SR 53 Westbound atChattahoochee RiverBridge ReplacementDesign-Build Industry ForumDecember 6, 2018Andrew Hoenig, PE, DB Program ManagerRichard O’Hara, DB Project Manager

Disclaimer StatementAt this meeting, the Department is providinginformation about the project’s delivery goals,anticipated scope, anticipated Design-Buildprocurement process, and potential risks.Participants are encouraged to ask questions duringthis meeting; however, any information providedby the Department is considered informationalonly and subject to change.

Agenda Design-Build Overview Schedule Project Overview Design-Build Procurement Open Discussion

Design-Build OverviewDesign-Build Combines preconstruction related services withconstruction services into one contract. Allows the contractor to participate in the project’sdesign in an effort to improve communications,expedite project delivery, and reduce costs.Governed by: 23 Code of Federal Regulations (CFR) Part 636 Georgia Code Section 32-2-81 (Enacted 2004) Board Rules, Chapter 672-18 (Adopted 2006 &2013)

Innovative DeliveryAmount Obligated to Design-Build Contracts

Upcoming Design-Build OpportunitiesProjectPI NumberSR 135 @ Altamaha River - TIA0007037SR 247/ Pio Nono & College St bridges0014895over Norfolk Southern Railroad0014899SR 53 WB @ Chattahoochee River0010212SR 25 at Savannah River (Houlihan Bridge)0013741and SR 25 at Middle River0013742I-16 @ SR 307Diverging Diamond InterchangeCountyJeff DavisMontgomeryAnticipated SelectionMethodTwo Phase Low BidLetting5/17/2019BibbBest Value7/12/2019HallTwo Phase Low BidChathamTBD0013727ChathamTBDTBDI-985 From I-85/Gwinnett to SR 53/Hall0014130Gwinnett HallTBDTBDI-85 Widening SR 211 to SR 11/US 1290013545Barrow JacksonBest ValueSummer 20247/19/2019AnticipatedFY d

DB Procurement DocumentsUpdatesRFQ Updated for clarityPass/Fail requirements remainRFP Updated for clarity, consistency & continuousimprovementDesign-Build Contract Template Published OnlineCombining Volumes 2 & 3 into single volumeUpdating Design-Build Manual Attachments

Tentative Schedulea. GDOT issues Public Notice Advertisement (PNA)11/02/2018----------b. Industry Forum – GDOT Room 402-40412/06/201810:30 A.M.c. Industry one-on-one meetings – GDOT Room 408/40912/06/20182:00 P.M. 5:00 P.M.d. GDOT issues Request for Qualifications (RFQ)2/08/2019-----------e. Deadline for Statement of Qualifications (SOQ)03/11/201911:00 A.M.f.04/05/2019-----------g. GDOT issues Request for Proposals (RFP) to the Finalists04/19/2019-----------h. Receipt of Technical Proposals and Price Proposals fromFinalists07/12/201911:00 A.M.i.7/19/201911:00 A.M.GDOT issues the Notice to FinalistsGDOT letting

SR 53 at Chattahoochee RiverProject SpecificsDecember 6, 2018Rick O’Hara, DB Project Manager

Project Overview Design-Build Delivery (2-Phase Low Bid) Maintain existing traffic during construction Construction is within existing or GDOT-obtained Right-ofWay DBE Goal for the Project is 11% (8% if prime self-performsconcrete) The bridge crosses Lake Lanier, an Army Corps of Engineerreservoir, in deep water.

