CA-2 DESIGN ANALYSIS REPORT FOR PROPOSED CONCRETE

2y ago
15 Views
3 Downloads
6.71 MB
33 Pages
Last View : 1m ago
Last Download : 3m ago
Upload by : Mia Martinelli
Transcription

TECHNICAL MEMORANDUMTo:Pete Pellissier, P.E., EA Engineering, Science, and Technology, Inc., PBCFrom:H. Marcus Kim, P.E., Hana Engineers & Consultants, LLCCopy:Bill Brooks, P.E., EA Engineering, Science, and Technology, Inc., PBCDate:20 April 2018Re:Atlantic Wood Industries Containment Area No.2 – Design Analysis Report for ProposedConcrete Slabs for Steel Quads Forming Beds (Final)This technical memorandum summarizes the design analysis performed for the proposedconcrete slabs for the steel quads forming beds at the Atlantic Wood Industries (AWI) Containment AreaNo.2 project site.Assumptions1. Dimensions and forming bed layout for the proposed slabs were provided by Atlantic Metrocast,Inc. (AMI). Pictures of the current forming beds layout are attached.2. Unit weights (pounds per lineal foot) of the steel quads forming beds are as provided by AMI (seeattached email correspondence).3. AMI will install anchor bolts for the steel quads forming beds to the spacing and layout as neededfor their operations after the concrete slabs are constructed.4. Proposed slabs subgrade is assumed to be composed of VDOT 21A stone aggregates. No swellpotential is assumed for this subgrade material.5. Negligible settlement and differential settlement is assumed.Concrete Slab on Grade AnalysisAll equations and analysis methodologies summarized herein are in accordance with thefollowing references unless otherwise noted:1. Departments of the Army and the Air Force, (1987). "Concrete Floor Slabs on Grade Subjected toHeavy Loads" Army Technical Manual TM 5-809-12, Air Force Manual AFM 88-3, Chapter 15.2. Packard, R. G., (1976). "Slab Thickness Design for Industrial Concrete Floors on Grade"(IS195.01D), Portland Cement Association.3. Portland Cement Association (PCA) guidelines reported in the American Concrete Institute,(2006). "Design of Slabs-on-Ground" - ACI 360R-06.4. Spears, Ralph, and Panarese, William, C., (1983), “Concrete Floors on Ground,” Portland CementAssociation, Illinois, Second Edition (Revised 1990).Hana Engineers and Consultants, LLC. 7501 Boulder View Drive Suite 620 Richmond, Virginia 23225 hanaengineers.comAR300772

5. Middlebrooks, T.A. and Bertram, G.E., (1942), “Soil Tests for Design of Runway Pavements.”Highway Research Board Proceedings of Twenty-Second Annual Meeting, Vol.22.The dimensions used in the design analysis of each slab, number of steel quads forming beds andpre-cast and pre-stressed concrete piles are tabulated below. Note we assumed 4 piles per quad at thefull length of the slab.Slab 1Length(ft)445Slab 2405Slab #16Thickness(ft)0.5No. ofQuads2Pile Crosssection (ft2)1No. ofpiles8100.511.364Width (ft)The total load provided from the steel quads on Slabs 1 and 2 are 267,000 lbs and 137,700 lbs,respectively. The self-weight of the slab was calculated using an assumed unit weight of concrete of 150lb/ft3. Using the same unit weight, the total weight of the piles for each slab was derived. The totalweight per slab therefore included the weights of the steel quads, the self-weight of the slabs, and theweight of the piles. When converted to a total stress, the stresses at Slabs 1 and 2 were about 187.5 psfand 190.7 psf, respectively.The following was used as input data for the analysis.Slab Thickness, t (in)Concrete Strength, f 'c (psi)Subgrade Modulus, k (pci)Factor of Safety, FS Uniform Load, slab 1 (psf)Uniform Load, slab 2 (psf)6.040002002.0187.5190.7Using these design input data, the modulus of rupture (MR) is calculated below.𝑀𝑀𝑅𝑅 9 𝑓𝑓′𝑐𝑐MR was 569.21 psi. The allowable bending stress (Fb) was calculated by dividing MR by the factorof safety (FS). The allowable bending stress was determined to be 284.60 psi.The modulus of elasticity (Ec) was approximated as𝐸𝐸𝑐𝑐 57000 𝑓𝑓′𝑐𝑐The modulus of elasticity was therefore about 3,605 ksi. Using reference 1, the stationaryuniformly distributed loads was calculated using the equation 𝐴𝐴𝐴𝐴𝐴𝐴𝐴 ��𝑢𝑢𝑢𝑢𝑢 ��𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 257.876 𝐹𝐹𝑏𝑏 𝑡𝑡 𝑘𝑘 𝐸𝐸𝑐𝑐Where t is the slab thickness. The total allowable stress was about 1,339 psf, which is higher thanthe applied stresses for Slabs 1 and 2 (187.5 psf and 190.7 psf, respectively).Hana Engineers and Consultants, LLC. 7501 Boulder View Drive Suite 620 Richmond, Virginia 23225 hanaengineers.comAR300773

