Cost Estimating In DOE For Capital Asset Projects - Energy

1y ago
13 Views
1 Downloads
626.13 KB
20 Pages
Last View : 2d ago
Last Download : 3m ago
Upload by : Kaden Thurman
Transcription

Cost Estimating in DOE for Capital Asset Projects May 25-26th, 2011, New Orleans, LA Paul Bosco, PE, PMP, LEED-AP Director, Office of Engineering & Construction Management

Outline of Presentation Senior Level Concerns/Thoughts Project Success Recent Policy Changes Cost Estimating Framework Bosco’s Cost Estimating Thoughts and Pet Peeves 2

Project Management (PM) Process DOE’s Acquisition Management System Request PED Funds Independent Review to Validate PB Operating Funds PED Funds Initiation Definition EIR for Major System Projects Construction Funds Operating Funds Execution Closeout TPC Critical Decision CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range CD-2 Approve Performance Baseline (PB) CD-3 Approve Start of Construction or Execution CD-4 Approve Start of Operations or Project Completion Projects Report Earned Value 20M PARS II Reporting for Projects 10M ICR ICE/ICR ICE ICE, if warranted 3

Congressional Concerns No policy establishing estimating standards No policy for performing ICEs and ICRs Consolidate DOE’s cost estimating organization Perform ICE’s on “Program” before constructing smaller project components Design maturity standards too subjective Concerns (mostly) addressed in 413.3B 4

Deputy Secretary In His Own Words The authority and accountability for any project, including its costs, must be vested firmly in the hands of the federal project manager. (Appendix A, Section 1. ,Objective and Appendix C, Section 18., Reviews) Some cost estimate, or cost range, should be provided at each CD gateway, but the degrees of rigor and detail for a cost estimate should be carefully defined, depending on the degree of confidence in project scale and scope that is reasonable to expect at that stage. Whatever figure or range that is provided should explicitly note relevant caveats concerning uncertainties inherent in estimates at CD-0 and CD-1 stages. (Appendix A, Section 1., Objective and Appendix C, Section 18., Reviews) A project sponsor should never be the sole cost estimator, at any stage (i.e., from CD-0 on) given inherent conflict of interest. (Appendix A, Section 1., Objective and Appendix C, Section 18., Reviews) The second cost estimator should come from outside of the line manager’s chain of commend, to avoid conflict of interest. (Appendix A, Section 1., Objective and Appendix C, Section 18., Reviews) 5

Project Delivery: Objective vs. Project Success DOE O 413.3B: OBJECTIVE – Projects will be delivered within original CD-2 Performance Baseline (cost and schedule) and be fully capable of meeting mission and key performance parameters. PROJECT SUCCESS: (For “Capital Asset Projects”) – Project completed within the ORIGINAL approved scope baseline, and not to exceed 110% of the ORIGINAL approved cost baseline at project completion (CD-4), unless otherwise impacted by a directed change. Portfolio Success: – 90% of all projects meet project success criteria. 6

Primary Performance Metrics Project Success Based on 3-Year Rolling Timeline 95% 90% 85% 80% 75% 70% 65% 60% Pre-RCA Post-RCA All Projects Target FY2006-08 FY2007-09 FY2008-10 FY2009-11 FY2010-12 FY2010 Target FY2010 Actual FY2011 Target FY2011 Actual Capital Asset Construction Success 85% 72% 90% 84% (projected) Capital Asset Cleanup Success 70% 100% 80% 86% (projected) Certified EVMS by CD-3 – Construction 90% 97% 95% 97% (To Date) Certified EVMS by CD-3 – Cleanup 75% 86% 85% 85% (To Date) Certified FPDs at Right Level by CD-3 88% 89% 90% 79% (To Date) 7

Front-End Planning: Req’ts Definition (Accurate Cost Estimates Start Here) DOE O 413.3B requires: – Design sufficiently mature prior to Critical Decision (CD-2) – Enhanced External Independent Review (EIR) procedures for (projects 100M) Project Definition Rating Index, PDRI Technology Readiness Assessment and Maturation Plans GAO’s 12-step cost estimating process Storage (e.g., NonNuclear Waste) Storage (e.g., Nuclear Waste) Utilities & Infrastructure Research & Development (e.g., Applied Science Laboratory) Industrial Buildings (e.g., Nuclear Chemical Processing Facility) Administrative (e.g., Office Space) Conceptual Design Less 0% Design Maturity Scale 50% More 100% 8

