ROOF MAINTENANCE GUIDERCABC Guarantee Corp. (RGC)CONTENTS1.OVERVIEW1.11.22.BASIC PREVENTATIVE MAINTENANCE2.12.22.32.42.53.Defects in Built-Up Bituminous RoofingDefects in Flexible MembranesMaintenance for Steep RoofingTHE ROOFSTAR GUARANTEE4.14.24.35.Maintenance ProgramInspectionDo's and Don'ts of Roof MaintenanceRoof PlanRGC Roofing Maintenance ChecklistIDENTIFYING ROOFING DEFECTS3.13.23.34.Roof Types (Definitions)Membrane Types (Most Common)Required Maintenance ItemsSuggested InspectionsFive (5) Year and Ten (10) Year Guarantee Program GuidelinesGLOSSARY OF COMMON ROOFING TERMS1

1.OVERVIEWThe most important reason for establishing a program of regular roof maintenance is to protect theowner's investment. A properly executed maintenance program will add years to the life of theroof by detecting minor problems before they become major, as well as providing better protectionfor, and avoiding interruption of, the internal functions of the building.A roof system is exposed to all manner of chemical and physical stress. The long term effects ofthese forces are called "Normal Aging". In reality, small isolated problems caused through abuse,stress concentration, inadequate ventilation, error, or other factors result in a shortened lifespan ofthe roofing system.Small problems or defects, if not detected and repaired, inevitably become major problemsaffecting the performance of the whole roof system.Roofs represent approximately 5 to 7% of capital building costs - but roofs cover 100% of thebuilding and its contents.1.1ROOF TYPES (DEFINITIONS)MEMBRANE ROOFINGConventional UninsulatedRoof membrane is installed directly to the deck (usually wood or concrete), and is exposed to theweather. There is no insulation directly below the membrane. In a wood deck of this type theinsulation, if used, is typically installed in the supporting joist space, which must be cross-vented.Conventional InsulatedRoof membrane is installed directly over insulating materials, which are installed on the deck(wood, concrete or steel). The membrane is exposed to the weather.Protected (or Inverted) MembraneRoof membrane is installed directly to the deck (wood, concrete or overlaid steel). Extrudedpolystyrene is installed over the membrane covered by filter fabric and appropriate ballast. Ballastis required to counteract insulation flotation and wind uplift, and to provide ultraviolet resistance forthe insulation. A modified protected membrane includes insulation both above and below themembrane. It is often used to provide slope to the membrane in order to improve drainage or tomove the dew point away from the membrane.STEEP ROOFINGIn the context of this guide, steep roofing may be defined as roofs with asphalt shingles, cedarshakes or shingles or metal roofing on slopes that exceed 1:6 (2" in 12").2

1.2MEMBRANE TYPES (MOST COMMON)Built-Up Roofing (also called "Tar & Gravel" or "BUR")A continuous, relatively inflexible roof assembly consisting of plies (usually 3 or 4) of saturatedfelts or fabrics between which layers of bitumen (asphalt, pitch, or modified rubberized asphalt) isapplied. The roof is usually surfaced with gravel to provide ultraviolet protection.Flexible MembranesFlexible membranes encompass a large number of unique membranes installed in single or multiply applications. The materials may be bituminous or non-bituminous and offer a wide choice ofphysical properties and performance.The key point with these membranes — from a maintenance and repair standpoint — is that eachtype is unique. The building owner must be aware of the specific type and product in place inorder to know what maintenance is required and what specialized repair materials and methodsshould be used.Remember: "This Roof May Be Different"Common Types of Flexible Membranes are:Modified BitumenA generic description for pre-manufactured sheet membranes consistingof asphalt, modified with a polymer, which improves the physicalproperties of the asphalt and coated on a reinforcing mat or carrier.Different polymers offer different physical properties. Sheets may beinstalled either in hot asphalt or by heating with a propane torch, and insome cases they may be self-adhesive. Applications normally consist of2 plies but may be a single ply in certain well sloped applications.Modified Bitumen Membranes are used in all roof types.EPDM (Ethylene PropyleneDiene Monomer)A generic description for synthetic rubber sheet membranes. Appliedonly in single-ply applications on all roof types. Seams are accomplishedwith proprietary adhesives.PVC (Polyvinyl Chloride andTPO (Thermoplastic polyolefin) Generic descriptions for a plastic sheet membrane. Applied in singleply applications on all roof types. Seams are accomplished by fusioneither with solvent or hot-air welding techniques.Although these are the most commonly used generic flexible membranes, there are other types on themarket (each of which, as mentioned, requires special knowledge and techniques). Make sure you knowwhat you are dealing with.3