The distributed loads was also calculated using reference 2 using the equation shown below,which resulted in a value of about 1,212 psf, which is considerable higher than the actual applieddistributed ���𝐴𝐴𝐴𝐴𝐴𝐴 ��𝑢𝑢𝑢𝑢𝑢 ��𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 0.123 𝐹𝐹𝑏𝑏 𝑡𝑡 𝑘𝑘As a secondary check, we used the PCA procedure reported in ACI 360R (2006) for plain concreteslabs. Using the table below (Table 1) for a 6-inch slab, k 200 pci, working stress of 300 psi, an allowableload of 1,340 psf is estimated at the critical aisle width.Table 1. Allowable Distribution Loads, Unjointed Aisles, Uniform Loading, and Variable Layout; (Table A-1.4.2in Appendix A of ACI 360R)Since negligible moment and shear are applied to the slab on grade, the procedure outlined inSection 6.3 in Reference 3 is used to determine the amount of non-prestressed reinforcement neededas shrinkage and temperature reinforcement and to control crack widths. This reinforcement is notintended to serve as flexural reinforcement. The cross-sectional area in square inches of steel per linearfoot (As) is calculated using the equation below.Hana Engineers and Consultants, LLC. 7501 Boulder View Drive Suite 620 Richmond, Virginia 23225 hanaengineers.comAR300774

𝐴𝐴𝑠𝑠 𝐹𝐹 𝐿𝐿 𝑤𝑤2 𝑓𝑓𝑠𝑠Where F is the friction factor of 1.5, L is the distance between the free ends of the slab that canmove due to shrinkage or expansion, w is the dead weight of the slab in psf, and fs is the allowable stressin the reinforcement (2/3 of the yield strength reinforcing steel, fy). The yield strength of reinforcingsteel (fy) is 60,000 psi. The above equation resulted in As equal to 0.056 in2/ft and 0.036 in2/ft for Slabs1 and 2, respectively. Thus for slab reinforcement, we recommend using a 6x6 W4.0xW4.0 welded wirereinforcement. This reinforcement has an As of 0.080 in2/ft in the longitudinal and transverse directions,and has an approximate weight of 58 lbs per 100 ft2.PCA suggests the spacing between contraction joints between 12 and 18 feet for a 6-inch plainslab on grade. This range is a function of concrete slump and aggregate size. We recommend contractionjoint spacing of 15 feet, which corresponds to slump of about 4 inches and aggregate size equal to orgreater than ¾-in. The joint groove should be 1.5-inches deep, which corresponds to about ¼ thethickness of the slab. Conventional saw-cut joints are typically run within 4 to 12 hours after the concretehas been finished.AMI is responsible for the installation of quads forming beds to the slabs. It is our understandingthe quads forming beds will be fastened to the slabs via anchor bolts that will be drilled and grouted intothe slab. We don’t foresee any negative impact to the overall performance and the life-span of the slabsresulting from these anticipated activities associated with installing the quads forming beds to the slab.Attachments:-Pictures of AMI’s current steel quads forming beds.Email correspondence from AMI regarding steel quads forming bed weights, dated March 7,2016.Hana Engineers and Consultants, LLC. 7501 Boulder View Drive Suite 620 Richmond, Virginia 23225 hanaengineers.comAR300775

