METHOD STATEMENT BASEMENT WATERPROOFING COSTAR BUILDING PRODUCT SYSTEM Next Generation Solutions For Today’s Construction www.costarchem.com
METHOD STATEMENT FOR BASEMENT WATERPROOFING 1. SCOPE This method statement describes the step by step procedure for waterproo ng a basement 2. DESCRIPTION This method statement describes the repair and waterproo ng of basements and retaining walls to best practice. 2.1 LIMITATIONS Ÿ Products shall only be applied in accordance with their intended use. Ÿ The most recent and relevant Product Data Sheets (PDS) and Safety Data Sheets (SDS) shall apply. Ÿ This method statement is only a guide and shall be adapted to suit local products, standards, legislation or other local requirements. 3. REFERENCES To ensure correct application of all components of Costar products, please refer to the following documents of each product component: Ÿ Ÿ PDS (Product Data Sheet) SDS (Safety Data Sheet) 4. PRODUCTS Best Practice states that a waterproo ng membrane should be used alongside a waterproo ng admixture: For areas with high water table: Krystal 2000/Krystal 2600 Waterproo ng Products Krystal 2000 Product Description Krystal Plug is 1-component, cementitious non-shrink, hydraulic cement-based on crystalline waterproo ng technology. It withstands strong hydrostatic pressure, is breathable, has no odour, no fume & is non ammable. Krystal Plug ensures permanent impermeability of concrete. OR Krystal 2600 Krystal Coat is one-component crystalline waterproo ng slurry that is specially designed to permanently waterproof both old and new concrete. It lowers the permeability of concrete. 01
METHOD STATEMENT FOR BASEMENT WATERPROOFING Conseal 300/Costar 1k Product Description Waterproo ng Products Conseal 300 CONSEAL 300 is a pure bitumen emulsion, with excellent elastic property used for long-lasting waterproo ng. It is a single component liquid which dries to form a black exible coating. OR Costar 1k Costar 1K is a blend of Portland cement, well graded quartz sand and polymer enhanced chemical ingredients which when mixed with water, forms a waterproof coating for concrete surfaces. It can be used above or below the grade. For areas with low water table: Hydropruf WP 300/ Krystal coat Product Description Waterproo ng Products Hydropruf WP 300 Hydropruf WP 300 is an integral waterproo ng admixture specially designed to improve the quality of concrete and mortar by waterproo ng and reducing the water demand for required workability and minimizes segregation and bleeding. OR Krystal Coat Krystal Coat is one-component crystalline waterproo ng slurry that is specially designed to permanently waterproof both old and new concrete. It lowers the permeability of concrete. 02
METHOD STATEMENT FOR BASEMENT WATERPROOFING For sealing joints: PVC Water stop/ Swellable Water Stop Product Description PVC Water stop Water Stop COSTAR PVC Waterstop is extruded from a high grade PVC compound which has been formulated to give excellent exibility and longevity characteristics. OR Swellable Water Stop Costar Swellable Waterstop is hydrophilic swelling waterstop which exhibits excellent durability and water sealing capacity. It expands as it absorbs water and lls concrete joint gaps conforming to the gap variation, ensuring excellent sealing. 5. INVESTIGATION Remove tiles or any other oor covering in order to nd out the location and cause of the leakage. 6. APPLICATION METHOD/TOOLS 6.1 Fit the water stop (Costar PVC Water stop/ Costar Swellable Water Stop) appropriately. (check technical data sheet for detailed application procedure. For areas with high water table: 6.2 Cast Concrete with Krystal 2000/Krystal 2600 Mix Krystal 2000/krystal 2600 with concrete mix based on water to cement ratio in mix. ( See method statement for detailed application procedure) W/C Ratio Dosage based on weight of cement 0.4 0.75% 0.4-0.5 0.80% 0.5-0.55 0.90% 6.3 Application of Krystal Coat Adequate surface preparation is required before the application of the treatment. The surface must be clean, free from dirt or grease and loose particles. The surface should be surface saturated with water. 6.4 Application of Costar 1k (Polymer Modi ed Coating) Add 5 parts of Costar 1K powder to 2 parts of water and mix for at least 3 minutes with a mechanical mixer to a creamy slurry consistency for brush or broom and to a pump-able consistency for spray applications. Apply Costar 1k with a brush or broom, or spray apply on the concrete surface. Leave as a brushed nish or trowel up by a skilled plasterer to a relatively smooth cementitious nish. Apply the second coat as soon as the rst coat has set, but still “green”. 03 02
