemet, including the extent to which the installation(s) (or parts thereof) will be reused, recycled or scrapped.(Suggested maximum 250 words)3.1 Topsides3.1.1 Topsides Decommissioning OverviewIndicate N/A if no topsides. Briefly describe the topsides and decommissioning methodology (see example inblue below). Insert a diagram to illustrate. Repeat for each topside in the programme(s). Note: For floatingfacilities, provide a brief description of the decommissioning method. (Suggested maximum 150 words)Topsides Description: The Welland Topside Structure comprises three levels and weighs 942 Te. The lowerlevel is the cellar deck with process, hydraulic pressure equipment and wells. The 20m x 14m main decksupports the control room, generation and temporary accommodation facilities with a pedestal crane and ventboom. The main deck is 25.6m above sea level. A helideck is located at the upper level.Figure 3.1: Diagram of Topsides18

Preparation/Cleaning: Outline in Table 3.1 the methods that will be used to flush, purge or clean the topsidesoffshore, prior to removal to shore, (see examples in blue below).Table 3.1: Cleaning of Topsides for RemovalWaste TypeComposition of WasteDisposal RouteOnboard hydrocarbonsProcess fluids, fuels andlubricantsDrained and transported ashore for reuse/disposalOther hazardous materialsNORM, LSA Scale, any radioactive Transported ashore for re-use/disposalmaterial, instruments containing by appropriate methodsheavy metals, batteriesOriginal paint coatingLead-based paintMay give off toxic fumes / dust ifflame-cutting or grinding/blasting isused so appropriate safety measureswill be takenAsbestos and Ceramic FibreAppropriate control and managementwill be enforcedRemoval Methods: Topsides must be completely removed and returned to shore. Possible methods should beoutlined in Table 3.2 (see examples in blue below). Tick which methods you are considering for topsidesdecommissioning. Then briefly describe those applicable to your project.Table 3.2: Topsides Removal Methods1) HLV (semi-submersible crane vessel) 2) SLV 3) Piece small 4) Other (describe briefly)MethodDescriptionSingle lift removal by SLV/HLVRemoval of topsides as complete units andtransportation to shore for re-use of selectedequipment, recycling, break up, and/or disposalModular removal and re-use/recycle by HLVRemoval of parts/modules of Topsides for transportationand reuse in alternate location(s) and/orrecycling/disposalOffshore removal ‘piece small’ for onshorereuse/disposalRemoval of topsides by breaking up offshore andtransporting to shore using work barge. Items will thenbe sorted for re-use, recycling or disposalProposed removal method and disposal route(Make sure this section appears in BOLD font)State the method you propose for removing anddisposing of the topsides, recognising any potentialissues regarding trans-frontier shipment of waste.Highlight if more than one option is being carriedforward into competitive tendering. If applicable addthe phrase – “A final decision on decommissioningmethod will be made following a commercial tenderingprocess.” (Suggested maximum of 50 words).19

3.2 Jacket(s)3.2.1 Jacket Decommissioning OverviewIndicate N/A if no Jacket. Provide an overview of the Jacket(s) Decommissioning methods. See example in bluebelow. Outline any special considerations affecting the options. Insert a diagram to illustrate. Repeat for eachjacket in the programme(s). (Suggested maximum 150 words)The jacket legs may need to be cut at the -11m level (26m above sea-bed) to allow re-use of the topsides by aPerenco subsidiary at a proposed new location. Although the full engineering process is not yet finalised, it isenvisaged that the Legs will be removed with piles in completeness and then cut on the vessel/barge decks orat an onshore location to the required length. The lower 26m of the jacket and piles and the subsea wellheadprotection frames will be transported ashore for recycling.Figure 3.2: Jacket Elevation20