Picture 1 – Existing two steel quads forming beds for 12-inch by 12-inch concrete piles.Picture 2 – Existing one steel quads forming bed for 14-inch by 14-inch concrete piles.AR300776

oss Worsham rworsham@atlanticmetrocast.com Monday, March 7, 2016 8:24 AMmarcus.kim@hanaengineers.comRE: Prestress conc. pile formsMarcus,The 14 inch quad tube pile form weigh 340 lbs/LF. I would figure 300 lbs/LF for the 12 inch quad pile form.Ross F. WorshamAtlantic wood industries, inc.Atlantic metrocast, inc.Phone (912) 966-7029Fax (912) 964-1331Cell (912) 667-5695AMI on LinkedInFrom: marcus.kim@hanaengineers.com [mailto:marcus.kim@hanaengineers.com]Sent: Sunday, March 06, 2016 11:53 PMTo: Ross WorshamSubject: Prestress conc. pile formsRoss,Do you know how much those steel forms weigh? Do you have any specs on those Hamilton Piling Forms? Couldn’t findmuch from their website Thanks,H. Marcus Kim, P.E.Geotechnical EngineerHANA Engineers and Consultants, LLC757.701.9382www.hanaengineers.com1AR300777

AWI CA2 SLABSPortsmouth, VAApril 20, 2018SECTION 03 30 00CAST-IN-PLACE CONCRETE SLAB05/14PART 11.1GENERALREFERENCESThe publications listed below form a part of this specification to theextent referenced. The publications are referred to within the text by thebasic designation only.AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)ACI 117(2010; Errata 2011) Specifications forTolerances for Concrete Construction andMaterials and CommentaryACI 121R(2008) Guide for Concrete ConstructionQuality Systems in Conformance with ISO9001ACI 211.1(1991; R 2009) Standard Practice forSelecting Proportions for Normal,Heavyweight and Mass ConcreteACI 301(2010; Errata 2011) Specifications forStructural ConcreteACI 302.1R(2004; Errata 2006; Errata 2007) Guide forConcrete Floor and Slab ConstructionACI 304R(2000; R 2009) Guide for Measuring,Mixing, Transporting, and Placing ConcreteACI 305R(2010) Guide to Hot Weather ConcretingACI 306.1(1990; R 2002) Standard Specification forCold Weather ConcretingACI 306R(2010) Guide to Cold Weather ConcretingACI 308.1(2011) Specification for Curing ConcreteACI 318(2014; Errata 1-2 2014) Building CodeRequirements for Structural Concrete andCommentaryACI 347(2004; Errata 2008; Errata 2012) Guide toFormwork for ConcreteACI SP-2(2007; Abstract: 10th Edition) ACI Manualof Concrete InspectionACI SP-66(2004) ACI Detailing ManualSECTION 03 30 00Page 1AR300778

AWI CA2 SLABSPortsmouth, VAApril 20, 2018ASTM INTERNATIONAL (ASTM)ASTM A1064/A1064M(2014) Standard Specification forCarbon-Steel Wire and Welded WireReinforcement, Plain and Deformed, forConcreteASTM C1017/C1017M(2013) Standard Specification for ChemicalAdmixtures for Use in Producing FlowingConcreteASTM C1077(2014) Standard Practice for LaboratoriesTesting Concrete and Concrete Aggregatesfor Use in Construction and Criteria forLaboratory EvaluationASTM C1107/C1107M(2014) Standard Specification for PackagedDry, Hydraulic-Cement Grout (Nonshrink)ASTM C1218/C1218M(1999; R 2008) Standard Specification forWater-Soluble Chloride in Mortar andConcreteASTM C1260(2014) Standard Test Method for PotentialAlkali Reactivity of Aggregates(Mortar-Bar Method)ASTM C143/C143M(2012) Standard Test Method for Slump ofHydraulic-Cement ConcreteASTM C150/C150M(2012) Standard Specification for PortlandCementASTM C1602/C1602M(2012) Standard Specification for MixingWater Used in Production of HydraulicCement ConcreteASTM C172/C172M(2014a) Standard Practice for SamplingFreshly Mixed ConcreteASTM C173/C173M(2014) Standard Test Method for AirContent of Freshly Mixed Concrete by theVolumetric MethodASTM C231/C231M(2014) Standard Test Method for AirContent of Freshly Mixed Concrete by thePressure MethodASTM C260/C260M(2010a) Standard Specification forAir-Entraining Admixtures for ConcreteASTM C31/C31M(2012) Standard Practice for Making andCuring Concrete Test Specimens in the FieldASTM C33/C33M(2013) Standard Specification for ConcreteAggregatesASTM C39/C39M(2014a) Standard Test Method forCompressive Strength of CylindricalSECTION 03 30 00Page 2AR300779