METHOD STATEMENT FOR BASEMENT WATERPROOFING 6.5 Or Application of Conseal 300 (bituminous waterproo ng membrane) Stir well before using for at least 2-3 min. Apply the CONSEAL 300 onto the surface by roller or brush, until all surfaces is covered. Reinforce always with the CONSEAL Fabric at problem areas, like wall- oor connections, 90o angles, chimneys, pipes, waterspouts (siphon), etc. In order to do that, apply on the still wet CONSEAL 300 a correct cut piece of CONSEAL Fabric, press it to soak, and saturate again with enough CONSEAL 300. We recommend reinforcement of the entire surface, with the CONSEAL Fabric. Use 5-10cm stripe overlapping. After 8-24 hours, apply another layer of the CONSEAL 300. For demanding applications, apply a third layer of the CONSEAL 300. If CONSEAL 300 is to be covered with ceramic tiles, fully saturate with ovendry silica sand (corn-size 0.4-0.8mm) the last layer while still wet. This saturation will create an adhesion bridge to the tile adhesive that will follow. For areas with low water table: 6.6 Cast concrete with Hydropruf 300 Mix Hydropruf 300with concrete mix at 250ml to 500 ml per 50kg bag of cement. ( See method statement for detailed application procedure) 6.7 Substrate Preparation Adequate surface preparation is required before the application of the treatment. The surface must be clean, free from dirt or grease and loose particles. The surface should be surface saturated with water. 6.8 Application of Krystal Coat Mix 3 parts of Krystal Coat powder with 1 part of clean water and mix for at least 3 minutes with a mechanical mixer to a creamy slurry consistency. Apply Krystal Coat either by spray application, brush application or dry-sprinkle and power-trowel or wooden oat application. (See method statement for detailed application procedure). Apply in 2 coatings (vertically and horizontally). 7. INSPECTION, QUALITY CONTROL As part of “Good Practice” the contractor shall apply an inspection procedure to check the quality of the applied protection system. 8. DISCLAIMER AND COSTAR COMPANY ADDRESS All recommendations, statements and technical data herein are based on tests we believe to be reliable and correct, but accuracy and completeness of said tests are not guaranteed and are not to be construed as a warranty either expressed or implied. User shall rely on his or her own information and tests to determine suitability of the product for the intended use and user assumes all risk and liability resulting from his or her use of the product. Nothing contained in any supplied materials relieves the user of the obligation to read and follow the warnings and instruction for each product as set forth in the current Technical Data Sheet, product label and Safety Data Sheet prior to product use away. COSTAR BUILDING PRODUCT SYSTEM Next Generation Solutions For Today’s Construction nigeria Call Technical Support E-mail 234 817 363 3662 technicalsupport@costarchem.com 04
METHOD STATEMENT FOR BASEMENT WATERPROOFING This method statement describes the repair and waterproo ng of basements and retaining walls to best practice. 2.1 LIMITATIONS Ÿ Products shall only be applied in accordance with their intended use. Ÿ The most recent and relevant Product Data Sheets (PDS) and Safety Data Sheets (SDS) shall apply.
1) Waterproofing should be fully bonded and continuous. 2) Compatibility is crucial. Quality is crucial. 3) Get expert input early - Sika has over 100 years of global waterproofing expertise on tap. Version: 0217 BELOW GROUND WATERPROOFING TO BS:8012/2009 Balcony waterproofing over non-habitable space connection to facade Balcony / podium deck
the potential use of the basement. In addition, consideration has to be made for the repair of the waterproofing system if failure were to occur and the consequential loss and the legal disputes resulting from the failure. Implications of BS8102 for New-Build Basements In deciding the method for waterproofing a new-build basement it is
3.7 Waterproofing details in horizontal and vertical areas 16 3.8 Installation of waterproofing membranes 19 3.9 Compartment waterproofing with waterstops 20 4. Welding methods 23 5. Quality control 24 6. Cleaning and inspection of completed waterproofing 26 7. Protection of completed waterproofing 26 8. Proposal for bills of quantities 28 9.
1.1 Hydrathane Exterior Waterproofing Membrane is a liquid-applied waterproofing membrane for use under ceramic or stone tile finishes on external decks and balconies. Scope 2.1 Hydrathane Exterior Waterproofing Membrane has been appraised for use as a deck and balcony waterproofing membrane for buildings within the following scope:
Basement construction, engineered option 19 Basement construction, simplified approach 15 Basement foundation in fill, not recommended 9 Basement foundation in fill, vulnerability to subsurface flooding 1, 9 Basement foundation, in fill placed above BFE 10 Basement foundation, with lowest floor at or above BFE 10
on a number of factors such as the method & type of basement construction, the depth below ground, and the proposed end use. The example designs in this guide are intended to demonstrate how BS 8102 compliant solutions can be achieved for some of the most common basement waterproofing scenarios. Ventilation In addition to dampness from the ground,
Waterproofing Details – Design Under Constrained Conditions Samuel Vesely, B.Sc. Key Words: Waterproofing details, constrained conditions, expansion joints Abstract The research and development (R&D) effort to develop high quality waterproofing materials is an ongoing, worldwide, process.
BASICS!OF!SCRUM!IN!AGILE! Abstract(Basic!Scrum!handbookfor!the!beginners!in! the!Agile!world!and!CSM!(Certified!Scrum! Master)!aspirants.! SudaRamakrishna((Thiparthy .