SR 53 at Chattahoochee River Project Location

Existing BridgesWestbound Bridge(replace)Eastbound Bridge(to remain)Year Constructed1956n/aNumber of ��2n/aLane Width12’n/aShoulder Width1’n/aSpan LengthsNumber of LanesClearance between existingand proposed WB bridgesClearance between existingWB and EB bridges10’-0”44'

Proposed Bridge Typical SectionLooking East on SR 53

Anticipated Area Classes for Lead DesignConsultant3.01Two-Lane or Multi-lane Rural Roadway Design- OR 4.02Major Bridge Design

Anticipated Area Classes for DB EPAHistoryAir QualityNoiseEcologyArchaeologyFreshwater Aquatic SurveysBat SurveysAttitude, Opinion, and Community Value Studies (Public Involvement)Traffic AnalysisTwo-Lane or Multi-Lane Rural Roadway DesignTwo-Lane or Multi-Lane Urban Roadway DesignUtility CoordinationHydraulic and Hydrological Studies (Roadway)Major Bridge DesignHydraulic and Hydrological Studies (Bridges)Land SurveyingEngineering SurveyingGeodetic SurveyingOverhead/Subsurface Utility Engineering (SUE)Soil Survey StudiesGeological and Geophysical StudiesBridge Foundation StudiesHydraulic and Hydrological Studies (Soils and Foundation)Hazardous Waste Site Assessment StudiesErosion, Sedimentation, and Pollution Control PlanField Inspections for Erosion Control

Risks and Mitigation StrategiesRiskMitigations for RFPGeotechnical Provide existing BFI’s, Soil Survey, and Geotechnicalboring logs/samplesSurvey Database Provide Survey database Environmental-related scope items and anticipatedreview/approval durationsEnvironmental Anticipated in-water work durations Coordination with the USACE and DNRDesign Exception/ None anticipatedDesign Variance

Risks and Mitigation StrategiesRiskHydraulicsMitigations for RFP Perform hydraulics screening H&H Technical memoLocal Outreach Early and ongoing coordination with stakeholdersCost Estimate Continue to monitor industry trendsOverall ContractDuration Establish reasonable durations per contract in order tocomplete all of the Work SUE QL-DUtilities Early coordination with utility owners Executed MOUs

Environmental Concerns Deep Water Crossing (approx. 90 feet deep) Recreational AreaLake Lanier Recreational and Reservoir Resource. Ecology ResourcesSpecies included in SP 107.23H: Northern long-earedbat and the Indiana bat. Permits – Georgia and federal requirements

Design-Build TeamRoles and Responsibilities Bridge and Roadway designSchedule development/managementGeotechnical reportsStream buffer variance applications (if needed)Permit and mitigation costsMaintain traffic, traffic control, and constructionsignage Utility coordination and relocation (if needed) Complete project within a defined timeline

GDOTRoles and Responsibilities Submittal review Environmental Special Studies/NEPA preparationand approval Construction Oversight/CEI Material Testing will be provided by OMAT CEI performed by OID/ATKINS

Anticipated Procurement ProcessTwo Phase Low BidPhase I - Request for Qualifications (RFQ) Georgia Procurement Registry (GPR) Restriction on communications Qualified Proposers meeting the Pass/Failrequirements will advance to Phase IIPhase II - Request for Proposals (RFP) GDOT DB SharePoint Site Administrative, Technical and Price Proposals GDOT awards to the lowest responsive bid

Required Information – RFQ Phase (1/3) Organization chart Lead Contractor/Lead Design Consultant basic companyinformation Lead Contractor Certificate of Qualifications Matrix listing GDOT Prequalified Area Classes– Include prequalification Notice of Professional ConsultantQualifications

Required Information – RFQ Phase (2/3) Exhibit I– Certification Form for Lead Design Consultant Exhibit II– GA Security and Immigration Compliance Act Affidavit for LeadContractor Exhibit II– GA Security and Immigration Compliance Act Affidavit for LeadDesign Consultant Statement(s) regarding removal / failure to complete anassigned contract Statements of Disclosure (Conflict of Interest) Signed Amendment(s) acknowledgement