AWI CA2 SLABSPortsmouth, VAApril 20, 2018Concrete SpecimensASTM C42/C42M(2013) Standard Test Method for Obtainingand Testing Drilled Cores and Sawed Beamsof ConcreteASTM C494/C494M(2013) Standard Specification for ChemicalAdmixtures for ConcreteASTM C618(2012a) Standard Specification for CoalFly Ash and Raw or Calcined NaturalPozzolan for Use in ConcreteASTM C94/C94M(2014b) Standard Specification forReady-Mixed ConcreteASTM C989/C989M(2014) Standard Specification for SlagCement for Use in Concrete and MortarsASTM E329(2014a) Standard Specification forAgencies Engaged in the Testing and/orInspection of Materials Used inConstructionCONCRETE REINFORCING STEEL INSTITUTE (CRSI)CRSI 10MSP1.2(2009; 28th Ed) Manual of Standard PracticeDEFINITIONSa."Cementitious material" as used herein must include all Portlandcement, pozzolan, fly ash, ground granulated blast-furnace slag, andsilica fume.b."Exposed to public view" means situated so that it can be seen from eyelevel from a public location after completion of the construction. Apublic location is accessible to persons not responsible for operationor maintenance of the building.c."Chemical admixtures" are materials in the form of powder or fluidsthat are added to the concrete to give it certain characteristics notobtainable with plain concrete mixes.e."Design strength" (f'c) is the specified compressive strength ofconcrete at 28 days to meet structural design criteria.g."Mixture proportioning" is the process of designing concrete mixtureproportions to enable it to meet the strength, service life andconstructability requirements of the project while minimizing theinitial and life-cycle cost.h."Mixture proportions" are the masses or volumes of individualingredients used to make a unit measure (cubic meter or cubic yard) ofconcrete.i."Pozzolan" is a siliceous or siliceous and aluminous material, which initself possesses little or no cementitious value but will, in finelydivided form and in the presence of moisture, chemically react withcalcium hydroxide at ordinary temperatures to form compounds possessingSECTION 03 30 00Page 3AR300780

AWI CA2 SLABSPortsmouth, VAApril 20, 2018cementitious properties.j."Workability (or consistence)" is the ability of a fresh (plastic)concrete mix to fill the form/mold properly with the desired work(vibration) and without reducing the concrete's quality. Workabilitydepends on water content, chemical admixtures, aggregate (shape andsize distribution), cementitious content and age (level of hydration).k."Owner's Representative" is defined as representative(s) of HanaEngineers and Consultants, LLC.1.3SUBMITTALSOwner approval is required for submittals with a "G" designation;submittals not having a "G" designation are for Contractor Quality Controlapproval. Submit the following in accordance with Section 01 33 00SUBMITTAL PROCEDURES:SD-01 Preconstruction SubmittalsQuality Control Plan; GSD-02 Shop DrawingsReproduction of contract drawings are unacceptable.FormworkReinforcing steel; GForm Removal Schedule; GAs-Built Drawings; GSD-03 Product DataMaterials For FormsAdmixturesNon-Shrink Grout; GSD-05 Design DataConcrete mix design; GSD-06 Test ReportsConcrete Mixture Proportions; GComplementary Cementitious MaterialsCompressive strength tests; GAggregate; GAir Content; GSlump Tests; GSECTION 03 30 00Page 4AR300781