2.BASIC PREVENTIVE MAINTENANCE2.1MAINTENANCE PROGRAMA preventive maintenance program is simply a program of scheduled inspections and subsequentcorrective action. The purpose is to maximize the life expectancy of the roofing system, thusproviding maximum protection to building and contents and minimizing overall costs.The basic elements of a preventive maintenance program for roofs are: Regular visual inspections to determine the current condition of the roof membrane andflashings. Immediate repair of any defect before it allows moisture to enter the roof system or buildinginterior. Non-destructive moisture detection to determine if moisture has infiltrated into the insulationof the roof system.A vital part of the condition of the roof system is whether or not the insulation remains dry. A roofmay appear to be in excellent condition from the surface, but may have areas of saturatedinsulation, which severely affect the thermal efficiency of the roof.Non-destructive moisture detection of roof systems has developed into a sophisticated techniquethat can provide accurate analysis of roof insulation condition. Two commonly used systems arenuclear meter and infrared thermography. Both systems require trained skilled operators, specificweather conditions, specific roof types, and professional analysis. Visual inspection by a trainedperson is the key to a successful maintenance program.2.2INSPECTIONRoofs should be inspected at least twice a year — spring and fall — and also after any significantweather or construction event.The inspection should be preceded by the preparation of a detailed roof plan on which all defectsor notes can be marked. If the inspection indicates that more than minor work is required, aninspection checklist is necessary to ensure thoroughness. Call your professional roofingcontractor to perform the required maintenance work.A typical roof plan and an inspection checklist are included in this guide for your convenience.Begin the inspection by looking at the underside of the deck, if accessible, and also at the outsideof the building. Look for cracks, stains, rusting, watermarks, efflorescence, wet spots, spalledmortar etc. or other signs of excessive moisture or deterioration. The observations may give cluesto not only roofing problems but also other conditions affecting the performance of the buildingenvelope.The final and most important part is inspecting the roof itself. The keys to a competent roofinspection are thoroughness and attention to detail — be prepared to get dirty!4

2.3 DO'S AND DON'TS OF ROOF MAINTENANCEDO's: Do be aware that wise maintenance will prolong the life of any roof — even the best of them. Do perform inspections at least twice a year, preferably at the end of winter and right aftersummer, when roofs have passed through the periods of severest stress. Do conduct additional inspections immediately after unusual occurrences such as extremelyheavy rains, high winds, hail, nearby fires, explosions, etc. Do check the building exterior for settlement or movement. Cracks in the wall are a warning ofpossible cracks in the roofing and flashing. Are overhangs, cornices, fascias and edging in goodcondition? Are gutters and downspouts satisfactory? Breaks in roof edge elements can causeleaks and also let wind get under the roofing membrane and cause blow-offs. Damaged orclogged gutters, roof drains, and downspouts can cause water back up on the roof. Do be certain that equipment servicemen going on the roof are warned against penetrating ordropping tools on the roof. They should be accompanied by your trained maintenance man toensure no damage to the roof assembly occurs. Do assure that your roof is kept clean and free from debris. Do recognize that exposure of roof felts (bare spots) on a gravel surfaced roof can lead to quickdeterioration. This requires immediate attention by qualified personnel. Do be advised that flashings, gum pans, gravel stops and all other roof penetrations are thesource of most leaks. Pay extreme and careful attention to these items.DON'TS: Don't allow unqualified personnel to maintain your roofs. Don't allow traffic on your roof unless accompanied by your informed maintenance man. Don't allow equipment servicemen to penetrate your roof without being certain that qualifiedpersonnel flash the penetrations. If your roof is covered by a RoofStar Guarantee, RGC or themembrane manufacturer should be notified prior to cutting the roof or altering it in any manner.5

