Engineering Scale Design And Testing Of Transformational Membrane .

7m ago
2 Views
1 Downloads
2.61 MB
25 Pages
Last View : 1m ago
Last Download : 3m ago
Upload by : Louie Bolen
Transcription

DE-FE0031946 Engineering Scale Design and Testing of Transformational Membrane Technology for CO2 Capture Shiguang Li,1 Yang Han,2 Winston Ho,2 Travis Pyrzynski,1 Weiwei Xu,1 Mark Stevens,1 Douglas Heim,1 Howard Meyer,1 Andrew Sexton,3 and Will Morris 4 1: GTI Energy, 2: The Ohio State University (OSU) 3. Trimeric Corporation (Trimeric), 4. Wyoming Integrated Test Center (ITC) U.S. Department of Energy National Energy Technology Laboratory Carbon Management Project Review Meeting August 15 – 19, 2022

Project Overview Performance period: October 1, 2020 – July 31, 2025 Total funding: 16.25 MM (DOE: 13 MM, Cost share: 3.25 MM ) Objectives: 1) Design and build an engineering-scale CO2 capture system using OSU’s transformational membrane in commercial-sized modules; 2) Conduct tests on coal flue gas at ITC and demonstrate a continuous, steady-state operation for a minimum of two months; and 3) Gather data necessary for further process scale-up Goal: Achieve DOE’s Transformational Carbon Capture performance goal of CO2 capture with 95% CO2 purity at a cost of 30/tonne of CO2 captured and at a cost of electricity (COE) at least 30% less than baseline CO2 capture approaches by 2030 Team: Member Roles Project management and planning Skid design, selection of skid fabricator, skid installation, and testing Support TEA and EH&S assessment Participate in project management and planning Membrane and module fabrication and QA/QC testing Support skid design and field testing, TEA and EH&S study Site host, lead on testing site preparation TEA and EH&S assessment 2

Testing on Coal Flue Gas at Wyoming Integrated Test Center Component Pressure (psig) Temperature ( C) Minimum Maximum Average 0.36 0.54 0.45 80 90 85 Gas composition (volume) CO2 12.0% 13.1% 12.7% O2 1.7% 4.2% 2.5% N2 Ar 66.7% 66.7% 66.7% H2O 15.2% 18.3% 18.1% Contaminant levels (volume) SO2 0.0 ppm 114.9 ppm 23.1 ppm NOx 19.2 ppm 38.4 ppm 27.8 ppm 3

Process Description ITC and Dry Fork Facilities OSU & GTI Skid Boundary 4

Roadmap Task 1 – Project management and planning (throughout the project) Engineering skid design, construction, installation, testing and TEA BP1 10/1/20-10/31/22 Task 3 – Design and Costing of the Skid, and Manufacturer Selection Commercial-sized membrane module fabrication Task 2 – Fabrication and Testing of Prototype Membrane and Modules Task 4 – Detailed Engineering Design of the Skid Task 5 – Procurement and Construction of Skid BP2 11/1/22-1/31/24 Task 7 – Testing Site Preparation Task 8 – Skid Installation at Testing Site Task 6 – Membrane Module Fabrication and QA/QC Testing Task 9 – Skid Commissioning BP3 2/1/24-7/31/25 Task 10 – Parametric Testing Task 11 – Continuous Steady-State Operation Task 13 – Removal of the Skid from Testing Site Task 12 – Identification of Commercial Membrane Manufacturer 5

OSU Membrane Structure and Transport Mechanism Simplicity of membrane for low cost: thin selective amine polymer layer on polymer support High-selectivity due to facilitated transport mechanism Membrane Feed Side Selective amine polymer layer (170 nm, dense layer) Permeate Side Facilitated Transport Mobile CO2 CO2 Carrier Polymer support ( 30 μm, Ø 40 nm) Nonwoven fabric backing ( 120 μm) CO2 CO2 CO2 CO2 Mobile Carrier Mobile Carrier CO2 CO2 Mobile Carrier Non-Reacting Gas: N2 3 Physical Solution-Diffusion N2 6

OSU Funding History and Progression of Module Scaleup 100 Membrane area (m2) 10 OER-CDO-D-15-09 DE-FE0031731 1 2nd NCCC test DE-FE0007632 0.1 1st NCCC test DE-FE0026919 0.01 1 10/1/14 2 10/1/15 3 10/1/16 4 10/1/17 Time frame 5 10/1/18 6 10/1/19 7 10/1/20 7