AWI CA2 SLABSPortsmouth, VAApril 20, 2018Ion Concentration; GWater; GSD-07 CertificatesCuring Concrete Elements; GConcrete Manufacturer's Qualifications; GConcrete Contractor's Qualifications; GField Testing Technician And Testing Agency; GCertificates Of Compliance; G1.4MODIFICATION OF REFERENCESAccomplish work in accordance with ACI publications except as modifiedherein. Consider the advisory or recommended provisions to be mandatory.Interpret reference to the "Building Official," the "Structural Engineer,"and the "Architect/Engineer" to mean the Owner's Representative.1.5DELIVERY, STORAGE, AND HANDLINGFollow ACI 301, and ACI 304R and requirements and recommendations. Do notdeliver concrete until forms, reinforcement, embedded items, and chamferstrips are in place and ready for concrete placement. Do not storeconcrete curing compounds or sealers with materials that have a highcapacity to adsorb volatile organic compound (VOC) emissions. Do not storeconcrete curing compounds or sealers in occupied spaces.1.5.1ReinforcementStore reinforcement of different sizes and shapes in separate piles orracks raised above the ground to avoid excessive rusting. Protect fromcontaminants such as grease, oil, and dirt. Ensure bar sizes can beaccurately identified after bundles are broken and tags removed.1.6QUALITY ASSURANCE1.6.11.6.1.1Design DataConcrete Mix DesignFifteen days minimum prior to concrete placement, submit a contractorfurnished mix design for the design strength of 4,000 psi concrete. Submita complete list of materials including type; brand; source and amount ofcement, complementary cementitious materials (if used), and admixtures; andapplicable reference specifications. Submit mill test and all other testfor cement, complementary cementitious materials, aggregates, andadmixtures. All test results must be within 21 days of submittal date.Provide documentation of maximum nominal aggregate size, gradationanalysis, percentage retained and passing sieve, and a graph of percentageretained verses sieve size. Provide mix proportion data using at leastthree different water-cementitious material ratios for each type ofmixture, which produce a range of strength encompassing those required foreach type of concrete required. If source material changes, resubmit mixproportion data using revised source material. Provide only materials thathave been proven by trial mix studies to meet the requirements of thisSECTION 03 30 00Page 5AR300782

AWI CA2 SLABSPortsmouth, VAApril 20, 2018specification, unless otherwise approved in writing by the Owner'sRepresentative. Indicate clearly in the submittal where each mix design isused when more than one mix design is submitted. Resubmit data on concretecomponents if the qualities or source of components changes.1.6.21.6.2.1Shop DrawingsFormworkACI 347. Drawings showing details of formwork including, but not limitedto; joints, supports, and sequence of form and shoring removal. Indicateplacement schedule, construction, location and method of forming controljoints. Include locations of inserts, and other embedded items.Reproductions of contract drawings are unacceptable. Submit Form RemovalSchedule indicating elements and minimum length of time for form removal.Design, fabricate, erect, support, brace, and maintain formwork so that itis capable of supporting without failure all vertical and lateral loadsthat may reasonably be anticipated to be applied to the formwork.1.6.2.2Reinforcing SteelACI SP-66. Indicate assembly diagrams, splicing and laps of bars, shapes,dimensions, and details of reinforcing steel, accessories, and concretecover. Do not scale dimensions from structural drawings to determinelengths of reinforcing bars. Reproductions of contract drawings areunacceptable.1.6.31.6.3.1CertificatesCuring Concrete ElementsSubmit proposed materials, methods and duration for curing concreteelements in accordance with ACI 308.1.1.6.3.2Concrete Manufacturer's QualificationsSubmit a certification indicating that the firm is experienced inmanufacturing and transporting ready-mixed concrete products and thatcomplies with ASTM C94/C94M requirements for production facilities andequipment. Manufacturer shall be certified according to NRMCA's "NRMCAQuality Control Manual - Section 3, Certification of Ready Mixed ConcreteProduction facilities."1.6.3.3Concrete Contractor's QualificationsSubmit qualifications of an installer who employs on-project personnelqualified as ACI-certified Flatwork Technician and Finisher and asupervisor who is an ACI-certified Concrete Flatwork Technician. Concreteconstruction firm shall be experienced in the framing, reinforcing,placing, finishing, curing, and repairing cast-in-place concrete.1.6.3.4Quality Control PlanDevelop and submit for approval a quality control plan in accordance withthe guidelines of ACI 121R and as specified herein. The plan shall includeplans for the concrete supplier, the reinforcing steel supplier, and theinstaller and address aspects of the mix design, materials, and workmanshipthat may affect the ultimate performance of the structure to meet theSECTION 03 30 00Page 6AR300783