WHEN IT'S TIME TO REROOF:DON'TS: Don't permit products of unproven quality to be used on your roof. Don't be taken in by "Cure-All" products, which can be applied by anyone. Don't take bids on projects without adequate, uniform specifications. Don't reroof over an existing roof unless a careful evaluation is made, and a qualified consultant orstandards authority gives prior approval. Don't expect a guarantee to keep the water out of your buildings. Guarantees do not cover manyof the problem areas of your roof. Don't think that the lowest price is always the best. Be certain you will not be faced with a numberof change order requests for extras after a project is awarded. Don't deal with firms who cannot stand behind their work and will not be available when you needthem. Remember that no product is better than the applicator.DO's: Do hire a professional roofer. Do call a member of RCABC. Do request the RoofStar Guarantee Do benefit from:Independent InspectionsRGC Accepted MaterialsRGC Guarantee Standards6

2.4 ROOF PLANEach roof covered by the RoofStar Guarantee comes with a complete "Roof System Record",which includes a roof plan and a copy of this maintenance guide. If you set up your own roofmaintenance file, you should prepare a roof plan using the following as a guide.Key To Potential Roof Top ProblemsABCDEFGHJKLMNPRSTUVWX- Ponded Water- Skylight- Roof Drain- Vent Pipe- Vent or Fan- Ladder- Walkway- Hatch- Flag Pole- Sign Support- Air Conditioning Unit- Pitch Pan- Chimney & Flashing- Parapet or Fire Wall- Coping- Base Flashing- Cap Flashing- Expansion Joint Cover- Down Spout & Leader- Fascia & Gravel Stop- Roof Vent7

2.5ROOFING MAINTENANCE CHECKLIST (page 1)DATEBUILDINGLOCATIONINSPECTORProblemO.K.MajorI. ROOF CONDITIONA.General AppearanceDebrisDrainagePhysical DamageGeneral ConditionNew Equipment / AlterationsOtherB.Surface ConditionBare Spots in GravelAlligatoring / CrackingSlippageOtherC.Membrane ConditionBlistering / Splitting / RidgingPhysical DamageOtherII. FLASHING CONDITIONA.Membrane FlashingPhysical DamageDeterioration / Blistering /Open LapsAttachmentOtherB.Metal FlashingsPhysical DamageAttachment / te ofRepair

2.5ROOFING MAINTENANCE CHECKLIST (page 2)ProblemO.K.MajorI. ROOF PENETRATIONSA.Equipment1.2.Open LapsPuncturesAttachmentOtherB.Equipment HousingC.Equipment OperationD.Roof Jacks / VentsE.Roof DrainsTypeConditionQuantityOverflowsIV. EXPANSION JOINT COVERSV. GUM PANSFill Material ShrinkageOtherVI. OTHER OBSERVATIONS1.2.3.9MinorObservationDate ofRepair

3IDENTIFYING POTENTIAL ROOFING PROBLEMS OR DEFECTS3.1DEFECTS IN BUILT-UP BITUMINOUS ROOFINGDefect ObservedPossible CauseRequired MaintenanceBlueberry blisters insurface of bitumenExpansion of volatile fractions ofbitumen or of air or water, in sunnyweather. More common with lowmeltpoint bitumens particularly withheavy coatings and poor gravelcover.Initially apply additional opaquegravel. If many blisters occur andare broken to expose felts, recoatwith bitumen and apply heavy layerof opaque gravel.Expansion in sunny weather ofentrapped air or water in areas ofpoor adhesion.Cut blister, trim excess material, readhere and patch. Heavy layer ofopaque gravel may help to preventre-occurrence.Blisters betweenlayers of feltBlisters betweenfelt membrane andsubstrateExpansion in sunny weather ofentrapped air or water, usually overdecks with concrete fills, or withwetted insulation.Ridging or bucklingMovement of either the felts or thedeck or substrate under moistureor thermal effects, causing longripple ridges especially where feltnot well bonded, often overinsulation or deck joints.Lifting at laps(fishmouths)CrackingbreakingorFelt penetrating toppour and gravel atlapsDeterioration due topondingPoor adhesion initially due towrinkled felt or workmanship, orpulling as a result of blister orridging formation.Breaks in unsupported felt.Cracking of blisters or ridges bytraffic. Breaks at sharp bends infelt.Poor workmanship initially resultingin poor adhesion. Curling of feltedges when left exposed too longduring construction.Improper design with no, orinadequate, slopes to drains.Drains at high points on roof orobstructed.10Where possible, cut blister, trimexcess material, re-adhere andpatch. Venting (if possible) mayhelp. Heavy layer of opaque gravelmay help.Usually little can be done. If of smallsize and elevation, a heavyapplication of gravel will make it lessconspicuous and give someprotection. If wide and high, cuttingand relaying is necessary. May reoccur if movement persists.Re-adhere if not wrinkled. Wherewrinkles or fishmouths, cut, removeexcess material, re-adhere andpatch.Cut out, provide support and patch.Cut blister, re-adhere felts andpatch. Round off and patch.Re-adhere if possible, or cut away.Cover with bitumen and gravel. Feltedge must not be exposed.Clear drains. Use additionalbitumen and gravel in the low areas,which may help to limit damage.Add additional drains if possible.