Project Size and Structure (Focus on the Work at Hand – Reduce Time Horizon & Risk) DOE O 413.3B requires: – Decision to break up large projects made at CD-1; must be documented Independent Cost Estimate (ICE) and/or Cost Review (ICR) prior to CD-1 (for programs / projects 100M) – Acquisition Executive (AE) must determine that funding profile is affordable and executable within budget – Each small project must have its own distinct performance baseline (CD-2) Distinguished program and project management; most appropriate for environmental remediation work Useable segments for intended purpose reduce time, risk and span of control; better defined scope; and funding profiles that meet the mission need Multiple projects that collectively support one mission need; one project data sheet for construction projects for full cost visibility 9

Funding/Budgeting & Cost Estimating (Get Estimates Right – Stabilize Funding) DOE O 413.3B outlines cost estimating and budgetary requirements: – Full funding of projects 50M, if feasible (execution window 2 yrs) – Acquisition Executive: endorse changes to approved funding profile – Prior to CD-0 (Mission Need): OECM conduct ICR for major system projects ( 750M) – Prior to CD-1 (Alternative Selection and Cost Range): OECM prepare ICE and/or conduct ICR for projects 100M If top of approved CD-1 cost range exceeds 50%, must reassess alternatives – Prior to CD-2 (Performance Baseline): OECM prepare ICE for projects 100M – Prior to CD-3 (Start of Construction/Execution): OECM prepare ICE, if warranted or requested by AE, for projects 100M Leveraging experienced, certified cost estimators from industry to augment staff in conduct of ICRs/ICEs, as needed; Utilizing DOE historical costs, when possible 10

Management and Oversight (Constantly Monitor Cost / Schedule Performance) DOE O 413.3B requires: – Project Assessment and Reporting System (PARS II) enhanced Project performance data uploaded monthly directly into PARS II from contractor’s project management systems Monthly project status reporting by: – Federal Project Director (FPD) – Program Manager – OECM – OECM central repository and compliance office; retain all critical decision, baseline change documents, lessons learned Manage, Monitor and Report on the “Project Success” Metric – Project peer reviews – Exported “Best Practice” from Science – Earned Value Management System (EVMS) certification & surveillance reviews 11

GAO Cost Estimating and Assessment Guide – The “12-Steps” 1. Cost estimating (CE) purpose 2. Cost estimating plan 3. Define program characteristics 4. Determine estimating structure 5. Identify ground rules and assumptions 6. Obtain data 7. Develop point estimate; compare to ICE 8. Conduct sensitivity analysis 9. Conduct risk and uncertainty analysis 10. Document the estimate 11. Present estimate to management for approval 12. Update the estimate to reflect actual costs/changes 12

Association for the Advancement of Cost Engineering International (AACEI) Classifications 13

Project Management (PM) Process When To Do a Project ICE and/or ICR Request PED Funds Independent Review to Validate PB Operating Funds PED Funds Initiation Definition EIR for Major System Projects Construction Funds Operating Funds Execution Closeout TPC Critical Decision CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range CD-2 Approve Performance Baseline (PB) CD-3 Approve Start of Construction or Execution CD-4 Approve Start of Operations or Project Completion Projects Report Earned Value 20M PARS II Reporting for Projects 10M ICR ICE/ICR ICE ICE, if warranted 14

Project Management (PM) Process How About Cost Estimates in Support of Contract Actions? M&O WORK AUTHORIZATION CONTRACT D/B AWARD #1 CONTRACT D/B/B AWARD #2 Request PED Funds Independent Review to Validate PB Operating Funds PED Funds Initiation Definition CONTRACT MOD - BCP EIR for Major System Projects Construction Funds Operating Funds Execution Closeout TPC Critical Decision CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range CD-2 Approve Performance Baseline (PB) CD-3 Approve Start of Construction or Execution CD-4 Approve Start of Operations or Project Completion Projects Report Earned Value 20M PARS II Reporting for Projects 10M ICR ICE/ICR ICE ICE, if warranted 15