AWI CA2 SLABSPortsmouth, VAApril 20, 2018operational objectives. Maintain a copy of ACI SP-15 and CRSI Manual ofPractice at the project site.1.6.3.5Field Testing Technician and Testing AgencySubmit data on qualifications of proposed testing agency and techniciansfor approval by the Owner's Representative prior to performing any work.a. Work on concrete under this contract shall be performed by an ACIConcrete Field Testing Technician Grade 1 qualified in accordance withACI SP-2 or equivalent. Equivalent certification programs shallinclude requirements for written and performance examinations asstipulated in ACI SP-2.b. Testing agencies that perform testing services on reinforcing steelshall meet the requirements of ASTM E329.c. Testing agencies that perform testing services on concrete materialsshall meet the requirements of ASTM C1077.1.6.3.6Certificates of ComplianceSubmit manufacturer's certificates of compliance for the following materialshowing that the named material conforms to the requirements of theContract Documents. The manufacturer's certifications shall name theappropriate materials, the publication or publications specified ascontrolling the quality of that item, and shall state that the itemconforms to the requirements specified. Certificates shall be printed onthe manufacturer's letterhead and shall be signed by the manufacturer'sofficial authorized to sign certificate of compliance, and having legalauthority to bind the manufacturer. Furnishing certificates of complianceshall not provide relief the Contractor of responsibility for providingmaterials that conform to the requirements of the Contract orcement.Cement and complementary cementitious materials.Test Reports1.6.4.1Concrete Mixture Proportionsa. Submit copies of test reports by independent test labs conforming toASTM C1077 showing that the mixture has been successfully tested toproduce concrete with the properties specified and that mixture will besuitable for the job conditions. Test reports shall be submitted alongwith the concrete mixture proportions.1.6.4.2Fly Ash and PozzolanIf used in the Contractor furnished mix design, submit test results inaccordance with ASTM C618 for fly ash and pozzolan. Submit test resultsperformed within 6 months of submittal date.1.6.4.3Ground Granulated Blast-Furnace SlagIf used in the Contractor furnished mix design, submit test results inaccordance with ASTM C989/C989M for ground granulated blast-furnace slag.SECTION 03 30 00Page 7AR300784

AWI CA2 SLABSPortsmouth, VAApril 20, 2018Submit test results performed within 6 months of submittal date.1.6.4.4AggregatesSubmit test results for aggregate quality in accordance with ASTM C33/C33M,and the combined gradation curve proposed for use in the work and used inthe mixture qualification. Where there is potential for alkali-silicareaction, provide results of tests conducted in accordance with ASTM C1260for potential alkali-silica reactions.1.6.4.5AdmixturesSubmit test results in accordance with ASTM C494/C494M and ASTMASTM C1017/C1017M for concrete admixture, ASTM C260/C260M forair-entraining agent, and manufacturer's literature and test reports forcorrosion inhibitor and anti-washout admixture as applicable. Submitteddata shall be based upon tests performed within 6 months of submittal.1.6.4.6CementSubmit test results in accordance with ASTM C150/C150M Portland cement.Submit current mill data.1.71.7.1ENVIRONMENTAL CONDITIONSCold Weather ConcretingComply with ACI 306R.1.7.2Hot Weather ConcretingComply with ACI 305R.PART 22.1PRODUCTSMATERIALS FOR FORMSProvide wood, plywood, or steel. Use plywood or steel forms where a smoothform finish is required. Lumber shall be square edged or tongue-and-grooveboards, free of raised grain, knotholes, or other surface defects.Plywood: PS-1, B-B concrete form panels or better. Steel form surfacesshall not contain irregularities, dents, scale, or sags.2.2FORM TIES AND ACCESSORIESProvide a form tie system that does not leave mild steel after break-off orremoval any closer than 2 inches from the exposed surface. Do not use wirealone. Form ties and accessories must not reduce the effective cover of thereinforcement.2.32.3.1CONCRETEConcrete StrengthConcrete shall have a minimum compressive strength (f'c) at 28 days of4,000 psi.SECTION 03 30 00Page 8AR300785