Required Information – RFQ Phase (3/3) Key Personnel experience and qualifications (resume)– ten (10) years Industry experience for each Key Personnelposition and should include at least three (3) years of experiencein the same or similar role for projects of similar size andcomplexity– relevant experience in the applicable proposed role for projects ofsimilar complexity, size, scope, delivery method and function Lead Contractor experience and qualifications– at least three (3) construction projects delivered using DesignBuild and/or conventional Design-Bid-Build contracting whichdemonstrate the Lead Contractor’s qualifications Lead Design Consultant experience and qualifications– at least three (3) design projects delivered using Design-Buildand/or conventional Design-Bid-Build contracting thatdemonstrate the Lead Design Consultant’s qualifications

Anticipated Procurement ProcessPhase II - Request for Proposals (RFP) April 19, 2019 – Issue RFPo Posted on GDOT DB SharePoint siteo Includes Reference Information Documents (RIDs)o Submit questions to OID Contracting Officer Administrative, Technical and Price Proposalso Due to GDOT by July 12, 2019o Price Proposal in separate packageo GDOT evaluates Administrative and TechnicalProposals on a pass/fail basiso Price Proposals to be opened on July 19, 2019

Questions?During project procurement, all proposer questions shall besubmitted to the Department via OT Design-Build uildGDOT Design-Build SharePoint ult.aspx

Consultant 3.01 Two-Lane or Multi-lane Rural Roadway Design-OR - . – GA Security and Immigration Compliance Act Affidavit for Lead Contractor . Key Personnel experience and qualifications (resume) –

Related Documents:

Westbound Loop 101 Eastbound Loop 101: Bell Rd : Union Hills Dr : Percent of Time Congested on Loop 101 (2015) Milepost: SR-51 I-17 : Time Time : Percent of Time Congested : 10: LOOP: 1: Westbound Loop 101 HOV Eastbound Loop 101 HOV: Bell Rd : Union Hills Dr : No HOV Data .

Chattahoochee Technical College recognized 19 students for their academic, character and leadership skills. The students, who are studying programs in from all areas of the college, were inducted into Chattahoochee Technical College's chapter of the National Technical Honor Society.

Chattahoochee Technical College is a Unit of the Technical College System of Georgia. It is comprised of eight campuses that serve a six-county area in North Georgia: Bartow, Cherokee, Cobb, Gilmer, . The Intensive English Program is offered at the Marietta Campus. Chattahoochee Technical College 980 South Cobb Drive, Marietta GA 30060

Avoiding stairs Tube guide map indexAvoiding stairs Tube guide map index C8 Abbey Road Lift access between street and platform D2 Acton Town ()µ Lift access between street and platform D7 Aldgate East No stair-free entrance/exit Level (same platform) interchange between westbound District line and westbound Hammersmith & City line.

Queensboro Bridge Bus Priority Study Local Bus Routes N * Estimated ridership volume Average Weekday Route Daily Q60 (Eastbound) 1,430 Q60 (Westbound)* 1,280 Q60 (Total) 2,710 Q101 (Eastbound) 450 Q101 (Westbound)* 400 Q101 (Total) 850 Q32 (Eastbound)

Dallas Co. 911 Dallas Co. Sheriff WestComm 911 Polk Co. 911 Polk Co. Sheriff Iowa State Patrol Iowa DOT TMC Iowa DOT Maintenance FREEWAY DIVERSION Dallas Exit 121 (Jordan Creek I-80 Westbound From: Exit 122 (60th Street) To: Pkwy) Plan 6108 1/7. 5/3/2017 Critical Locations to Monitor Affected Stakeholders

Dallas I-80 Westbound From: Exit 118 (Grand Prairie) To: Exit 117 (R22) Plan 2720 5A/7 STAKEHOLDER CONTACTS Stakeholder Responsibilities Dallas County 911 Communications Center 515-993-4567 Coordinate with the incident commander as to whether a diversion route is needed and which one should be implemented.

Contents—Continued E. Command Language Program, page 37 F. Guidelines for a Successful Command Language Program, page 39 G. Training Resources, page 41 Table List Table 2–1: Language proficiency indicator, page 2 Table 6–1: Foreign language proficiency bonus payment levels, page 15 Table 6–2: Department of the Army Civilian foreign language proficiency pay payment table, page 18