3.2.2 Jacket Removal MethodsTick the different methods that you are considering for the removal and disposal of the jacket. Complete Table3.3 (examples in blue below) to describe how the jacket would be removed completely and returned to shore.Any piles should be severed below the natural seabed level at such a depth to ensure that any remains areunlikely to become uncovered. Operators should aim to achieve a cut depth of 3m below the natural seabedlevel, however consideration will be given to the prevailing seabed conditions which should be detailed below.Table 3.3: Jacket Removal Methods1) HLV (semi-submersible crane vessel) 2) SLV 3) Piece small 4) Other (describe briefly)MethodDescriptionSingle lift removal by SLV/HLVRemoval of topsides as complete units andtransportation to shore for re-use of selectedequipment, recycling, break up, and/or disposalModular removal and re-use/recycle by HLVRemoval of parts/modules of Topsides for transportationand reuse in alternate location(s) and/orrecycling/disposalOffshore removal ‘piece small’ for onshorereuse/disposalRemoval of topsides by breaking up offshore andtransporting to shore using work barge. Items will thenbe sorted for re-use, recycling or disposalProposed removal method and disposal route(Make sure this section appears in BOLD font)State the method you propose for removing anddisposing of the topsides, recognising any potentialissues regarding trans-frontier shipment of waste.E.g. All necessary permits and consents required fortrans-frontier shipments of waste will be in place priorto leaving UK waters.Highlight if more than one option is being carriedforward into competitive tendering. If applicable addthe phrase – “A final decision on decommissioningmethod will be made following a commercial tenderingprocess.” (Suggested maximum of 50 words).3.3 Subsea Installation(s) and Stabilisation Feature(s)Outline in Table 3.4 how the items will be decommissioned (examples in blue below). If mattresses are buried toa minimum depth of 0.6m below the seabed, OPRED would consider a proposal in the form of a comparativeassessment to leave the mattresses in situ (robust evidence of the mattress burial status should be submittedwith the comparative assessment). It is expected that mattresses buried to less than 0.6m below the seabed arerecovered to shore.Table 3.4: Subsea Installation(s) and Stabilisation Feature(s) Decommissioning OptionsSubsea installation(s)and stabilisationfeature(s)NumberOption21Disposal Route (if applicable)

Wellhead(s)2Full recovery as part of MODUcampaign to P&A wellsReturn to shore for reuse orrecyclingManifold(s)1Full recoveryReturn to shore for reuse orrecycling20020Full recoveryIt is intended that the mattresseswill be recovered to shore, howeverin the event of practical difficultiesduring the removal execution ,OPRED will be consulted and analternative method ofdecommissioning will be examinedthrough a comparative assessment.Recover to shoreTemplate(s)Protection Frame(s)Concrete mattressesTransport ashore for disposalGrout bagsFormworkFrond MatsRock DumpOther (describe briefly)3.4 PipelinesDecommissioning Options: In Table 3.5 summarise the pipeline(s) or pipeline groups that fall within thedecommissioning programme. (See examples in blue below). Include a cross reference to Table 2.3. Remedialrock-dump is not OPRED’s preferred decommissioning solution and should only be selected following discussionwith OPRED and if a comparative assessment shows this is the best outcome and other options are not feasible.*Key to Options:1) Remove - reverse reeling4) Remedial removal2) Remove - Reverse S lay5) Remedial trenching3) Trench and bury6) Partial RemovalTable 3.5: Pipeline or Pipeline Groups Decommissioning OptionsPipeline or Group (asper PWA)Condition of line/group(Surface laid/trenched/buried/spanning)Whole or part ofpipeline/groupDecommissioning options*consideredPLXUntrenchedPart. Section within500m zone of theThames AW platformwill be decommissionedat a later dateShow which options arebeing considered byinserting relevant number(s)from the list above i.e.1,3,6PLXX, PLXXXTrenched, buriedWhole of pipelines2,5,922

Comparative Assessment Method: Briefly outline the method used to undertake a Comparative Assessment inline with the requirements of OPRED Guidelines. Cross reference to Comparative Assessment document.(Suggested maximum of 100 words)Outcome of Comparative Assessment: Produce a table similar to example in Table 3.6 below for each pipelineor pipeline group, summarising the outcome of the Comparative Assessment. Identify the recommended option,and briefly present your justification for this recommendation. Cross-reference any separate ComparativeAssessment document. Repeat for each pipeline/pipeline groupTable 3.6: Outcome of Comparative AssessmentPipeline or Group (asper PWA)Recommended Option*JustificationPLXOption 3Line condition made lifting impractical; burial willremove snagging risk for fishermenPLXX, PLXXXOption 9Already trenched and buried to 0.7m, stable, nosnagging hazards3.5 Pipeline Stabilisation Feature(s)Outline in Table 3.7 how the items will be decommissioned (examples in blue below). If mattresses are buried toa minimum depth of 0.6m below the seabed, OPRED would consider a proposal in the form of a comparativeassessment to leave the mattresses in situ (robust evidence of the mattress burial status should be submittedwith the comparative assessment). It is expected that mattresses buried to less than 0.6m below the seabed arerecovered to shore.Table 3.7: Pipeline Stabilisation Feature(s)Stabilisation feature(s)Concrete mattressesNumber2005Disposal Route (if applicable)Full recoveryTo remain in situ until pipelinecrossings decommissionedIt is intended that the mattresseswill be recovered to shore, howeverin the event of practical difficultiesduring the removal execution ,OPRED will be consulted and analternative method ofdecommissioning will be examinedthrough a comparative assessment.Recover to shoren/a80Full recoveryTo shore for disposal inlandfill2000TeTo remain in placen/a20Grout bagsOptionTransport ashore for disposalFormworkFrond MatsRock Dump (Te)23