AWI CA2 SLABSPortsmouth, VA2.3.2April 20, 2018Contractor Furnished Mix DesignContractor shall determine the appropriate concrete mixture that meets therequirements in the contract documents. Follow ACI 211.1 recommendedpractice for selecting proportions for normal weight concrete to be used inthe work. Strength requirements shall be based on 28-day compressivestrength determined by 6 by 12 inch cylindrical specimen in accordance withASTM C39/C39M.2.3.3Complementary Cementitious MaterialsThe concrete mixture may contain one or combination of the complementarycementitious material listed below. Total complementary cementitiousmaterial (individually or combined) shall not exceed 25 percent of cementcontent by weight.2.3.3.1Fly AshASTM C618, Type F or C; fly ash shall not exceed 25 percent of cementcontent by weight. Blast furnace slag products, if proposed in a concretemix, shall not exceed 25 percent of the cement content by weight. Thecombination of these two products, if proposed in a submitted mix design,shall not exceed 25 percent of the mix cement content by weight.2.3.3.2Raw or Calcined Natural PozzolanNatural pozzolan must be raw or calcined and conform to ASTM C618, Class N,including the optional requirements for uniformity and effectiveness incontrolling Alkali-Silica reaction and must have an ignition loss notexceeding 3 percent. Class N pozzolan for use in mitigating Alkali-SilicaReactivity must have a Calcium Oxide (CaO) content of less than 13 percentand total equivalent alkali content less than 3 percent.2.3.3.3Ground Granulated Blast-Furnace SlagASTM C989/C989M, Grade 120.2.3.4Portland CementProvide cement that conforms to ASTM C150/C150M, Type I or Type II. Cementshall be free from water soluble salts or alkalis which will causeefflorescence on exposed surfaces. Use only one brand of cement for eachtype of cement throughout project. No visual variations in color shallresult in exposed concrete.2.3.5WaterWater must comply with the requirements of ASTM C1602/C1602M. Minimize theamount of water in the mix. Improve workability by adjusting the gradingrather than by adding water. Water must be potable; free from injuriousamounts of oils, acids, alkalis, salts, organic materials, or othersubstances deleterious to concrete. Submit test report showing watercomplies with ASTM C1602/C1602M.2.3.62.3.6.1AggregatesNormal Weight Fine AggregateNormal weight fine aggregate shall be washed, inert, natural sandSECTION 03 30 00Page 9AR300786

AWI CA2 SLABSPortsmouth, VAApril 20, 2018conforming to ASTM C33/C33M.2.3.6.2Normal Weight Coarse AggregateNormal weight coarse aggregate shall be well-graded crushed stoneconforming to ASTM C33/C33M. Maximum designated sizes for normal weightcoarse aggregate to be used in concrete sections shall be 3/4-inch for allconcrete work.2.3.7AdmixturesWater-reducing admixture: Shall comply with ASTM C494/C494M, Type A, andcontain no more than .05 percent chloride ions.High-Range Water Reducing (HRWR) admixture (Super Plasticizer) shall not beused for this project.Use air entrainment admixture for all concrete in accordance withmanufacturer's written instructions. Minimum air content for all sizes ofaggregate shall range from 4 to 7 percent in exterior environment. Airentraining admixture shall comply with ASTM C260/C260M.Evaporation retarder shall use water-based monomolecular film; use one ofthe following with flatwork containing corrosion inhibiter or silica fumeadmixture.Water-reducing Set Retarders: Conform with ASTM C494/C494M Type D and maybe used when ambient temperatures exceed 80 degrees F.Accelerator admixture: Non-chloride and non-corrosive accelerators shallconform to ASTM C494/C494M Type C and may be used when temperatures arebelow 50 degrees F.2.4NON-SHRINK GROUTASTM C1107/C1107M2.52.5.1REINFORCEMENTReinforcing SteelUse ASTM A1064/A1064M, steel wire/welded wire reinforcement mat.2.5.2Reinforcing Bar SupportsSupports include bolsters, chairs, spacers, and other devices necessary forproper spacing, supporting, and fastening reinforcing barsProvide wire bar type supports of coated or non-corrodible materialconforming to ACI SP-66 and CRSI 10MSP.Legs of supports in contact with formwork must befabrication, or stainless-steel bar supports.PART 33.1plastic coated afterEXECUTIONEXAMINATIONDo not begin installation until substrates have been properly constructed;SECTION 03 30 00Page 10AR300787