IGCE versus ICE? Independent Government Cost Estimate (IGCE) – Used to support contract negotiations FAR 36.203(a) - An independent Government estimate of construction costs shall be prepared and furnished to the contracting officer at the earliest practicable time for each proposed contract and for each contract modification anticipated to exceed the simplified acquisition threshold. The estimate shall be prepared in as much detail as though the Government were competing for award. Project Independent Cost Estimate (ICE) – Used to support Congressional budget request 16

Baseline Confusion:PMB or PB(TPC)? What’s the Baseline? CD-0, CD-1 or CD-2? TPC EAC Contingency & DOE ODCs CONTRACT AWARD CP MR & Fee BAC PMB VAC SV CV AC or ACWP PV or BCWS EV or BCWP time current time planned estimated completion completion date date 17

“Precision without Accuracy” CD-0 & CD-1 estimate ranges Cost Range examples – CD-0 4.1B - 5.6B (20 years) 502 - 552.7M (16 years) 92.8 - 102.4M (8 years) – CD-1 375M - 400M (14 years) 67M - 73.2M (6 years) Class 5 Range (give (mostly) or take) Low Range -20% to -50% High Range 30% to 100% 18

Contingency versus Management Reserve Contingency: Who owns it? – For Government directed scope addition or requirement change – Added to contract via Federal change control process – Outside of contract scope and risks Management Reserve: Who controls it? – Determined by the Contractor – For estimate uncertainties and risk events w/in contract scope – Maintained by Contractor and incorporated into PMB via Contractor’s change control process 19

Final Thoughts/Comments “Should Cost” and Art over Science 20

GAO Cost Estimating and Assessment Guide -The "12-Steps" 1. Cost estimating (CE) purpose 2. Cost estimating plan 3. Define program characteristics 4. Determine estimating structure 5. Identify ground rules and assumptions 6. Obtain data 7. Develop point estimate; compare to ICE 8. Conduct sensitivity analysis 9. Conduct risk and .

Related Documents:

Bruksanvisning för bilstereo . Bruksanvisning for bilstereo . Instrukcja obsługi samochodowego odtwarzacza stereo . Operating Instructions for Car Stereo . 610-104 . SV . Bruksanvisning i original

Section 3, Cost Estimating Methods, discusses historical, conceptual, risk-based, and cost-based estimating methods and estimating software. Section 4, Cost Estimating Factors, discusses cost drivers and the impact that each has on the construction cost estimate throughout the project development process.

Electrical Construction Estimating Introduction to Electrical Construction Estimating Estimating activites will use the North State Electric estimating procedures. Estimating and the Estimator Estimating is the science and the art by which a person or organization determines in advance of t

10 tips och tricks för att lyckas med ert sap-projekt 20 SAPSANYTT 2/2015 De flesta projektledare känner säkert till Cobb’s paradox. Martin Cobb verkade som CIO för sekretariatet för Treasury Board of Canada 1995 då han ställde frågan

service i Norge och Finland drivs inom ramen för ett enskilt företag (NRK. 1 och Yleisradio), fin ns det i Sverige tre: Ett för tv (Sveriges Television , SVT ), ett för radio (Sveriges Radio , SR ) och ett för utbildnings program (Sveriges Utbildningsradio, UR, vilket till följd av sin begränsade storlek inte återfinns bland de 25 största

Hotell För hotell anges de tre klasserna A/B, C och D. Det betyder att den "normala" standarden C är acceptabel men att motiven för en högre standard är starka. Ljudklass C motsvarar de tidigare normkraven för hotell, ljudklass A/B motsvarar kraven för moderna hotell med hög standard och ljudklass D kan användas vid

LÄS NOGGRANT FÖLJANDE VILLKOR FÖR APPLE DEVELOPER PROGRAM LICENCE . Apple Developer Program License Agreement Syfte Du vill använda Apple-mjukvara (enligt definitionen nedan) för att utveckla en eller flera Applikationer (enligt definitionen nedan) för Apple-märkta produkter. . Applikationer som utvecklas för iOS-produkter, Apple .

API RP 500 and API RP 505 NFPA 497 and NFPA 499. PETRONAS Technical Standards provides guidelines to ensure proper management of Ex Equipment. 1. Ex Electrical Equipment Inspection and Maintenance Guidelines (Ex IMG) Standards and Guidelines Personnel Inspection Maintenance 2. Ex Equipment Repair Guidelines (Ex ERG) 3. Ex Management Assessment Guidelines (Ex MAG) 4. Ex .