3.6 WellsProvide a short statement, similar to the example in blue below, to indicate your approach to well plug andabandonment. (Suggested maximum of 150 words)Table 3.8: Well Plug and AbandonmentThe wells which remain to be abandoned, as listed in Section 2.4 (Table 2.5) will be plugged andabandoned in accordance with Oil and Gas UK Guidelines for the suspension and abandonment of wells.A PON5/Portal Environmental Tracking System (PETS)/Marine Licence application will be submitted insupport of any such work that is to be carried out.24

3.7 Drill CuttingsDrill Cuttings Decommissioning Options: OSPAR recommendation 2006/5 has indicated that if the oil releaserate from a cuttings pile is less than 10Te/yr and the area persistence is less than 500 km2years then the bestenvironmental option for the management of the pile is to leave it in place undisturbed to degrade naturally.Complete Table 3.9 to give details of each of the drill cuttings pile(s). Repeat for each pile and delete or addextra columns as appropriate. Note any interactions between the cuttings pile(s) and jacket removal.Table 3.9: Drill Cuttings Decommissioning OptionsHow many drill cuttings piles are present?Tick options examined: Remove and re-inject Leave in place Cover Relocate on seabed Remove and treat onshore Remove and treat offshore Other (describe briefly)Review of Pile characteristicsPile 1Pile 2Pile 3Y/NY/NY/NY/NSampling to be included in pre-decommissioning survey?Y/NY/NY/NY/NDoes it fall below both OSPAR thresholds?Y/NY/NY/NY/NWill the drill cuttings pile have to be displaced in order toremove the jacket?Y/NY/NY/NY/NY/NY/NY/NY/NY/NY/NY/NY/NHow has the cuttings pile been screened? (desktopexercise/actual samples taken) – delete as necessaryPile 4Dates of sampling (i

outlined in this document is for a _ year decommissioning project plan due to begin in _. 1.3 Introduction Insert introductory paragraphs outlining the background of the decommissioning proposal with information on topsides, jacket and pipelines (where applicable).

Related Documents:

The primary objectives are to identify the alternatives available to Reed College with regards to decommissioning and to estimate the associated costs. Note that the removal of reactor fuel is done before commencement of decommissioning operations; therefore, this task is not included as part of decommissioning costs.

OIG conducted an Audit of NRC's Decommissioning Funds Program (OIG-16-A-16) that included a review of NRC's oversight of the decommissioning funds of both reactors and materials. The audit report was issued in June 2016. During that audit, OIG was not able to verify the accuracy of the Inventory List of material licensee decommissioning

2 Contents Page The Song Tree Introduction 3-7 Programme 1 Fly, golden eagle 8 Programme 2 Magic hummingbird 9 Programme 3 It’s hard to believe 10 Programme 4 Another ear of corn 11 Programme 5 The door to a secret world 12 Programme 6 Song of the kivas 13 Programme 7 Mighty Muy’ingwa 14 Programme 8 Heavenly rain 15 Programme 9 Rehearsal 16 Programme 10 Performance 17

2 Contents Page Music Workshop Introduction 3 Programme 1 Loki the Joker 7 Programme 2 Odin, Mighty World-Creator 8 Programme 3 Goblins a Go-Go! 9 Programme 4 Sing us a Saga 10 Programme 5 Thor on a journey 11 Programme 6 Apples of Iduna 12 Programme 7 Birds of the North 13 Programme 8 Rehearsal and Performance (1) 14 Programme 9 Rehearsal and Performance (2) 15 .

Audit of NRC’s Transition Process for Decommissioning Power Reactors . plant is dismantled and the property is decontaminated. The entire decommissioning process may take up to 60 years. For a map of si

Project Execution Plan Building 123 Decommissioning Project 91 1 1 I97 Page 5of 19 Document Number RFIRMRS-97-082 Revision 4 BUILDING 123 DECOMMISSIONING PROJECT EXECUTION PLAN 1.0 Project History/ Background 1.1 Introduction The purpose of this project is to decommission buildings 123, 113, 114, and 123S, stabilize in place o

3 International Atomic Energy Agency Decommissioning Planning -Key Elements Review of decommissioning strategies Specific studies to support selected strategy Feasibility/ Cost-Benefit analyses Cost estimate for the work at the actual site Schedule for performing the work at the site Technical scope of

Advanced level Speciflcation summary 1. 2 Advanced level Speciflcation summary Qualification objective CIPD Advanced level qualifications provide a depth of knowledge alongside the opportunity to specialise in chosen areas of expertise. Candidates will be able to develop their understanding of organisations and the external context within which HR operates. Using critical analysis, self .