Defect ObservedPossible CauseRequired MaintenanceBare spots fromloss of gravelGravel applied in adverse weather.Too thin a layer of too-fine gravel.Inadequate adhesion of gravel atedges and corners.Recoat with adequate bitumen andapply a heavy dressing of properlysized gravel.General weatherdeterioration ofbitumenInadequate gravel or other surfaceprotection, inadequate bitumen,lack of maintenance.Flashing failuresInadequate allowance formovement. Inadequate fixing intoreglets. Poor adhesion orinadequate protection of strippingfelts. Movement at roof drains orvent pipes. Damage to capping atparapets and expansion joints.Loss of mastic or damage to masticpans.PondingInsufficient slope to drains.Building settlement.Structural movement.If felt strength affected, cannot berejuvenated with coatings. If feltsnot affected, apply new bitumen andgravel protection.Repair with allowance.Re-fix and caulk. Apply new feltsand protect. Allow movement andrepair. Repair to allow movementand shed water. Repair, add freshmastic, counter-flash.Where ponding cannot beeliminated, pumping is sometimesused to remove water from roof afterrain. Add new drains if possible.WindscourInadequate adhesion of gravel.Ballast too small for application.Alligator CrackingSlippageSealingWhere bare spots are due to windscour at corners, it may benecessary to use concrete slabs asthe protective cover in the areaaffected.When alligator cracking of surfacebitumen occurs on bare spots or onsmooth-surface roofs withoutprotective covering, adding morebitumen is only a short-termremedy; cracks will recur.Remove alligatored material andrecoat if possible. Use a feltreinforced recoating. Protect therecoating with gravel or a paintcoating.Slippage of gravel, felts orcomplete membrane on slopingroofs is due to improper choice ofbitumen, thick layers of bitumen,phased construction, excessivelyheavy protective covering, lack ofmechanical fastening whererequired.If not too severe, may correct itselfby change in bitumen properties onexposure. Mechanically fasten ifpossible, or remove and reroof withstiffer bitumen and adequatefastening of components.Deterioration due to U.V.degradation, ozone or otheratmospheric contaminants,physical abuse, normal wear andtear etc.11For skylights and similar roofconstruction, new gasketing orsealants may be required.

3.2DEFECTS IN FLEXIBLE MEMBRANESThe most important thing to remember when dealing with maintenance or repair toany flexible membrane (be it TPO, PVC, EPDM or modified bitumen) is that youmust understand and know the specific system, its components and required repairmaterials and techniques. Do not mix and match materials without specificinstructions from the membrane manufacturer.3.2.1 Modified Bitumen MembranesModified bitumens are in many ways similar to built-up roofing for inspections,maintenance and repairs. Similar defects may appear such as blisters, ridging,buckling and fishmouths. Follow the manufacturer's published repair methods.Particular attention should be given to seam inspection especially at endlaps and "T" joints where moisture may penetrate and migrate.Severe granule loss may result in ultraviolet degradation of the sheetmembrane. Recoat the bare spots with new granules in adhesive.Watch for chemical contamination near roof top units and vents.Watch for deterioration or slipping of base flashings.Wrinkles are not uncommon to the systems; provided they are small andisolated and do not cause an opening across a lap seam, they may not affectperformance.3.2.2 EPDM, TPO and PVC Single Ply MembranesReferring to the checklist, report the general appearance of the roof and thesurface conditions of the membrane.General appearance is primarily a function of housekeeping. Debris, poordrainage, or ponding may be evidence of physical damage.Any discolouration, cracking or splitting, as well as punctures, should be notedand repaired.Seams should be observed for open joints, fishmouthing or ridging.On fully-adhered systems, it is important to note any unadhered areas. Onmechanically-fastened systems, a check should be made to be sure that thereis no evidence of fasteners backing out or popping. On ballasted systems, theweight and depth of stone ballast should be checked against the designspecifications.Any signs of scouring should be noted and all gravel redistributed evenly.If increased foot traffic becomes necessary, be sure to provide walkways.12