AWI CA2 SLABSPortsmouth, VAApril 20, 2018verify that substrates are level.Check field dimensions before beginning installation.3.2PREPARATIONDetermine quantity of concrete needed and minimize the production of excessconcrete. Designate locations or uses for potential excess concrete beforethe concrete is poured; such locations shall be approved by the Owner'sRepresentative before the concrete is placed.3.2.1GeneralSurfaces against which concrete is to be placed must be free of debris,loose material, standing water, snow, ice, and other deleterious substancesbefore start of concrete placing.Remove standing water without washing over freshly deposited concrete.Divert flow of water through side drains provided for such purpose.3.2.2Foundation Subgrade PreparationExcavate and grade bottom of foundation accurately to provide uniformbearing and support for the slabs. Ensure that subgrades have beeninspected and approved by the Owner's Representative prior to concreteplacement.3.2.3Reinforcement and Other Embedded ItemsSecure reinforcement, joint materials, and other embedded

ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection ACI SP-66 (2004) ACI Detailing Manual SECTION 03 30 00 Page 1 AR300778. AWI CA2 SLABS Portsmouth, VA April 20, 2018 ASTM INTERNATIONAL (ASTM) ASTM A1064/A1064M (2014) Standard Specification for Carbon-Steel Wi

Related Documents:

Present ICE Analysis in Environmental Document 54 Scoping Activities 55 ICE Analysis Analysis 56 ICE Analysis Conclusions 57 . Presenting the ICE Analysis 59 The ICE Analysis Presentation (Other Information) 60 Typical ICE Analysis Outline 61 ICE Analysis for Categorical Exclusions (CE) 62 STAGE III: Mitigation ICE Analysis Mitigation 47 .

Research Design: Financial Performance Analysis In this study, financial performance analysis will be used. The analysis is based on three types of analysis methods which are horizontal analysis, trend analysis and ratio analysis. All data analysis is based on the items on the financial statement. A financial statement is a written record

Design and Analysis Software v2 file used as a template to contain primary analysis and secondary analysis settings. This option can be used for the analysis of legacy EDS or SDS files when a specific set of primary and secondary analysis settings are needed. The primary and secondary analysis settings will be used when the analysis (-a) option .

Legal Design Service offerings Legal Design - confidential 2 Contract design Litigation design Information design Strategy design Boardroom design Mastering the art of the visual Dashboard design Data visualization Legal Design What is especially interesting in the use of visual design in a p

Module 7: Fundamental Analysis (NCFM Certification) 1. Introduction of Fundamental Analysis What is Fundamental & Technical Analysis? Difference between technical & fundamental analysis Features & benefits of Fundamental analysis 2. Top-Down Approach in Fundamental Analysis Economic Analysis Industry Analysis Company analysis 3.

Qualitative analysis, quantitative analysis, non-financial indicator analysis, financial indicator analysis, internal performance analysis, external performance analysis, project-orientated analysis, organization-orientated analysis 8 [36] Area-based Knowledge measurement in products and processes,

Oasys GSA Contents Notation 8 Degrees of freedom 10 Active degrees of freedom 10 Degrees of Freedom with no Local Stiffness 11 Analysis Options 13 Static Analysis 13 Static P-delta Analysis 13 Modal Analysis 14 Modal P-delta Analysis 14 Ritz Analysis 15 Modal Buckling Analysis 16 Model Stability Analysis 17 Non-linear Static Analysis 18

Qualitative Analysis of Anions 1 Experiment 10 Qualitative Analysis of Anions Pre-Lab Assignment Before coming to lab: Read the lab thoroughly. Answer the pre-lab questions that appear at the end of this lab exercise. The questions should be answered on a separate (new) page of File Size: 343KBPage Count: 16Explore further(PDF) Experiment Report: Analysis of Anions and Cations .www.academia.eduExperiment 7 Qualitative Analysis: Anionswww.csus.eduLab Experiment #8: Qualitative Analysis of Common Anions .www.youtube.comQualitative Analysis of Anions - Odinitywww.odinity.comLab 13 Qualitative Analysis of Cations and Anionsdoctortang.comRecommended to you b