OSU Progression of Membrane Performance 8

Task 2 progress Continuous Fabrication of Polymer Support Non-woven fabric Casting knife N2 Rewind roller of polymer support N2 Humidity enclosure Vapor 21″ Coagulation bath Pneumatic solution vessel 1,500 ft of quality support has been prepared; 100% of BP1 commitment 9

Bicontinuous Polymer Support Fabricated TFC† on bicontinuous support TFC on ideal support 20% surface porosity; 130,000 GPU§ CO2 permeance §1 GPU 10–6 cm3(STP) cm–2 s–1 cmHg–1 † TFC thin-film composite 10

Continuous Fabrication of Transformational Membrane Coating knife 21″ 1,400 ft of prototype membrane has been prepared; 100% of BP1 commitment 11

High CO2/N2 Separation Performance Achieved/Confirmed Cross-sectional SEM image 12

Commercial-Size 8-inch Diameter Spiral-Wound (SW) Membrane Elements/Modules Fabricated Configuration of SW element 20″ 8″ 14″ DE-FE0026919 DE-FE0031946 Individual SW element ( 8″ and 35 m2) 4″ 3 SW elements have been prepared; 50% of BP1 commitment 13

Individual SW Element QA/QC: Good Quality Confirmed Simulated flue gas 20.0% CO2, 48.4% N2, 15.0% O2, 16.6% H2O, 3 ppm SO2, and 3 ppm NO2 at 77 C 14

Task 1.3 progress Initial TEA Basis Two Cases: Two stage (90% capture): for comparison to DOE reference cases Single stage (70% capture): believed to be most economical process configuration Membrane Performance: Operating temperature: 77 C Impurity tolerance: 3 ppmv SO2, 4 ppmv NO2 CO2 permeance: 3,500 GPU CO2/N2 selectivity: 167 Product: CO2 Purity 95 vol%, O2 10 ppmv 15

Cost of Electricity and Cost of CO2 Capture Unit Case B12A (no CO2 capture) Case B12B (90% capture) COE mills/kWh 64.4 105.2 100.5 89.1 Incremental Cost of CO2 Capture mills/kWh - 40.8 36.1 24.7 % - 63.4% 56.1% 38.4% 30% /tonne - 45.63 40.32 38.62 30 Increase in COE vs. Case B12A Cost of CO2 Capture Two Stage Single Stage DOE Membrane Membrane Goal (90% capture) (70% capture) Inlet flue gas compression is the largest capital cost center Membranes are less than 10% of the total purchased equipment costs 16

Sensitivity Study: Costs Can Potentially Decrease to 36.38 (90% Removal) and 33.61 (70% Removal) /tonne of CO2 Captured Sensitivities: 1) direct contact cooler (DCC) removal, 2) turboexpander cost reduction, and 3) flue gas compressor cost reduction 17

Task 3 progress Initial Design Completed, Bid Package Issued, Bids Received, Selection of Skid Fabricator in Work Generate initial design package Task 3 PFD, P&ID drawings w/ process description Equipment, sizing and data sheets Instrumentation and data sheets Data acquisition requirements Power and controls engineering Plant electricity, heat, and water consumption Waste generation and management Flue gas inlet and outlet conditions Start-up, steady-state operation, and shutdown procedures HAZOP review and recommendations Finalize package and send to bidders Review bids and select skid fabricator Task 4 BP2 Detailed engineering design of the skid Skid construction and acceptance testing Evaluation criteria: Project costs and clarifications Project schedule and ability to manage Ability to provide expected deliverables Project team, experience, references Approach to quality control 18

Risk Assessment: Challenges and Mitigation Strategies Technical Challenges/Risks 2) 95% CO2 purity not achieved Mitigation: 2a: Adjust pressure, temperature, flow rate conditions 3) CO2 capture cost not in line with the expected outcome Mitigation: 3a: Optimize process design 3b: Optimize equipment selection Risk summary 5 4 Likelihood 1) Corrosion or particulates fouling of membrane equipment Mitigation: 1a: Select materials of construction based on lessons learned from GTI’s previous engineering scale project 1b: Modify process conditions and add pre-treatments 3 1 3 2 3a 2 1a 1 1b 1 3b 2a 2 3 4 5 Consequence 19

Technology Development Path / Future Plan Duration 3–4 500 h TRL Duration 5 500 h Duration 6 1,500 h TRL Duration TRL Duration 7 Months 8–9 Years Scale TRL TRL Potential licensing partner Potential licensing partner Site (TBD) Testing site (TBD) Small bench scale 2016 2018 Integrated bench scale 2020 2022 Current engineering scale 2024 Future 10 MWe large pilot scale 2026 2028 Future 100 MWe demonstration 2030 2032 2034 Year 20