The following troubleshooting guide for TPO, PVC and EPDM membranes identifies somedefects and the possible causes.Defect ObservedPossible CauseDiscolouration of MembraneChemical or atmospheric contaminationCracking, crazing, or splitting ofmembranePossible defective membrane. Callmanufacturer immediately.Fishmouthing or open jointsImproper seam welding or adhesive.Loss of adhesion in fully-adheredsystemInterlaminar separation between insulationand facing indicating failure of insulation.Separation between membrane andinsulation indicating improper application ofadhesive. Call manufacturer immediately.Loose fastening in mechanicallyfastened systemFasteners not properly installed. Fastenerstoo short. Buckling, warping, shifting orcorrosive deterioration of deck or structure.Heavy foot traffic.Movement of ballast in loosely laidsystemBallast too small for wind uplift conditions.Foot traffic or vandalism.Ridging or buckling of membrane atinsulation jointsMovement of substrate due to moistu

ROOF MAINTENANCE GUIDE RCABC Guarantee Corp. (RGC) CONTENTS 1. OVERVIEW 1.1 Roof Types (Definitions) 1.2 Membrane Types (Most Common) 2. BASIC PREVENTATIVE MAINTENANCE 2.1 Maintenance Program 2.2 Inspection 2.3 Do's and Don'ts of Roof Maintenance 2.4 Roof Plan 2.5 RGC Roofing Maintenance Checklist 3. IDENTIFYING ROOFING DEFECTSFile Size: 280KB

Related Documents:

1. Roofing system 1 2. Requirement of roofing material 1 3. Metal roofing 1 4. Classification of metal roofing 2 5. Merits of self supported roofing system 3 6. Material and technology 3 7. Specification of galvalume sheet 4 8. Primary sheeting material 4 9. Present systems of self supported roofing 5 10.

6 ROOFING 38 6.01 Leaks in roofing, flashings and accessories 38 6.02 Roof cladding 38 6.03 Roof tiles 38 6.04 Roof tile pointing 38 6.05 Overhang of roofing (tiles and sheet roofing) 39 6.06 Cutting of roof tiles 39 6.07 Dry valley construction

Skyline Roofing Installation Guide April 2019 5 ROOF PREPARATION ASC Building Product's Skyline Roofing can be used in both new construction and retrofit roofing applications .Resistance: Skyline Roofing must be installed over

REPAIRS & MAINTENANCE ROOFING & ROOF DRAINAGE Up to two storeys: fixed to existing roof frame Concrete tiled roof 49 to 75/m2 Terracotta tiled roof 2 62 to 100/m Slate tiled roof (traditional system) 2 300 to 500/m Fibreglass roof 35 to 60/m2 Polycarbonate roofing 2 60 to 450/m Steel

Roof Layout Plan. Roof Plan A roof plan is commonly drawn to a scale of 1/8 inch per foot or 1/16 inch per foot. A roof plan shows the shape of the roof, as well as roofing materials, underlayment and location of vents. Roof Plan A roof framing plan shows size and direction of the

Vacuum Insulated Roofing System, used with an overlay of Alumasc PIR. Tapered Roofing The Alumasc VTherm Vacuum Insulated Roofing System can also be used in a tapered roofing scheme. Alumasc Roofing offers a supporting design service, which ensures that the most cost effective solution for a roof is identified, and that the end result is the

A low slope roof or flat roof has four parts such as roof deck, vapour retarder, insulation and roof membrane. The combination of these parts is known as roof assembly. 3.1 Roof Deck An entire roof system is held up by a roof deck. This is the base of roof assembly. Roo

the accounting profession - have come to be known as 'creative accounting'. (1988: 7-8) Terry Smith reports on his experience as an investment analyst: We felt that much of the apparent growth in profits which had occurred in the 1980s was the result of accounting sleight of band rather than genuine economic growth, and we set