Summary 1,400 ft of the prototype membrane fabricated, which is 100% of the total amount for BP1 Prototype membrane exhibited CO2 permeance of 3,500 GPU and a CO 2/N2 selectivity of 160 at 77 C, which was consistent with the OSU Gen II membrane performance obtained previously Initial EH&S and TEA Topical Reports submitted to DOE in 2021 90% CO2 removal: 40.32/tonne of CO2 captured (12% reduction vs. B12B) 70% CO2 capture: 38.62/tonne of CO2 captured (15% reduction vs. B12B) Cost has potential to be further decreased to 33.61 (70% removal) /tonne of CO 2 captured Initial design package completed; selection of skid fabricator ongoing 21

Acknowledgements Financial and technical support DE-FE0031946 DOE: Andrew O'Palko, Andy Aurelio, Dan Hancu, José Figueroa and Lynn Brickett Partners 22

Appendix – Project Organization and Structure 23

Appendix – Gantt Chart 24

Disclaimer This presentation was prepared by GTI Energy and OSU as an account of work sponsored by an agency of the United States Government. Neither GTI Energy, OSU, the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors herein do not necessarily state or reflect those of the United States Government or any agency thereof. 25

Detailed engineering design of the skid Skid construction and acceptance testing Review bids and select skid fabricator Task 3 Task 4 BP2 Initial Design Completed, Bid Package Issued, Bids Received, Selection of Skid Fabricator in Work Task 3 progress 18 Evaluation criteria: Project costs and clarifications Project schedule and ability to manage

Related Documents:

CCC-466/SCALE 3 in 1985 CCC-725/SCALE 5 in 2004 CCC-545/SCALE 4.0 in 1990 CCC-732/SCALE 5.1 in 2006 SCALE 4.1 in 1992 CCC-750/SCALE 6.0 in 2009 SCALE 4.2 in 1994 CCC-785/SCALE 6.1 in 2011 SCALE 4.3 in 1995 CCC-834/SCALE 6.2 in 2016 The SCALE team is thankful for 40 years of sustaining support from NRC

Svstem Amounts of AaCl Treated Location Scale ratio Lab Scale B en&-Scale 28.64 grams 860 grams B-241 B-161 1 30 Pilot-Plant 12500 grams MWMF 435 Table 2 indicates that scale up ratios 30 from lab-scale to bench scale and 14.5 from bench scale to MWMW pilot scale. A successful operation of the bench scale unit would provide important design .

Materials Science and Engineering, Mechanical Engineering, Production Engineering, Chemical Engineering, Textile Engineering, Nuclear Engineering, Electrical Engineering, Civil Engineering, other related Engineering discipline Energy Resources Engineering (ERE) The students’ academic background should be: Mechanical Power Engineering, Energy .

HOW A POERFUL E-COMMERCE TESTING STRATEGY 7 HITEPAPER 4.3 Obtaining Strong Non-Functional Testing Parameters Retailers also need to focus on end-user testing and compatibility testing along with other non-functional testing methods. Performance testing, security testing, and multi-load testing are some vital parameters that need to be checked.

EN 571-1, Non-destructive testing - Penetrant testing - Part 1: General principles. EN 10204, Metallic products - Types of inspection documents. prEN ISO 3059, Non-destructive testing - Penetrant testing and magnetic particle testing - Viewing conditions. EN ISO 3452-3, Non-destructive testing - Penetrant testing - Part 3: Reference test blocks.

Assessment, Penetration Testing, Vulnerability Assessment, and Which Option is Ideal to Practice? Types of Penetration Testing: Types of Pen Testing, Black Box Penetration Testing. White Box Penetration Testing, Grey Box Penetration Testing, Areas of Penetration Testing. Penetration Testing Tools, Limitations of Penetration Testing, Conclusion.

Scale Review - Review the E - flat scale. Friday 5/29/2020. Scale Review - Review the c minor scale. Sight Reading. Monday 6/1/2020. History - Read 20th Century Packet - Complete listenings and quiz. Scale Review - Practice the B - flat Major scale. Tuesday 6/2/2020. Scale Review - Practice the g melodic minor scale. Wednes

Remember, this is just an abridged form of the major scale. It's not a 'separate', distinct scale. It's just the major scale, in a simpler form. Can you see that this has just a few notes less? Minor Scale Minor Pentatonic Scale Remember, this is just an abridged form of the minor scale. It's not a 'separate', distinct scale.